SPECIFICATIONS
FOR
2026
SEWER REHABILITATION
PREPARED BY
LUKE THOELE, P.E.
CITY ENGINEER
201 EAST JEFFERSON AVENUE
P.O. BOX 648
EFFINGHAM, ILLINOIS
November 2026
TABLE OF CONTENTS
Table of Contents ........................................................................................................................................................... 2
NOTICE TO CONTRACTORS .................................................................................................................................... 3
SPECIAL PROVISIONS ............................................................................................................................................... 4
LOCATION OF PROJECT ....................................................................................................................................... 4
DESCRIPTION OF WORK ...................................................................................................................................... 4
LIQUIDATED DAMAGES ....................................................................................................................................... 4
CLOSING THE STREETS AND TRAFFIC CONTROL COMPLETE ................................................................... 4
WORK TO BE PERFORMED BY OTHERS ........................................................................................................... 5
PREVAILING WAGE ............................................................................................................................................... 5
SUBSTANCE ABUSE AND PREVENTION PROGRAM ...................................................................................... 5
INSURANCE ............................................................................................................................................................ 5
SCOPE OF THE PROJECT ...................................................................................................................................... 6
PAYMENT AND PERFORMANCE BOND ............................................................................................................. 6
UNFORESEEN CONDITIONS ................................................................................................................................ 7
RECORD DOCUMENTS ......................................................................................................................................... 7
WARRANTY AND GUARANTEE .......................................................................................................................... 7
DEFECTIVE WORK ................................................................................................................................................ 8
SANITARY/STORM SEWER CLEANING AND CCTV INSPECTIONS ............................................................ 10
CURED-IN-PLACE PIPE (CIPP) ........................................................................................................................... 17
RESTORATION ...................................................................................................................................................... 23
CONTRACT ................................................................................................................................................................ 24
PROPOSAL ................................................................................................................................................................. 27
REFERENCES ........................................................................................................................................................ 28
SCHEDULE OF PRICES ........................................................................................................................................ 28
NOTICE OF AWARD ................................................................................................................................................. 32
NOTICE TO PROCEED ............................................................................................................................................. 33
2
SPECIAL PROVISIONS
The following Special Provisions supplement the "Standard Specifications for Road and Bridge
Construction of the State of Illinois", adopted January 1, 2022, and the Supplemental Specifications and
Recurring Special Provisions, which govern the 2026 Sewer Rehabilitation, City of Effingham, Illinois, and
in case of conflict with any part or parts of said Specifications, the said Special Provisions shall take
precedence and shall govern.
LOCATION OF PROJECT
The proposed work for this project is in multiple locations within the corporate boundaries of the City of
Effingham.
DESCRIPTION OF WORK
The proposed work is officially known as "2026 Sewer Rehabilitation" for the City of Effingham,
Effingham, Illinois. The project shall consist of cleaning Cured-in-Place Pipe (CIPP) rehabilitation of
sanitary/storm sewer pipe in the areas designated on the attached location maps and other
miscellaneous work.
LIQUIDATED DAMAGES
OWNER and CONTRACTOR recognize that time is of the essence in the performance of the Contract and
that failure on the part of the Contractor to complete the contract work in the time herein set forth will
result in certain loss and damages to the Owner. Failure on the contractor's part to complete such work
shall be considered just cause for forfeit of his/her surety bond.
In case the Contractor of the work shall fail or neglect to complete any section of work on or before
March 30, 2027, then said Contractor shall and will pay to the Owner such sums as may be due to him
under the terms of the Contract at the rate specified in the Standard Specifications for Road and Bridge
Construction.
The City expects to award the project at its Council Meeting on November 17th. The City expects work to
progress at a rate that would allow the completion of the project by the completion date specified
assuming material can be received in a timely manner. If the liners are ordered in November, but delivery
is delayed past February 10th, the City will extend the completion date to the same amount of days as
the delay in delivery. Documentation will be required to support this extension.
