MT. DIABLO UNIFIED SCHOOL DISTRICT
PURCHASING &WAREHOUSE DEPARTMENT
2326 BISSO LANE, CA 94520-4802
BID #1973
Volume I
MDUSD 2026 Roofing Project – Holbrook Elementary
School and Valle Verde Elementary School
Roofing restoration and/or replacement with Garland
system at Holbrook Elementary School and Valle Verde
Elementary School
March 17, 2026
DOCUMENT 00 01 10
TABLE OF CONTENTS - CONTRACT DOCUMENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS
Division 00
Section
00 01 01
00 01 10
00 01 15
00 11 16
00 21 13
Title
Title Page
Table of Contents (This Document)
List of Drawings, Tables and Schedules
Notice to Bidders / Invitation to Bid
Instructions to Bidders
00 41 13
00 43 13
00 43 36
00 43 40
00 43 50
DOCUMENTS THAT BIDDER MUST SUBMIT AS PART OF ITS BID
Bid Form
Bid Bond (Security)
Designated Subcontractors List
Noncollusion Declaration
Iran Contracting Act Certification
00 45 00
00 45 10
00 45 40
00 45 55
00 45 85
00 54 50
00 54 55
Notice of Award
Agreement
Certifications to be Completed by Contractor
Disabled Veteran’s Business Enterprise Participation Certification
Criminal Background Investigation/Fingerprinting Certification
Escrow of Bid Documentation
Escrow Agreement for Security Deposits in Lieu of Retention
00 61 14
00 61 15
Performance Bond
Payment Bond (Contractor’s Labor and Material Bond)
00 65 00
00 65 10
00 65 36
00 70 00
00 71 00
00 91 13
District Closeout Forms
Notice to Proceed
Warranty and Guarantee Form
General Conditions
Special Conditions
Addenda - All addenda issued by District become part of the Contract.
END OF DOCUMENT
Mt. Diablo Unified School District
TABLE OF CONTENTS
DOCUMENT 00 01 10- 1
DOCUMENT 00 01 15
LIST OF DRAWINGS, TABLES AND SCHEDULES
DRAWINGS
Holbrook Elementary
Sheet Number
1
2
3
4
5
6
7
8
Description
Cover Sheet
Scope of Work
Roof Plan
Typical Details
Details
Details
Details
Details
Valle Verde
Elementary
Sheet Number
Description
1 Cover Sheet
2 Scope of Work
3 Roof Plan
4 Typical Details
5 Details
6 Details
7 Details
8 Details
SCHEDULES
The following is the anticipated schedule and is subject to change
Activity
Issue Bid
Mandatory Bid Walk
Request for Information Deadline
Bids Due
Anticipated Board Action-Approval of Bid
Contract Documentation
Notice to Proceed
Project Completion-Holbrook Elementary School
Project Completion-Valle Verde Elementary
Anticpated Closeout Documention
Anticipated Board Action-Notice of Completion
Date
2/19/2026
3/4/2026
3/10/2026
3/17/2026
4/15/2026
4/26/2026
6/3/2026
7/31/2026
7/31/2026
8/28/2026
9/23/2026
Mt. Diablo Unified School District
END OF DOCUMENT
LIST OF DRAWINGS, TABLES AND SCHEDULES
DOCUMENT 00 01 15- 1
DOCUMENT 00 11 16
NOTICE TO BIDDERS / INVITATION TO BID
1. Notice is hereby given that the governing board (“Board”) of the Mt. Diablo Unified School District (“District”)
will receive sealed bids to construct the following project:
Bid #1973 MDUSD 2026 Roofing Project – Holbrook and Valle Verde Elementary Schools (“Project” or
“Contract”)
2. To bid on this Project, the Bidder is required to have been prequalified by the District prior to submitting its
bid. In addition, if the Project has electrical, mechanical, or plumbing components that will be performed by
subcontractors performing under the following license classification(s), then each of those subcontractors that
intend to bid as a first-tier subcontractor to a general contractor (prime contractor) are required to have been
prequalified by the District: C-4, C-7, C-10, C-16, C-20, C-34, C-36, C-38, C-42, C-43, and/or C-46. All
prequalification questionnaires will be received until 3:00p.m., March 10th, 2026, Through the District’s
Prequalification Vendor, Quality Bidders at https://www.qualitybidders.com/users/sign_up.
