1. Request for Proposal
San Miguel County (County) and the Colorado Department of Transportation (CDOT), are
soliciting requests for proposals (RFP) from innovative firms specializing in Architectural and
Engineering Design Services. The selected firm will develop a comprehensive master site plan
which will include designs for the operational site needs (CDOT and County Road and Bridge
Operations) and Deep Creek Workforce Housing Project.
The scope of work includes architectural design, engineering, and site planning to ensure all
necessary maintenance activities can be accommodated within the western County’s portion of
the site and with the relocation of the operational activities, to the eastern portion of the site will
be designed for housing. The project must include the following; for detailed scope, see the
deliverables section below:
● Consolidated Site and Housing Plan
○ Master Plan integrating housing layout for approximately twenty-five (25)
residential units or more, with consideration for additional units and/or phases if
reasonably feasible.
● Phased Design Packages
○ Conceptual sketches, design development drawings, and approximately eighty
percent (80%) construction drawings and specifications for the approved project.
● Detailed Construction Cost Estimate
○ Itemized estimate by phase, including maintenance facilities, housing
infrastructure/site preparation, and any housing construction phases.
● Supporting Documents
○ Zoning analysis (Section 5-315-PUB), maintenance plan, coordination memo,
permitting checklists.
● Optional Services
○ Guaranteed Maximum Price (GMP) Proposal (at County/CDOT discretion)
Prepare GMP based on eighty (80%) drawings, phased (Maintenance Facilities,
Site Preparation, Housing)
○ Construction Readiness (addendum): Bid preparation, CM/GC qualification,
inspections, punch lists.
○ Timeline: 6-9 months from NTP; assumes 2-week feedback, no scope changes;
excludes 100% CDs/permitting.
2. Background
San Miguel County (County) and the Colorado Department of Transportation (CDOT),
collectively referred to as the Parties have partnered to develop plans for a workforce housing
project located at 15551 HWY 45 Telluride (Deep Creek CDOT Maintenance Yard) in San
Miguel County, Colorado. Under a Workforce Housing Planning Agreement, both parties intend
2 | Page
to jointly plan and if necessary modify the layout of the CDOT and County properties to
accommodate the construction of essential facilities and residential units. The project’s purpose
is to provide workforce housing for both County and State employees.
Advancing this project will help address the critical shortage of workforce housing affecting the
San Miguel County community and key employers such as CDOT. The Parties are now
soliciting from qualified contractors to provide Architectural, Engineering, and Site Planning
services for the Deep Creek Workforce Housing Planning Project.
Property Ownership
Since 2024, San Miguel County and the Colorado Department of Transportation (CDOT) have
explored a partnership to develop a workforce housing project on their respective parcels. The
County owns the parcel located at 15553 HWY 145 Telluride, known as the San Miguel County
Deep Creek Road and Bridge Shop, which comprises 3.201 acres. CDOT owns the adjacent tract
of land, identified as Parcel No. 1 in the SE1/4 of Section 26, Township 43 North, Range 10
West, NMPM, known as 15551 HWY 145 Telluride of the Deep Creek CDOT Maintenance
Yard, consisting of of 2.515 acres.
Under the agreement, the Parties will jointly undertake all necessary actions to develop a site
plan that accommodates the required maintenance activities on the County property while
supporting the development of workforce housing on the CDOT property. The agreement further
directs CDOT and County to take all steps necessary, under the County Land Use Code and
other applicable state and local regulations, to obtain approval for a residential development on
the CDOT property. In addition, the parties will prepare eighty percent (80%) of the construction
drawings and obtain construction cost estimates for the approved project.
This agreement is limited to the planning and design phase. It does not commit either party to the
project’s final construction. A separate agreement or amendment will be executed if both parties
determine that the project to be viable and elect to proceed.
General Zoning Information
The 5.72-acre site is located off of Highway 145 in San Miguel County, Colorado and is
designated as Public under the County Land Use Code, with surrounding properties zoned
Forestry/Agriculture.
The Public Zone District is intended to ensure that development within the district is guided by
an adopted master plan. Uses allowed with one-step planning commission approval must meet
specific criteria, and additional details on these zoning standards are provided in Section 5-315-
Public (PUB)
of the County Land Use Code.
3 | Page
Background Studies and Project Goals
The 2025 San Miguel County Housing Needs Assessment, in partnership with the Town of
Mountain Village and the Town of Telluride worked with the San Miguel County Regional
Housing Authority (SMRHA) to conduct a Regional Housing Needs Assessment. SMRHA
contracted EPS and RRC Associates to conduct the market analysis, which describes the current
need for affordable housing within a multi-jurisdictional area that meets the actual workforce
demand in San Miguel County and will serve as a planning tool for future housing initiatives. In
2025, San
Miguel
County
began
undertaking a comprehensive land use code audit and update to identify and remove regulatory
barriers that constrain housing development in unincorporated areas. This project will assess
current zoning regulations, development standards, and permitting processes to identify where
unnecessary complexity, costs, or delays prevent housing production. This project will
implement key recommendations from the East End Master Plan and other community planning
efforts. The goal of this project is to enable more housing choices while preserving community
character. The following documents and reports will help inform and define the projects
program and goals:
● San Miguel County Housing Needs Analysis 2025
● San Miguel County Housing Needs Assessment Presentation 2025
● San Miguel County Housing Code Update
● San Miguel County Board of County Commissioners Mission Statement 2026
● Colorado Department of Transportation Performance Plan 2025-2026
4 | Page
3. Scope of Work and Deliverables
The following outlines the primary duties and key tasks for the scope of work, deliverables of the
firms specializing in Architectural and Engineering Design Services for successful project
delivery. The project will follow a structured, phased design process and the final scope will be
refined and agreed upon during the fee negotiations between the County and CDOT and the
selected firm. Each phase will require both CDOT and County review of progress plans prior to
proceeding to the next phase.
Key Tasks
Phase 1
1. Architectural Design
a. Architectural design will be developed for residential units of various unit types
and sizes, emphasizing a phased approach to support 20-25 units (or more if
reasonably feasible based on-site constraints, zoning, feasibility).
b. Architectural design of maintenance facilities will not be included as part of this
project. Footprints and layout for these facilities will be included under site
planning.
2. Engineering Analysis
a. Perform utility, drainage, access, and maintenance evaluations for all project
areas, including necessary survey and geotechnical assessment for all areas of the
site plan.
3. Site Planning
a. Optimize the layout on both sites, specifically CDOT’s portion for housing, and
both parcels for open space circulation, and long-term access for all associated
activities.
4. Regulatory and Stakeholder Coordination.
a. Ensure all design phases comply with the County’s Land Use Code, master
planning needs.
b. Coordinate regularly with key stakeholders, including CDOT and any relevant
County departments.
Phase 2
5. Conceptual Design Phase
a. Develop an initial site layout for both sites, housing massing (20-25 + units),
location for CDOT maintenance buildings, a master plan framework, and zoning
compliance sketches; incorporate maintenance easements and early stakeholder
input by both Parties.
6. Design Development Phase
a. Refine plans with detailed architectural, structural, civil, and MEP engineering;
produce 80% construction drawings for County/CDOT review.
7. Preconstruction Services Phase