DN01166 (WBS DF18314.2045332) Grading, Drainage, Paving, And Structure At Bridge 440055 Over Hungry River On SR 1802 (Big Hungry Road) in Henderson County Addendum 1

Location: North Carolina
Posted: Jul 9, 2026
Due: Jul 14, 2026
Agency: Division of Highways
Type of Government: State & Local
Category:
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.
  • DN01166 (WBS DF18314.2045332)
    POC
    DN01166 (WBS DF18314.2045332) Grading, Drainage, Paving, And Structure At Bridge 440055 Over Hungry River On SR 1802 (Big Hungry Road) in Henderson County
  • Attachment Preview

    STATE OF NORTH CAROLINA
    DEPARTMENT OF TRANSPORTATION
    JOSH STEIN
    GOVERNOR
    DANIEL H. JOHNSON
    SECRETARY
    July 8, 2026
    ADDENDUM # 1
    Contract Number: DN01166
    TIP Number:
    N/A
    Federal Aid Number: Helene
    WBS Number:
    DF18314.2045332
    County:
    Henderson
    Description:
    Grading, Drainage, Paving, And Structure At Bridge 440055 Over
    Hungry River On SR 1802 (Big Hungry Road) in Henderson
    County
    Letting Date:
    July 14, 2026
    Plan Holders
    Content Summary: Provision Changes & Plans Changes
    The above contract has experienced the following revisions:
    1. Replace the Structures Project Special Provisions with the attached
    2. Replace sheet S-4 with the attached
    These revisions do not change bid items or the associated quantities.
    There is no ebsx addenda file associated with this addendum.
    Thank you for your attention to this matter.
    If you have any questions, please contact the Division Proposal Engineer at (828) 331-
    5200.
    Sincerely,
    Mailing Address:
    NC DEPARTMENT OF TRANSPORTATION
    DIVISION OF HIGHWAYS - DIVISION 14
    253 WEBSTER ROAD
    SYLVA, NC 28779
    Jeanette L. White, P.E.
    Highway Division 14, Project Development-
    Team Lead
    Telephone: (828) 331-5200
    Fax: (828) 331-5201
    Customer Service: 1-877-368-4968
    Location:
    253 WEBSTER ROAD
    SYLVA, NC 28779
    Website: www.ncdot.gov
    Docusign Envelope ID: 3BD5BB56-DC4D-868B-82A8-7FCAB901DAC1
    DF18314.2045332
    ST-1
    Henderson County
    Project Special Provisions
    Structure
    Table of Contents
    Page #
    FALSEWORK AND FORMWORK
    (11-30-23) ...……………….ST-2
    SUBMITTAL OF WORKING DRAWINGS
    (01-31-25) ………..………..ST-8
    CRANE SAFETY
    (12-05-25) ..………………ST-14
    GROUT FOR STRUCTURES
    (12-01-17) ….…………….ST-15
    ASBESTOS ASSESSMENT
    (11-30-23) ………………..ST-16
    CORED SLAB AND BOX BEAM
    POST TENSIONING
    (08-25-25) ………………..ST-19
    CONSTRUCTION, MAINTENANCE AND
    REMOVAL OF TEMPORARY ACCESS AT
    STATION 13+70.81 -L-
    (SPECIAL) ………………..ST-20
    REMOVAL, STAGING, DEMOLITION AND
    CONSTRUCTION OF STRUCTURE AT
    STATION 13+70.81 -L-
    (SPECIAL) ………………..ST-21
    TEMPORARY TIMBER MATS
    (SPECIAL) ………………..ST-23
    ORTHFECSASRIOONLIN
    SEAL
    052672
    TTHEENWG
    INEER
    R. ACO
    6/29/2026
    Docusign Envelope ID: 3BD5BB56-DC4D-868B-82A8-7FCAB901DAC1
    DF18314.2045332
    ST-2
    Henderson County
    FALSEWORK AND FORMWORK
    (11-30-23)
    GENERAL
    Use this Special Provision as a guide to develop temporary works submittals required by the
    Standard Specifications or other provisions; no additional submittals are required herein. Such
    temporary works include, but are not limited to, falsework and formwork.
    Falsework is any temporary construction used to support the permanent structure until it becomes
    self-supporting. Formwork is the temporary structure or mold used to retain plastic or fluid
    concrete in its designated shape until it hardens. Access scaffolding is a temporary structure that
    functions as a work platform that supports construction personnel, materials, and tools, but is not
    intended to support the structure. Scaffolding systems that are used to temporarily support
    permanent structures (as opposed to functioning as work platforms) are considered to be falsework
    under the definitions given. Shoring is a component of falsework such as horizontal, vertical, or