The contract time may be changed only by change order. For each change order, CONTRACTOR shall
submit to the OWNER for review, sufficient reason for delay to enable the OWNER to ascertain the
necessity and reasonableness of the delay, and the allowability and eligibility of delay proposed.
CLOSING THE STREETS AND TRAFFIC CONTROL COMPLETE
The streets and all entrances shall remain open to traffic unless authorized by the City Engineer or
Operations Manager. The Contractor shall provide the City a traffic control plan and schedule and will be
responsible for providing public notices to inform the public of various routing plans. When the street
should be closed to traffic, it shall be the Contractors responsibility to plan with the affected party in
keeping access to the premises in so doing, shall give 48 hours' notice to the Engineering and Street
Department. When the contractor is working from or on the street, they shall place proper traffic
control in accordance with traffic control standards from the Illinois Department of Transportation. The
4
contractor shall furnish, erect, and maintain all barricades, signs and other warning devices required by
Section 107.14 and no additional compensation will be allowed.
WORK TO BE PERFORMED BY OTHERS
Any necessary patching or preparation work and or any necessary work to adjust or construct grates,
manholes and other utilities will be made before operation begins by the city forces on the specified
locations. Proper notification time shall be allowed for the Street Department to make adjustments.
PREVAILING WAGE
Prevailing rate of wages ascertained by the Illinois Department of Labor (IDOL) or as determined by the
court on review shall be paid to all laborers, workers, and mechanics performing work under this
contract pursuant to Public Act 100-1177. The prevailing rate of wages are revised by IDOL and are
available on the Department's official website. Any revised rate shall apply to this contract, and the
contractor shall be responsible for paying the revised rate. The contractor shall be responsible for
determining the appropriate rates for this project and for anticipating the prevailing wage rate that will
apply at the time the work is performed. The contractor shall be responsible for submitting all certified
payrolls for the awarded project and for any subcontractor work to the IDOL website pursuant to Public
Act 100-1177. Paper or electronic copies shall be provided to the City upon request only for up to 3 years
after the project is complete.
SUBSTANCE ABUSE AND PREVENTION PROGRAM
In addition to all other labor requirements set forth in this proposal and in the Standard Specifications
for Road and Bridge Construction, adopted by the Department, during the performance of this contract,
the Contractor for itself, its assignees, and successors in interest (hereinafter referred to as the
"Contractor") agrees as follows:
Before the Contractor and any Subcontractor commences work, the Contractor and any Subcontractor
shall have in place a written Substance Abuse Prevention Program for the prevention of substance abuse
among its employees which meets or exceeds the requirements in P.A. 95-0635 or shall have a collective
bargaining agreement in effect dealing with the subject matter of P.A. 95-0635. The Contractor and any
Subcontractor shall file with a public body: a copy of the substance abuse prevention program along with
a cover letter certifying that their program meets the requirements of the Act, or a letter certifying that
the Contractor or a Subcontractor has a collective bargaining agreement in effect dealing with the
subject matter of this Act.
INSURANCE
Contractors are required to furnish the City with Certificates of Insurance in the following amounts, and
the City of Effingham will be listed as an Additional Insured on a primary non-contributory basis. The
Certificate of Insurance shall be accompanied by an "Additional Insured - Designated Person or
Organization" form.
5
Worker's Compensation Statutory Limits
Employer's Liability $ 1,000,000
General Liability $ 2,000,000
Auto Liability $ 1,000,000
Excess Liability $ 2,000,000
Certificates of Insurance shall contain a provision or endorsement that the coverage afforded will not be
canceled, materially changed or renewal refused until at least 30 days prior written notice has been
given to Owner and Contractor.
Certificates of Insurance always remain in effect at least until final payment and thereafter when
Contractor may be correcting, removing, or replacing defective Work; and
Contractor shall furnish Owner and each other additional insured to whom a certificate of insurance has
been issued, evidence satisfactory to Owner and any such additional insured of continuation of such
insurance at final payment.
