Project Name Pinto Island Yard Elevation Raising
Project No. 11681 Task No. 1
To: Prospective Bidders
Date:
Please procure the following and deliver to the address below:
Delivery of Proposal
Alabama Port Authority
250 N. Water Street
Mobile, AL 36602
Delivery of Work
Alabama Port Authority
910 Dunlap Drive
Mobile, AL 36602
DESCRIPTION OF WORK
July 2026
This Requisition solicits proposals for excavation of existing soils from the terminal dock to be placed in
low spots in the rear of the yard at locations specified by Terminal staff. Additionally, the Contractor will
be required to place and compact ALDOT No. 610 Stone in the excavated area to provide a suitable
driving surface for Terminal operations at the Pinto Island Steel Terminal for the Alabama Port Authority
(APA). Work will be in accordance with the requirements stated herein, attached insurance
requirements, all referenced documents, and applicable State of Alabama Laws.
The work consists principally of providing bonds, labor, materials, equipment, insurance, and
supervision necessary for the specified work designated within this proposal. The project site is located
at 910 Dunlap Drive in Mobile, Alabama 36602.
All Contractors submitting bids are to carefully examine the site of the proposed work by appointment
only and thoroughly review the contract requirements prior to submission of a bid proposal. Each
Bidder shall satisfy oneself as to the character, quality, and quantities of work to be performed, and as
to the requirements of the proposed contract. The submission of a proposal shall be proof that the
bidding Contractor has made such examination and is satisfied as to the conditions to be encountered in
performing the work and as to the requirements of the proposed Contract. All bidding Contractors must
hold the proper license from the State Licensing Board for General Contractors, Montgomery, Alabama.
The license classification shall be HS (Highways and Streets), MU (Municipal and Utility), or H/RR (Heavy
and Railroad).
A NON-MANDATORY pre-bid meeting is scheduled for Thursday, August 6, 2026, at 10:00 a.m. The
meeting location will be at the work site on Dunlap Drive at the Pinto Island Steel Terminal. Any
prospective bidders needing directions should call the project manager a minimum of 24 hours in
advance of the meeting.
The work performed under this contract shall not commence until the Contractor has submitted a
Performance Bond, Labor & Material Bond, and Certificate of Insurance. Performance Bond shall be in
an amount equal to 100% of the contract price; Labor & Material Bond equal to 100% of the contract
price; and Certificate of Insurance shall be as per the attached requirements and countersigned by a
licensed resident agent in the State of Alabama. The work performed under this contract shall not
commence until the Contractor has submitted bonds and insurance in an acceptable form.
Form ENG-FR-003 R&P
Last Revised 3/4/10
1|Page
Alabama Port Authority
Requisition and Proposal
Project Name Pinto Island Yard Elevation Raising
Project No. 11681 Task No. 1
The Contractor will be required to complete the work under the Contract within thirty (30) calendar
days after receipt of a “Notice to Proceed”. The work will have to be scheduled and performed in a
manner that will not interfere with the operations of the facility ongoing in the immediate and adjacent
areas. Work will start no later than ten (10) calendar days after receipt of notice to proceed. APA intent
is that work hours will be during normal daylight hours. The contractor will be required to submit a
detailed schedule within 10 days of the “Notice to Proceed” and before work begins.
The Contractor shall comply with all Federal and State laws, local ordinances and regulations, and all
orders and decrees of bodies or tribunals having any jurisdiction or authority, which in any manner
affect those engaged or employed on the work, or which in any way affect the conduct of the work.
The Contractor shall place a competent superintendent on the Project who shall have experience in the
work being performed under the Contract. The assigned superintendent shall have the responsibility for
the day-to-day operations of the work and shall remain on the Project site while the work under the
Contract is being performed.
Time is an essential element in the contract. As the prosecution of the work will inconvenience the
owner and interfere with business, it is important that the work be pressed vigorously to completion.
Also, the cost to the Alabama Port Authority of the administration of the contract, supervision,
inspection and engineering will be increased as the time occupied in the work is lengthened. Therefore,
exclusive of Sundays and national holidays, for each day that the work remains incomplete after the
time specified, an amount of $300.00 shall be paid by the contractor to the Alabama Port Authority as
liquidated damages for the loss sustained by the State because of failure of the contractor to complete
the work within the specified time.
IMPORTANT NOTICE TO BIDDERS REGARDING EMPLOYMENT PRACTICES: Effective October 1, 2011,
the Beason-Hammon Alabama Taxpayer and Citizen Protection Act (“the Act”) requires that any
business entity contracting with or providing any grant or incentives to the state, including the Alabama
Port Authority, certify compliance with the Act. All Bidders must certify such compliance by executing
the enclosed “Certificate of Compliance” and returning it to the Alabama Port Authority with your bid
package. In addition, the bidding company shall submit with their bid evidence that the company is
enrolled in the E-Verify system. The following E-Verify website link is provided for convenience:
http://www.dhs.gov/files/programs/gc_1185221678150.shtm.
IMPORTANT NOTICE TO BIDDERS REGARDING ACCESS TO APA RESTRICTED FACILITIES:
The Alabama Port Authority’s Access Policy is provided on the APA website and in the links below:
https://www.alports.com/port-access/
ALL persons working on this project are REQUIRED to have valid access credentials to include: 1) A TWIC
Card, 2) APA Badge, and 3) APA Vehicle Decal.
