MS6-M26001 - 2026 Street Maintenance - Phase 1

Location: Kansas
Posted: Jan 14, 2026
Agency: City of Lawrence
Type of Contract: Awards
Type of Government: State & Local
Category:
  • F - Natural Resources and Conservation Services
  • J - Maintenance, Repair, and Rebuilding of Equipment
Publication URL: To access bid details, please log in.


Project ID:

Title: MS6-M26001 - 2026 Street Maintenance - Phase 1

Addenda: 0

Release Date: 1/14/2026

Due Date: 2/3/2026

Follow
MS6-M26001 - 2026 Street Maintenance - Phase 1
Invitation For Bid
MSO - CMED
91350 , 91384 , 91395 , 91396 , 96861
Project ID: CIFB-2600001
Release Date: Wednesday, January 14, 2026
· Due Date: Tuesday, February 3, 2026 3:30pm
Posted Wednesday, January 14, 2026 8:00am
All dates & times in Central Time
Draft Response No Bid19 days, 19 hours, 59 minutes


Post Information

Posted At:Wed, Jan 14, 2026 8:00 AM
Sealed Bid Process:Yes (Bids Sealed / Pricing Sealed)
Private Bid:No
Overview


Summary

The work to be done under this contract includes: Mill and overlay, microsurfacing, and pavement patching
across the City of Lawrence. The project also includes sidewalk ramps and minimal concrete pavement
replacements. The project includes, but is not limited to the following approximate quantities of work: 10,844
SY of milling, 1,518 tons of asphalt surface course (2”), 108,003 SY of microsurfacing, 3,700 LF of curb and
gutter, 321 SY of concrete pavement, 724 SY of sidewalk, and 3,789 SF of sidewalk ramps.

Schedule:
Area 1(location on title page of construction plans)- No schedule restrictions. The area may be worked on
concurrently with other project locations.
Area 2 (location on title page of construction plans)2- Contractor Shall start after July 15, 2026 and needs to be
coordinated with "MS-230027 - Maple Lane Storm, Sanitary and Watermain Improvements" project for traffic
control impacts/detour routing likely anticipated work on 19th Street between Maple Lane and Harper Street as
part of that project. Harper Street work may not conflict with the Douglas County Fair (Approximately July 27,
2026 - August 2, 2026) and can start after the fair.
Area 3 (location on title sheet of construction plans)- No schedule restrictions. The area may be worked on
concurrently with other project locations.



Timeline

Release Project Date:
January 14, 2026
Question Submission Deadline:
January 23, 2026, 12:00pm
Response Submission Deadline:
February 3, 2026, 3:30pm
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Bid 63 Pavement and Storm Sewer Project SW Oakley from SW 10th to ...

City of Topeka

Bid Due: 6/02/2026

...Bid 63 Pavement and Storm Sewer Project SW Oakley from SW 10th to ...

City of Topeka

Bid Due: 6/02/2026

...basins to enhance maintenance access and safety. L. Storm Drain Isolation near Ferric ...

Johnson County

Bid Due: 6/25/2026

...basins to enhance maintenance access and safety. L. Storm Drain Isolation near Ferric ...

Johnson County Kansas

Bid Due: 6/25/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.