    inclined support members. Where the term “temporary works” is used, it includes all of the
    temporary facilities used in bridge construction that do not become part of the permanent structure.
    Design and construct safe and adequate temporary works that will support all loads imposed and
    provide the necessary rigidity to achieve the lines and grades shown on the plans in the final
    structure.
    MATERIALS
    Select materials suitable for temporary works; however, select materials that also ensure the safety
    and quality required by the design assumptions. The Engineer has authority to reject material on
    the basis of its condition, inappropriate use, safety, or nonconformance with the plans. Clearly
    identify allowable loads or stresses for all materials or manufactured devices on the plans. Revise
    the plan and notify the Engineer if any change to materials or material strengths is required.
    DESIGN REQUIREMENTS
    (A) Working Drawings
    Provide working drawings for items as specified in the contract, or as required by the Engineer,
    with design calculations and supporting data in sufficient detail to permit a structural and safety
    review of the proposed design of the temporary work.
    On the drawings, show all information necessary to allow the design of any component to be
    checked independently as determined by the Engineer.
    When concrete placement is involved, include data such as the drawings of proposed sequence,
    rate of placement, direction of placement, and location of all construction joints.
    When required, have the drawings and calculations prepared under the guidance of, and sealed
    by, a North Carolina Registered Professional Engineer who is knowledgeable in temporary
    works design.
    Docusign Envelope ID: 3BD5BB56-DC4D-868B-82A8-7FCAB901DAC1
    DF18314.2045332
    ST-3
    Henderson County
    If requested by the Engineer, submit with the working drawings manufacturer’s catalog data
    listing the weight of all construction equipment that will be supported on the temporary work.
    Show anticipated total settlements and/or deflections of falsework and forms on the working
    drawings. Include falsework footing settlements, joint take-up, and deflection of beams or
    girders.
    As an option for the Contractor, overhang falsework hangers may be uniformly spaced, at a
    maximum of 36 inches, provided the following conditions are met:
    Member Member Max. Overhang Max. Slab Edge Max. Screed
    Type Depth,
    Width,
    Thickness, Wheel Weight,
    (PCG) (inches)
    (inches)
    (inches)
    (lbs.)
    II
    36
    39
    III
    45
    42
    IV
    54
    45
    MBT
    63
    51
    MBT
    72
    55
    14
    2000
    14
    2000
    14
    2000
    12
    2000
    12
    1700
    Bracket Min.
    Vertical Leg
    Extension,
    (inches)
    26
    35
    44
    50
    48
    Overhang width is measured from the centerline of the girder to the edge of the deck slab. For
    Type II, III & IV prestressed concrete girders (PCG), 45-degree cast-in-place half hangers and
    rods must have a minimum safe working load of 6,000 lbs.
    For MBT prestressed concrete girders, 45-degree angle holes for falsework hanger rods shall
    be cast through the girder top flange and located, measuring along the top of the member, 1’-
    2 ½” from the edge of the top flange. Hanger hardware and rods must have a minimum safe
    working load of 6,000 lbs.
    For link slabs, the top of girders directly beneath the link slab shall be free of overhang
    falsework attachments or other hardware. Submit calculations and working drawings for
    overhang falsework in the link slab region.
    The overhang bracket provided for the diagonal leg shall have a minimum safe working load
    of 3,750 lbs. The vertical leg of the bracket shall extend to the point that the heel bears on the
    girder bottom flange, no closer than 4 inches from the bottom of the member. However, for
    72-inch members, the heel of the bracket shall bear on the web, near the bottom flange