3. Bidders must submit sealed bids on or before 10:00 a.m., March 17th, 2026,at the District Purchasing &
Warehouse Office at 2326 Bisso Lane, Concord, California 94520, and Bidders must ensure that the District
time stamps the Bidder’s bid at or before that time. After the designated bid opening time, the District will
open the bids and publicly read them aloud. Any claim by a Bidder of error in its bid must be made in
compliance with Public Contract Code § 5100, et seq. The District is not responsible for (1) bids received after
the deadline noted above; or (2) bids misdelivered, by any method, even to a different District address.
4. The Project consists of:
Roofing restoration and/or replacement with Garland System per plans and specifications at
Holbrook and Valle Verde Elementary Schools.
5. All bids shall be on the forms provided by the District. Each bid must conform and be responsive to all
pertinent bid and Contract Documents, including, but not limited to, the Instructions to Bidders.
6. To bid on this Project, the Bidder is required to possess one or more of the following State of California
Contractor Licenses:
B: General Building Contractor
C-39: Roofing
The Bidder's license(s) must be active and in good standing at the time of the bid opening and must remain so
throughout the term of the Contract.
7. As security for its Bid, each Bidder shall provide with its Bid form
• a bid bond issued by an admitted surety insurer on the form provided by the District,
• cash, or
• a cashier's check or a certified check, drawn to the order of the Mt. Diablo Unified School District,,
in the amount of ten percent (10%) of the total bid price. This bid security shall be a guarantee that the Bidder
shall, within seven (7) calendar days after the date of the Notice of Award, enter into a contract with the
District for the performance of the services as stipulated in the bid.
8. The successful Bidder shall be required to furnish a 100% Performance Bond and a 100% Payment Bond if it is
awarded the Contract for the Project.
9. The successful Bidder may substitute securities for any monies withheld by the District to ensure performance
Mt. Diablo Unified School District
INVITATION TO BID
DOCUMENT 00 11 16- 1
under the Contract, in accordance with the provisions of Public Contract Code § 22300.
10. The successful Bidder and its subcontractors shall pay all workers on the Project not less than the general
prevailing rate of per diem wages and the general prevailing rate for holiday and overtime work as determined
by the Director of the Department of Industrial Relations, State of California, for the type of work performed
and the locality in which the work is to be performed within the boundaries of the District, pursuant to Labor
Code § 1770 et seq. Prevailing wage rates are on file with the District and are available to any interested party
on request or at www.dir.ca.gov/oprl/statistics_and_databases.html. Bidders and Bidders’ subcontractors
shall comply with the registration and qualification requirements pursuant to Labor Code §§ 1725.5 & 1771.1.
11. A mandatory pre-bid conference and site visit will be held on March 4th,2026, at 10:00a.m. starting at
Holbrook Elementary School (3333 Roland Way, Concord, CA) followed by Valle Verde (3275 Peachwillow Ln.,
Walnut Creek, CA.)., All prospective Bidders are required to sign in at the start of the walk and attend both
campus walks. The Site Visit is expected to take approximately one hour per site. Failure to attend or
tardiness will render bid ineligible.
12. Contract Documents are available on February 19th, 2026, for review on the District Purchasing & Warehouse
webpage: https://www.mdusd.org/departments/business-services/purchasing-warehouse/bid-
information/construction-bids. In addition, Contract Documents are available for review at the following
builders’ exchanges:
Bay Area Builders Exchange
(520) 483-8880
A list of these builders' exchanges is available at the District’s Facilities Office.
13. The District’s Board reserves the right to reject any and all bids and/or waive any irregularity in any bid
received. If the District awards the Contract, the security of unsuccessful Bidder(s) shall be returned within
sixty (60) days from the time the award is made. Unless otherwise required by law, no Bidder may withdraw
its bid or bid security for ninety (90) days after the date of the bid opening.
14. The District shall award the Contract, if it awards it at all, to the lowest responsive responsible Bidder based
on:]
The base bid amount only.
END OF DOCUMENT
Mt. Diablo Unified School District
INVITATION TO BID
DOCUMENT 00 11 16- 2
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.