Management, Operations & Maintenance Services for Wastewater Treatment Plants

Location: Texas
Posted: Jul 9, 2026
Due: Jul 20, 2026
Agency: City of Pasadena
Type of Government: State & Local
Category:
  • M - Operation of Government Owned Facilities
Solicitation No: 26-008
Publication URL: To access bid details, please log in.
Bid Number Bid Name Release Date Due Date
26-008 Management, Operations & Maintenance Services for Wastewater Treatment Plants 06/11/2026 07/20/2026

Attachment Preview

City of Pasadena
Request for Proposals
RFP #26-008
for
MANAGEMENT, OPERATIONS, & MAINTENANCE
SERVICES FOR
WASTEWATER TREATMENT PLANTS
Issued: June 10, 2026
ISSUED BY:
City of Pasadena
1149 Ellsworth Drive
Pasadena, Texas 77506
RESPONSES DUE:
Monday, July 13, 2026
by 4:00 PM, CST
TABLE OF CONTENTS
I.
REQUEST FOR PROPOSALS....................................................................................................................3
II.
SCOPE OF SERVICES AND RESPONSIBILITIES...……………………………………………………5
III. EVALUATION CRITERIA………………………………………............................................................11
IV. REQUIREMENTS FOR RESPONSE…………………………………………………………………….12
V.
SUBMISSION OF RESPONSE………………...........................................................................................15
VI. AWARD OF CONTRACT……………………………………………………………………………….16
VII. INSURANCE AND LIABILITY...............................................................................................................18
VIII. SPECIAL PROVISIONS…………………………………………………………………………………18
IX. ANTICIPATED SCHEDULE…………………………………………………………………………….20
ATTACHMENTS:
ATTACHMENT “A” VENDOR INFORMATION QUESTIONNAIRE AND ASSURANCES
ATTACHMENT “B” PRICE PROPOSAL FORM
ATTACHMENT “C” HOUSE BILL 89 VERIFICATION AFFIDAVIT
ATTACHMENT “D” CAPITAL IMPROVEMENT PROJECTS (https://bit.ly/44Od1Vk)
ATTACHMENT “E” SAMPLE AGREEMENT
ATTACHMENT “F” WWTP CURRENT PERMIT (https://bit.ly/44Od1Vk)
ATTACHMENT “G” 2023 FACILITY ASSESSMENT (VINCE BAYOU WWTP, GOLDEN ACRES WWTP)
(https://bit.ly/44Od1Vk)
ATTACHMENT “H” PRETREATMENT PLAN (https://bit.ly/44Od1Vk)
I. REQUESTS FOR PROPOSALS
The City of Pasadena (“the City”) requests Proposals from interested, qualified Respondents capable of providing
full-service operations, maintenance, and management for the Pasadena Wastewater Treatment Facilities in
accordance with the terms and Scope of Services specified herein. The City Wastewater Treatment Facilities consist
of the New Vince Bayou Wastewater Treatment Plant (WWTP) and the Golden Acres WWTP. Vince Bayou WWTP
is located at 209 N Main Street, Pasadena, TX, 77506 and Golden Acres WTTP is located approximately 100 yards
South of Spencer Highway and adjacent to the west edge of Trebor Street, Pasadena, Texas, 77505.
This solicitation complies with applicable City Policy and State of Texas law, including Local Government Code 252.
The City will select the successful Respondent that is determined to provide the best value to the City of Pasadena
based on the published Evaluation Criteria and its final ranking.
The initial term of the resulting Agreement, subject to approval by the City Council, will be 5 years with one (1) five
(5)-year renewal options. While the City plans to enter into a long-term agreement with the selected Contractor, the
City reserves the right to choose to not to renew the contract at the end of each renewal period (years 5 and 10) with
the Contractor providing up to one (1) year transition period. Renewals will be subject to compliance and performance
history in addition to City Council approval.
II. SCOPE OF SERVICES AND RESPONSIBILITIES
1.0 Introduction - The City is seeking qualified respondents capable of providing full-service operations, maintenance,
and management for 2 existing wastewater treatment facilities.
1.1 Purpose of Solicitation - In issuing this RFP, the City is seeking to partner with a Contractor having the technical
and financial resources to perform the required operation, maintenance, and management services for existing
WWTPs facilities. Additionally, the selected Contractor will provide a strong technical support team to operate
safely and in compliance with all regulatory requirements, implement sustainable and effective maintenance
programs, and provide efficiencies in labor and materials.
Request for Proposals submitted by Firms in response to this RFP will be evaluated in accordance with the criteria
outlined in Section III. EVALUATION CRITERIA of this document. Based on the City’s evaluation, the
Contractor providing the “best value” will be selected by the City for contract negotiations. A response to this RFP
is mandatory for consideration.
1.2 Background - The City currently treats wastewater at two facilities – Vince Bayou WWTP and Golden Acres
WWTP. The wastewater collection system includes 65 Lift Stations (LSs) located City-wide.
1.2.1. Vince Bayou WWTP (Vince Bayou)
Vince Bayou was originally built in the early 2000s, and is located at 209 N Main Street, Pasadena, TX,
77506. The current Texas Pollutant Discharge Elimination System (TPDES) permit is included as
Attachment F – Wastewater Treatment Plants (WWTP) Permits. The liquid treatment process includes
manual screening and grit removal followed by extended aeration secondary treatment utilizing oxidation
ditches and secondary clarifiers, post aeration basins, ultraviolet (UV) disinfection, and effluent flow
measurement structure. The solids treatment includes Waste Activated Sludge (WAS) pumping, gravity
thickener, and sludge dewatering via belt filter press. Subsequently, the dewatered sludge is hauled to
authorize landfill site. Figure 1 shows the aerial map of the Vince Bayou WWTP.
3
Figure 1: Aerial Map of Vince Bayou WWTP