SCOPE OF THE PROJECT
The quantities shown in the proposal are the approximate quantities required to complete the work. The
City reserves the right to delete up to twenty-five percent (25%) of the work for budgetary reasons or
due to conflicts with other construction work.
The City of Effingham intends to CIPP line sanitary and storm sewers within their sewer system. See the
schedule of prices for quantities.
PAYMENT AND PERFORMANCE BOND
Section 102 of the Standard Specifications for Road and Bridge Construction shall be revised as follows:
The Contractor shall deliver a payment and performance bond to the City Engineer in the total amount
of the contract at the time the contract is executed by the City.
Such bond shall be conditioned for the completion of the contract, for the payment of material used in
such work and for all labor performed in such work, whether by subcontractor or otherwise.
Each such bond is deemed to contain the following provisions whether such provisions are inserted in
such bond or not:
"The principal and sureties on this bond agree that all the undertakings, covenants, terms, conditions
and agreements of the contract or contracts entered into between the principal and the City will be
performed and fulfilled and to pay all persons, firms and corporations having contracts with the principal
or with subcontractors, all just claims due them under the provisions of such contracts for labor
performed or materials furnished in the performance of the contract on account of which this bond is
given, when such claims are not satisfied out of the contract price of the contract on account of which
this bond is given, after final settlement between the City and the principal has been made."
6
The bond required by this Section may be acquired from an Illinois company, agent or broker of the
contractor's choice, except that the bond supplier shall be rated A (Excellent) or A+ (Superior), Financial
Size Category Class XII or larger, in the most recent issue of Best's Key Rating Guide published by A.M.
Best Company of Oldwick, New Jersey 08858.
FOR ALL CONTRACTS UNDER $100,000, a bank letter of credit from a local (Effingham County) bank
setting forth all of the conditions herein before stated and signed and attested to by two officers of said
bank and the Contractor shall be acceptable under this section.
UNFORESEEN CONDITIONS
Contractor shall promptly notify Owner and Engineer in writing of any subsurface or latent physical
conditions encountered at the Site which differ materially from those specified or indicated, or which
could be reasonably interpreted from examination of the Site and available subsurface information at
the time of bidding.
Owner will promptly investigate those conditions and will obtain the necessary additional surveys and
tests and furnish copies of results to Contractor.
If it is found that the subsurface or latent physical conditions encountered at the Site differ materially
from those specified or indicated, or which could have been reasonably interpreted from examination of
the Site and available subsurface information at the time of bidding, then a Change Order will be issued
by the Owner incorporating the necessary revisions.
RECORD DOCUMENTS
A. Contractor shall maintain in a safe place at the Site one record copy of all Drawings,
Specifications, Addenda, Written Amendments, Change Orders, Work Change Directives, Field
Test Records, Field Orders, and written interpretations and clarifications in good order and
annotated to show all changes made during construction. These record documents together
with all approved Samples and a counterpart of all approved Submittals shall be available to
Owner for reference. Upon completion of the Work, these record documents and Submittals
shall be delivered to Owner.
B. Receipt and acceptance of record documents will be a prerequisite for final payment on the
Contract.
WARRANTY AND GUARANTEE
A. Contractor warrants and guarantees to Owner that all Work will be in accordance with the
Contract Documents and will not be defective. Prompt notice of all defects shall be given to
Contractor. All defective Work, whether in place, may be rejected, corrected or accepted.
B. No provision in the Contract Documents nor any specified guaranteed time limit shall be
held to limit Contractor's liability for defects to less than the legal limit of liability in
accordance with the Law.
C. All Equipment and Materials furnished by Contractor for the Work shall carry a written
guarantee from the manufacturer or Supplier of such items when called for in the
Specifications. Written guarantees shall be submitted to Owner with other Submittals.
