Parrott Drive Sanitary Sewer Project- Phase 1

Location: California
Posted: Feb 9, 2026
Agency: Hillsborough town
Type of Contract: Awards
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.
Parrott Drive Sanitary Sewer Project- Phase 1

Bid Opening Summary
This project involves the replacement, rehabilitation and new installation of approximately 3,400 linear feet of 8-inch sanitary sewer pipes, within the public right-of-way and easement area. Pipe installation methods may include trenching or horizontal directional drilling (HDD) and pipe-bursting. The project also includes manhole removal/replacement, new manhole installation and safely removing and disposing of asbestos concrete pipes (ACP).

Pre-bid Meeting: October 1, 2025 at 11:00am, Public Works Corporation Yard, 1320 La Honda, Hillsborough, CA 94010. Pre-Bid Meeting Notes
Bids Due: October 15, 2025 at 2:00pm to Town of Hillsborough City Hall located at 1600 Floribunda Ave, Hillsborough, CA 94010
Engineering Estimate: $1,450,000
Contact: Javad Ghaffari, jghaffari@hillsborough.net , 650-375-7510
Bid Documents:

Attachment Preview

TOWN OF
HILLSBOROUGH
HILLSBOROUGH, CALIFORNIA, 94010
PARROTT DRIVE SANITARY SEWER PROJECT-PHASE-1
Addendum No.
2
NOTICE IS HEREBY GIVEN to all bidders and interested parties that the Advertisement
of Proposals, Bid Proposals, Contract Documents, and Specifications of the subject
project are hereby modified only insofar as the following clarifications, corrections,
changes, and amendments are concerned. The Bidder MUST acknowledge the
receipt of this addendum and attach a signed copy to the Proposal section of the
Contract Documents.
QUESTIONS
1- Sheet 9 / 10: Is the RIM of 315.01 for Manhole 14K15 at STA 42+36 correct? The
elevation profile does not match.
RESPONSE: Rim elevation for Manhole 14K15 is 315.01.
2- Can the laterals be replaced by pipe bursting?
RESPONSE: Yes, laterals can be pipe burst with fused HDPE
3- Where are the 2 EA manholes to be rehabilitated per Bid Item 17, 18 & 19 located?
RESPONSE: These are allowances for the City to field direct rehabilitation if
needed.
1
4- Spec 33 05 07 refers to conductor casings and annular space grouting, and that
the lengths of the conductor casings are shown on the drawings, which they are not.
Are conductor casings and annular space grouting required for the HDD installation?
RESPONSE: No, the soil condition within the project area doesn’t dictate the
use of a conductor.
5- Please provide the entire Geotechnical Soils Report as referenced in the
specifications.
RESPONSE: A copy of the Geotechnical report is posted in the link below:
https://www.barkerblueplanroom.com/projects/373/plan-holders/parrott-drive-
sanitary-sewer-project-phase-1
6- The Town Standard Trench detail C-16 states that grinding & paving is required.
Can we saw cut in lieu of grind? In addition is fabric in the pavement required?
RESPONSE: Saw-cutting is acceptable in lieu of grinding. There is no need to
use fabric for paving restoration in this project.
7- Pre-Bid Meeting Questions and Clarifications
The following items were discussed during the pre-bid meeting:
Question 1 Asbestos Pipe Disposal
Bidders inquired about the availability of disposal facilities for asbestos pipe materials,
noting the limited options in Northern California.
Staff subsequently confirmed that a facility in Reno, Nevada will accept asbestos
pipes.
Associated costs are as follows:
o Transport: $250/hour
o Disposal: $65/cubic yard
Question 2 Horizontal Directional Boring and Geotechnical Data
Bidders inquired about potential subsurface conditions along Parrott Drive, specifically the
possibility of encountering hard rock at depths of 20 to 25 feet.
Staff confirmed that the geotechnical report identified the presence of sandstone at
one boring location.
2
A summary of the geotechnical investigation is included as an attachment to the bid
documents.
Clarification Plan Note Correction
A correction is hereby issued to the profile drawing on page 10 of the plans:
The note reading “6-INCH VCP TO 6-INCH HDPE” shall be revised to read: “6-
INCH VCP TO 8-INCH HDPE.”
The following Addenda were issued, modifying the Project Manual and
Contract Documents:
Addendum No.2, Issued on October 10, 2025
ADDENDUM ACKNOWLEDGEMENT
Bidder acknowledges receipt of this addendum, which shall be attached to the proposal.
CONTRACTOR REPRESENTATIVE
DATE
3
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Project ID: IFB No. PW-0300 Title: Laurent St Sewer Rehabilitation Addenda: 0 Release ...

City of Santa Cruz

Bid Due: 6/16/2026

...Nadeau Trunk Sewer Rehabilitation Category: Construction Bids Project Number: 01-P-0066 Post... reinforced concrete ...

Los Angeles County Sanitation Districts

Bid Due: 6/02/2026

...Nadeau Trunk Sewer Rehabilitation Category: Construction Bids Project Number: 01-P-0066 Post... reinforced concrete ...

Los Angeles County Sanitation Districts

Bid Due: 6/02/2026

...Project ID: 25-110-RFP Title: Bryte Sewer Pump Station Rehabilitation Addenda: 1 Release Date: ...

City of West Sacramento

Bid Due: 6/25/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.