Vince Bayou is located mostly within the 500-year floodplain zone, with portions of the plant within the
100-year floodplain zone, according to FEMA FIRM 48201C0905N (dated 5/2/2019).
1.2.2. Golden Acres WWTP (Golden Acres)
Golden Acres was originally built in 1950s with major upgrades in 1980s as well as 2010s. The WWTP is
located approximately 100 yards South of Spencer Highway and adjacent to the west edge of Trebor Street,
Pasadena, Texas, 77505. The plant consists of two separate parallel treatment facilities, the East Plant and
the West Plant, that share a common influent LS and headworks. The East Plant liquid treatment includes
extended aeration secondary treatment with oxidation ditches and clarifiers, followed by chlorine
disinfection, effluent flow measuring weirs, and effluent pump station. The solids treatment includes WAS
pumping, gravity thickener, aerobic digester, and sludge dewatering via belt filter press. Subsequently, the
dewatered sludge is hauled to authorize landfill site. For the past few years, the Golden Acres WWTP has
been operating using only the East Plant to treat all flows. The TDPES permit is included as Attachment F
– Wastewater Treatment Plants (WWTP) Permits. Golden Acres is located within the 500-year and 100-
year floodplain zone, according to FEMA FIRM MAP 48201C9020M (dated 1/6/2017). Figure 2 shows the
aerial map of the Golden Acres WWTP.
Figure 2: Aerial Map of Golden Acres WWTP
4
1.2.3. Facility Assessment
The City conducted a facility assessment of both the Vince Bayou and Golden Acres WWTP in 2023.
The findings of facility assessment are included in Attachment G and is provided for reference only.
The Contractor is expected to conduct a field visit to the facilities to understand the current existing
condition and operational capabilities of the facility and include their operational plan in the proposal
(i.e. project approach).
1.2.4. Operations Requirements
The responsibility of the Contractor shall be to operate the Treatment Facilities to meet all Effluent
Requirements, and the subject Texas Pollutant Discharge Elimination System (TPDES) permits as well as
any other federal, state, and local requirements, or as may hereafter be mandated and are within the physical
capabilities of the WWTP Facilities.
It is understood that the City cannot list every generally acceptable practice that should be associated
within a scope of work of this magnitude. As such the City has an expectation that the selected
Contractor will perform the necessary scoping items that are reasonable and rational. The City does
not expect to receive out-of-scope change orders because a single specific item was not discussed in this
scope.
2.0 Operation, Maintenance, & Management
2.1 Scope of Work
The contractor is responsible for Operation, Maintenance, and Management of the existing Wastewater Treatment
Facilities. This scope includes, but is not limited to the following:
The Contractor is expected to provide adequate personnel and equipment to meet the current permitted
capacity requirements of the WWTP.
All personnel should possess the experience, qualifications,skills, and wastewatercertificationsrequiredto perform
properandeffectiveoperationsand maintenance activities for the WWTPs, and to meet current permit requirements.
The Contractor shall coordinate supervision and conduct regular evaluation of plant personnel to adhere to their
quality control measures.
Staff must respond to callouts 24 hours/day and within 45 minutes of notification.
The Contractor shall submit a plan for equipment and vehicles in the technical approach to demonstrate the
plan to maintain, operate, and manage the two facilities.
2.1.1 Minimum personnel qualifications for management/supervisory positions include:
Principal-in-charge (PIC) must have substantial experience in wastewater operation and maintenance and
possess either a Texas Class A Wastewater Operator’s license or equivalent from another state with
reciprocity. The principal-in-charge must attend all meetings required to update City officials of the operation
of the facility. The principal-in-charge must be responsible for contract administration, reporting and all
aspects of operations and maintenance performance. The Contractor shall not change the designated
representative without notice to and discussion of change with City. If City objects to the assigned principal-
in-charge, the Contractor agrees to provide an acceptable and qualified individual within the 30 calendar days
of such written notice as noted in the Agreement.
On-site Operations Manager/Supervisor for each WWTP facility must possess a Texas Class A Wastewater
Operator’s License or equivalent from another state with reciprocity. They must have at least 5 years of
experience in wastewater treatment and wastewater facility maintenance and repair. These staff members
must be qualified and trained to perform routine and corrective maintenance (CM) activities according to
manufacture recommendations, operate/maintain the City’s WWTP SCADA and troubleshoot operational
issues, and manipulate the facilities to maintain compliance.
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...) Status: Open Solicitation Number: IFB 6100 CLMC1171 Description: Wastewater Billing Meter Assessments... ...

City of Austin

Bid Due: 8/13/2026

...Bid Information Type Request for Bid Status Issued Number REQ00002440 (Monica Park Wastewater...

City of Garland

Bid Due: 7/23/2026

...Wastewater Analysis Mexia State Supported Living Center Solicitation ID: HHS0017407 Due Date: 7/23...

State Government of Texas

Bid Due: 7/23/2026

...Project ID: Title: Phase 1 - Waterleaf wastewater and reclaimed water improvements Addenda: ...

City of Kyle

Bid Due: 8/24/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.