    transition.
    Provide adequate overhang falsework and determine the appropriate adjustments for deck
    geometry, equipment, casting procedures and casting conditions.
    If the optional overhang falsework spacing is used, indicate this on the falsework submittal and
    advise the girder producer of the proposed details. Failure to notify the Engineer of hanger type
    and hanger spacing on prestressed concrete girder casting drawings may delay the approval of
    those drawings.
    Docusign Envelope ID: 3BD5BB56-DC4D-868B-82A8-7FCAB901DAC1
    DF18314.2045332
    ST-4
    Henderson County
    Falsework hangers that support concentrated loads and are installed at the edge of thin top
    flange concrete girders (such as bulb tee girders) shall be spaced so as not to exceed 75% of
    the manufacturer’s stated safe working load. Use of dual leg hangers (such as Meadow Burke
    HF-42 and HF-43) are not allowed on concrete girders with thin top flanges. Design the
    falsework and forms supporting deck slabs and overhangs on girder bridges so that there will
    be no differential settlement between the girders and the deck forms during placement of deck
    concrete.
    When staged construction of the bridge deck is required, detail falsework and forms for screed
    and fluid concrete loads to be independent of any previous deck pour components when the
    mid-span girder deflection due to deck weight is greater than ¾”.
    Note on the working drawings any anchorages, connectors, inserts, steel sleeves or other such
    devices used as part of the falsework or formwork that remains in the permanent structure. If
    the plan notes indicate that the structure contains the necessary corrosion protection required
    for a Corrosive Site, epoxy coat, galvanize or metalize these devices. Electroplating will not
    be allowed. Any coating required by the Engineer will be considered incidental to the various
    pay items requiring temporary works.
    Design falsework and formwork requiring submittals in accordance with the current edition of
    AASHTO Guide Design Specifications for Bridge Temporary Works except as noted herein.
    (1) Wind Loads
    Table 2.2 of Article 2.2.5.1 is modified to include wind velocities up to 110 mph. In
    addition, Table 2.2A is included to provide the maximum wind speeds by county in North
    Carolina.
    Table 2.2 - Wind Pressure Values
    Height Zone
    Pressure, lb/ft2 for Indicated Wind Velocity, mph
    feet above ground
    70
    80
    90
    100
    110
    0 to 30
    15
    20
    25
    30
    35
    30 to 50
    20
    25
    30
    35
    40
    50 to 100
    25
    30
    35
    40
    45
    over 100
    30
    35
    40
    45
    50
    (2) Time of Removal
    The following requirements replace those of Article 3.4.8.2.
    Do not remove forms until the concrete has attained strengths required in Article 420-16
    of the Standard Specifications and these Special Provisions.
    Do not remove forms until the concrete has sufficient strength to prevent surface damage.
    This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
    Daily notification on new contract opportunities

    With GovernmentContracts, you can:

    • Find more opportunities and win more business
    • Receive daily alerts for all new bid opportunities
    • Get contract opportunities matched to your business
    ONE WEEK FREE TRIAL

    See also

    ...Project: CATS Unit Paving and Repairs Ref. #: 269-2026-1782 Department: City Procurement Type: ...

    City of Charlotte

    Bid Due: 7/29/2026

    ...Project: CATS Unit Paving and Repairs Ref. #: 269-2026-1782 Department: City Procurement Type: ...

    City of Charlotte

    Bid Due: 7/29/2026

    ...Notice to Bidders: 2026-2027 Asphalt Paving Program - Available until August 6, 2026 ...

    City of Monroe

    Bid Due: 8/06/2026

    ...(002) ) GRADING, DRAINAGE, SIDEWALK AND PAVING ON SR 1747 (EAST STADIUM DR) ...

    Division of Highways

    Bid Due: 8/06/2026

    * Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.