Form ENG-FR-003 R&P
Last Revised 3/4/10
2|Page
Alabama Port Authority
Requisition and Proposal
Project Name Pinto Island Yard Elevation Raising
Project No. 11681 Task No. 1
CONTRACTOR’S PROPOSAL
The Contractor hereby agrees to provide specified equipment and perform the specified work for the
prices outlined in the following schedule. The quantities listed may be increased or decreased to the
actual installed amount after construction. In the event the quantities do change, the unit price shall
apply according to scope of work.
BASE BID
Item No.
Description
1
Mobilization
2
Excavation and placement
of Existing Soils
3
Installation of Class 1
Geotextile Fabric
4
Placement of ALDOT No.
610 Stone
Unit
Lump Sum
Lump Sum
Lump Sum
Tons
Quantity Unit Price
Value
Lump Sum Lump Sum $__________
Lump Sum Lump Sum $__________
Lump Sum Lump Sum $__________
790 $______/TN $__________
Total Base Bid
$
Total Base Bid in Words:
_____________________________________________________________________________________
_____________________________________________________________________________________
NOTES:
1. Sealed bid proposals will be received via courier to the Alabama Port Authority, 1400 Alabama State
Docks Blvd, Room 216, Administration Building, Mobile, AL 36602 by 11:00 A.M. on Friday, August 14,
2026. Sealed bid proposals can also be hand delivered from 11:45 A.M. to 12:00 P.M. on Friday,
August 14, 2026, to the Alabama Port Authority in the International Trade Center building, 250 North
Water Street, 1st floor – Killian Room, Mobile, AL. The official bid opening will be conducted in the
Killian Room at 1:00 P.M. on Friday, August 14, 2026. No faxed or electronic bids will be accepted.
Sealed bids shall have the bidder’s name, contractor’s license number, project name, and time and
date of bid opening shown on the outside.
2. A Bid Bond or Certified Check made payable to the Alabama Port Authority and equal to five (5%)
percent of the amount bid, not to exceed $10,000, must accompany the Bid Proposal.
3. Authority reserves the right to refuse to issue a proposal form or a contract to a prospective bidder for
any of the following reasons:
a) Failure to pay, or satisfactorily settle, all bills due for labor and materials on former contract in
force with the Authority.
b) Contractor default under previous Contract with the Authority.
c) Proposal withdrawal or Bid Bond forfeiture on previous project with the Authority.
d) Unsatisfactory work on previous contract with the Authority.
Form ENG-FR-003 R&P
Last Revised 3/4/10
3|Page
Alabama Port Authority
Requisition and Proposal
Project Name Pinto Island Yard Elevation Raising
Project No. 11681 Task No. 1
NOTES (CONTINUED):
4. Authority may make such investigations as deemed necessary to determine the ability of the bidder to
perform the work, and the bidder shall furnish all such information and data for this purpose as the
Authority may request. The Authority reserves the right to reject any bid if the evidence submitted
by, or investigation of, such bidder fails to satisfy the Authority that such bidder is
properly qualified to carry out the obligations of the Contract.
5. Any questions regarding the procurement should be directed to Sean Kelly, Project Manager, via email
at sean.kelly@alports.com.
6. The right is reserved, as the interest of the Alabama Port Authority may require, to reject any and all
bids and to waive informalities in bids received.
7. The Alabama Port Authority will utilize its sales tax exemption status on this project.
SIGNATURES
Receipt of following addendums is acknowledged:
Addendum No. _________________
Addendum No. _________________
Addendum No. _________________
REFERENCED/ATTACHED DOCUMENTS
It is the sole responsibility of the prospective bidder to verify they have received all referenced/attached
documents.
• Alabama Port Authority –Insurance Requirements for Contract Work
• Certificate of Compliance with the Beason-Hammon Alabama Taxpayer and Citizen Protection
Act.
Contractor’s Signature:
Contractor Company___________________________________________________________________
___________________________________ __________________________________ ____________
Name
Title
Date
Signature of Party Originating Requisition:
Sean Kelly, P.E.
Date
Project Manager
Form ENG-FR-003 R&P
Last Revised 3/4/10
4|Page
Alabama Port Authority
Requisition and Proposal
Project Name Pinto Island Yard Elevation Raising
Project No. 11681 Task No. 1
Scope of Work Specifications
Work shall consist of the following:
1. Contractor shall provide Performance, and Labor & Materials Bond for this project before
commencing work.
2. Contractor shall provide labor, materials, equipment, and supervision necessary to execute work
efficiently and safely as outlined in contract documents.
3. Contractor shall remove approximately 990 CY of existing soil to to a depth of 6”, to be placed in
designated locations in the rear of the steel yard.
4. Contractor shall furnish and install geotextile fabric, meeting ALDOT Class 1 specifications.
5. Contractor shall furnish and install approximately 790 Tons of ALDOT No. 610 stone, compacted,
across the length of the pier to an elevation approximately 3” below the edge of the concrete
craneway.
6. Contractor shall execute the work in (3) phases to correspond with the three ship berths of the
terminal, so as to always maintain operability of (2) terminal berths during construction.
Form ENG-FR-003 R&P
Last Revised 3/4/10
5|Page
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.