7
DEFECTIVE WORK
The term "defective" is used in these documents to describe Work that is unsatisfactory, faulty, not in
conformance with the requirements of the Contract Documents, or not meeting the requirements of any
inspection, test, approval, or acceptance required by Law or the Contract Documents.
A. Any defective Work may be disapproved or rejected by Owner at any time before final
acceptance even though it may have been overlooked and included in a previous Application
for Payment.
B. Prompt notice will be given by Owner to Contractor of defects as they become evident.
UNCOVERING WORK
A. If any Work is covered contrary to the request of Owner, it shall, if requested by Owner, be
uncovered for Owner's observation and replaced at Contractor's expense.
OWNER MAY STOP THE WORK
A. If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable
materials or equipment, or fails to furnish or perform the Work in such a way that the
completed Work will conform to the Contract Documents, Owner may order Contractor to
stop the Work, or any portion thereof, until the cause for such order has been eliminated;
however, this right of Owner to stop the Work shall not give rise to any duty on the part of
Owner to exercise this right for the benefit of Contractor or any other party.
CORRECTION OR REMOVAL OF DEFECTIVE WORK
A. If required by Owner, Contractor shall promptly, as directed, either correct all defective
Work, whether or not fabricated, installed or completed, or, if the Work has been rejected by
Owner, remove it from the Site and replace it with non-defective Work. Contractor shall bear
all direct, indirect, and consequential costs of such correction or removal (including but not
limited to fees and charges of engineers, architects, attorneys, and other professionals)
made necessary thereby.
ONE-YEAR CORRECTION PERIOD
A. If within one year after the Date of Substantial Completion or such longer period of time as
may be prescribed by Laws or Regulations or by the terms of any applicable special
guarantee required by the Contract Documents or by any specific provision of the Contract
Documents, any Work is found to be defective, Contractor shall promptly, without cost to
Owner and in accordance with Owner's written instructions, either correct such defective
Work, or, if it has been rejected by Owner, remove it from the Site and replace it with non-
defective Work. If Contractor does not promptly comply with the terms of such instructions,
or in an emergency where delay would cause serious risk of loss or damage, Owner may
have the defective Work corrected or the rejected Work removed and replaced, and all
direct, indirect, and consequential costs of such removal and replacement (including but not
limited to fees and charges of engineers, architects, attorneys, and other professionals) will
8
be paid by Contractor. In special circumstances where a particular item of Equipment is
placed in continuous service before Substantial Completion of all the Work, the correction
period for that item may start to run from an earlier date if so provided in the Specifications
or by Written Amendment.
ACCEPTANCE OF DEFECTIVE WORK
A. If, instead of requiring correction or removal and replacement of defective Work, prior to
Owner's recommendation of final payment, if Owner prefers to accept it, Owner may do so.
Contractor shall bear all direct and indirect costs attributable to Owner's evaluation of and
determination to accept such defective Work (such costs to be approved by Owner as to
reasonableness and to include but not be limited to fees and charges of engineers,
architects, attorneys, and other professionals).
OWNER MAY CORRECT DEFECTIVE WORK
A. If Contractor fails within a reasonable time after written notice of Owner to proceed to
correct and to correct defective Work or to remove and replace rejected Work as required by
Owner, or if Contractor fails to perform the Work in accordance with the Contract
Documents, or if Contractor fails to comply with any other provision of the Contract
Documents, Owner may, after seven days' written notice to Contractor, correct and remedy
any such deficiency. In exercising the rights and remedies under this Paragraph, Owner shall
proceed expeditiously.
B. To the extent necessary to complete corrective and remedial action, Owner may exclude
Contractor from all or part of the Site, take possession of all or part of the Work, and
suspend Contractor's services related thereto, take possession of Contractor's tools,
appliances, construction equipment, and machinery at the Site and incorporate in the Work
all Equipment and Materials stored at the Site or for which Owner has paid Contractor but
which are stored elsewhere.
