REVERSE OSMOSIS, DEGASIFICATION AND ION EXCHANGE SYSTEM SUPPORT SERVICES

Location: California
Posted: Jan 29, 2026
Due: Feb 27, 2026
Agency: City of Pasadena
Type of Government: State & Local
Category:
  • J - Maintenance, Repair, and Rebuilding of Equipment
Solicitation No: 2026-IFB-LM-0055
Publication URL: To access bid details, please log in.


Project ID: 2026-IFB-LM-0055

Title: REVERSE OSMOSIS, DEGASIFICATION AND ION EXCHANGE SYSTEM SUPPORT SERVICES

Addenda: 0

Release Date: 1/29/2026

Due Date: 2/27/2026

Follow
REVERSE OSMOSIS, DEGASIFICATION AND ION EXCHANGE SYSTEM SUPPORT SERVICES
Competitive Bid
Water & Power Department, Power Supply
237 , 2379 , 23799 , 237990 , 5413 ... show all
Project ID: 2026-IFB-LM-0055
Release Date: Thursday, January 29, 2026
ยท Due Date: Friday, February 27, 2026 2:00pm
Posted Thursday, January 29, 2026 12:00pm
All dates & times in Pacific Time
Draft Response Events RSVP No Bid
Time Remaining: 28 days, 19 hours, 42 minutes


Post Information

Posted At:Thu, Jan 29, 2026 12:00 PM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

Glenarm Power Plant

The City of Pasadena produces approximately 8 million gallons of demineralized and deionized (purified) water annually at the City's Glenarm Power Plant for use in electric power production. The technology used to produce and maintain this water includes reverse osmosis (RO), degasification and ion exchange. This solicitation seeks a qualified vendor, with subject matter expertise in water purification technologies, to support the power plant's water treatment processes.



Background

Glenarm Power Plant

The City of Pasadena Glenarm Power Plant consists of five natural-gas fueled combustion turbines (GT1, GT2, GT3, GT4 and GT5) equipped with generators that produce electrical power. GT5 is also equipped with a once through steam generator and steam turbine. Purified water is produced at the Glenarm Power Plant for the following uses:

Injection into the gas turbine engine combustors to suppress oxides of nitrogen (NOx) in the engine exhaust

Injection into the low or high pressure air compressors to enhance power output (Spray Intercooling)

Makeup to the GT5 steam condensate cycle

Cleaning of energized power lines

The Glenarm Power Plant Gas Turbines, and water treatment processes, operate intermittently and seasonally in response to peak electrical power demand as shown in the table below:



Timeline

Release Project Date:
January 29, 2026
Pre-Bid Meeting (Non-Mandatory):
February 11, 2026, 8:30am
Broadway Power Plant Gate 7 85 E. State Street, Pasadena, CA 91105
Question Submission Deadline:
February 19, 2026, 3:00pm
Bid Submission Deadline:
February 27, 2026, 2:00pm
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Project ID: 2026-IFB-LM-0320 Title: Furnish and Deliver Utility and Miscellaneous Street Repairs... , ...

City of Pasadena

Bid Due: 6/12/2026

...Project ID: 2026-IFB-LM-0320 Title: Furnish and Deliver Utility and Miscellaneous Street Repairs... ... ...

City of Pasadena

Bid Due: 6/23/2026

...Project ID: 2026-IFB-LM-0046 Title: Replace CAISO Remote Intelligent Gateway (RIG) and CAISO... , ...

City of Pasadena

Bid Due: 6/08/2026

...Project ID: 2026-IFB-LM-0155 Title: Hill Ave Library Roof Replacement and Structural Connections... , ...

City of Pasadena

Bid Due: 6/04/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.