Big O’Neal Sewer Subbasin Rehabilitation Phase 4 (Division C)
| Location: |
South Carolina |
| Posted: |
Feb 27, 2026 |
| Due: |
Mar 31, 2026 |
| Agency: |
State of South Carolina - State Fiscal Accountability Authority(SFAA) |
| Type of Government: |
State & Local |
| Category: |
- Y - Construction of Structures and Facilities
|
| Solicitation No: |
D&S 25003 |
| Publication URL: |
To access bid details, please log in. |
Project Name:
Big O’Neal Sewer Subbasin Rehabilitation Phase 4 (Division C)
Agency/Owner:
Ad Publish Date:
February 27, 2026
Project Number:
D&S 25003
# of Bid Copies:
Bid/Submittal Date & Time:
March 31, 2026 - 10:00am
Project Location:
Project Delivery Method:
Other
Construction Cost Range:
N/A
Agency Project Coordinator:
Dunn & Shirley, LLC | Keith Dunn, PE/PLS
Email:
Telephone:
(864)-245-0569
Appr. 2,484 LF Pipe Burst and 3,292 LF Cured-In Place Pipe of varied sizes (8, 10, & 12 inch) of sewer rehab., 31 lateral connections, 86 VF of manhole rehab, misc. point repairs, pavement restoration, and all restoration. The bid is divided into a Base Bid with three (3) add alternates. Bidders must comply with all State and Federal requirements identified in the bid documents, including American Iron and Steel (AIS), Davis-Bacon Act and Related Acts.
Documents May Be Obtained From:
Daily notification on new contract opportunities
With GovernmentContracts, you can:
- Find more opportunities and win more business
- Receive daily alerts for all new bid opportunities
- Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.