C. Contractor shall allow Owner, Owner's representatives, agents, and employees such access
to the Site as may be necessary to enable Owner to exercise the rights and remedies under
this Paragraph.
D. All direct, indirect, and consequential costs of Owner in exercising such rights and remedies
will be charged against Contractor in an amount approved as to reasonableness by Owner,
and a Change Order will be issued incorporating the necessary revisions in the Contract
Documents with respect to the Work; and Owner shall be entitled to an appropriate
decrease in the Contract Price. Such direct, indirect, and consequential costs will include but
not be limited to fees and charges of engineers, architects, attorneys and other
professionals, all court and arbitration costs, and all costs of repair and replacement of work
of others destroyed or damaged by correction, removal, or replacement of Contractor's
defective Work.
E. Contractor shall not be allowed an extension of the Contract Times because of any delay in
performance of the Work attributable to the exercise by Owner of Owner's rights and
remedies hereunder.
9
SANITARY/STORM SEWER CLEANING AND CCTV INSPECTIONS
A. GENERAL REQUIREMENTS
1. This section includes provision of cleaning operations, inspection, and closed-circuit
television monitoring operations, and all associated work for the sizes and lengths of
sewers encountered.
2. If the specified low flow levels are not achievable using flow through plugs or by
scheduling inspection during low flow hours, the CITY may authorize the inspection
above these flow levels.
3. The CONTRACTOR shall be responsible for any backups in the sanitary/storm sewer
system caused by the cleaning and/or TV operation. Any damage to property, both
public and private, including but not limited to backup into homes, businesses, etc., shall
be repaired, cleaned or replaced to the satisfaction of the owner of such property at no
cost to the CITY.
B. REFERENCES
National Association of Sewer Service Companies (NASSCO):
Pipeline Assessment and Certification Program (PACP) Reference Manual
Recommended Specifications for Sewer Collection System Rehabilitation Standard (2006)
C. DEFINITIONS
Television Inspection: A necessary operation to complete a true-color audio-visual inspection to
verify existing internal sewer line conditions. Furnish labor, materials, equipment, tools, and
other incidental services for CCTV inspection.
D. SUBMITTALS
Submit a written/printed copy of television inspection logs to the Engineer. Logs shall record
defects according to NASSCO's Pipeline Assessment and Certification Program (PACP) or/and
Manhole Assessment and Certification Program (MACP).
Submit 2 copies of visual and audio recording to the Engineer in electronic format. The Engineer
will review the inspections to ensure the required information is provided, and the recording
quality is acceptable, but not for content accuracy. If the Engineer determines the recording is
defective or not adequate quality, the Contractor shall perform CCTV inspection again at the
Contractor's expense.
E. QUALITY ASSURANCE
The television inspection shall be performed one section of line at a time. An individual digital
video file and data file shall be developed for each manhole-to-manhole section. Inspection shall
be performed in accordance with NASSCO's Pipeline Assessment and Certification Program
(PACP) and/or Manhole Assessment and Certification Program (MACP).
F. CLEANING EQUIPMENT
The CONTRACTOR shall provide all equipment necessary for proper flushing and cleaning of the
sewers of the sizes indicated prior to television inspection. Hydraulic high pressure sewer
10

With GovernmentContracts, you can:
LINENS for Valley Hi Nursing and Rehabilitation Department: Procurement Division, Valley Hi Nursing
McHenry County
Bid Due: 11/20/2026
Bid Solicitation # Alternate Id Contract/Blanket # Buyer Description Bid Opening Date Bid
State Government of Illinois
Bid Due: 1/20/2027
Status Ref# Project Close Date Days Left Action Open P-23001 P-23001-GENERAL CONTRACTOR SERVICES
Chicago Park District
Bid Due: 12/31/2027
Status Ref# Project Close Date Days Left Action Open P-23001 REQUEST FOR QUALIFICATIONS
Chicago Park District
Bid Due: 12/31/2027