Missouri Department of Transportation
Ed Hassinger, Director
1.888.ASK MODOT (275.6636)
June 10, 2026
Dear Consultant:
The Missouri Highways and Transportation Commission is requesting the services of a consulting
engineering firm to perform the described professional services for the project included on the attached list.
If your firm would like to be considered for these consulting services, you may express your interest by
responding to the appropriate office, which is indicated on the attachments. Limit your letter of interest to no
more than three pages. This letter should include a statement to indicate your firm’s understanding of the
project. It should also include any other information which might help us in the selection process, including
key personnel you would assign to the project and the backgrounds of those individuals, and any sub-
consultants you would propose to use, and an indication of your firm’s approach to promoting and
developing a diverse workforce. MoDOT is committed to reflecting the diversity of the communities we
serve and we expect our partners to do the same. We will utilize the consultant information already on file
so we will not need a lengthy submittal of other general company information. In addition, please attach one
page with detailed information on similar projects that your key personnel have worked on. Indicate the role
your key personnel played in the projects and include reference contact information.
DBE firms must be certified by the Missouri Department of Transportation in order to be counted as
participation towards an established DBE Goal. We encourage DBE firms to submit letters of interest as
prime consultants for any projects they feel can be managed by their firm. We also encourage both DBE
firms and non-DBE firms to consider joining MoDOT’s Mentor/Protégé program whenever possible as part
of a MoDOT project.
MoDOT will evaluate firms based on: Project Understanding & Innovation, Past Performance,
Qualifications of Personnel Assigned, General Experience of Firm, Familiarity/Capability, Accessibility of
Firm & Staff. Firm’s not providing a response on approach to workforce diversity will be considered non-
responsive to this solicitation. Firm’s that are not current on all of the required prequalification categories
found in MoDOT’s Approved Consultant Prequalification List at the date of the solicitation expiration will
be considered non-responsive.
We request all letters be received by 3:00 pm, June 29th, 2026 at the following email address:
Seiji.Shimbo@modot.mo.gov
Sincerely,
Sarah Kleinschmit, P.E.
State Design Engineer
Attachment
!
DISTRICT OFFICES
Southeast District
Donnie Brown – District Engineer
Missouri Department of Transportation
2675 N. Main
Sikeston, MO 639801
Contact
Seiji Shimbo – Project Manager
573-380-9765
seiji.shimbo@modot.mo.gov
Garret Hager – Structural Project Manager
573-526-1505
garrett.hager@modot.mo.gov
Email responses are encouraged.
Southeast District
Butler County
Job No:
JSE0210, JSE0211, & JSE0226
Location:
Rte. HH, Rte. HH, Rte. 142
Proposed Improvement:
Bridge Replacements (P0256, P0258, S0523)
Length:
See information documents
Approximate Construction Cost: $2,587,000
DBE Goal (if applicable)
0%
Consultant Services Required:
Right of Way: Consultant to provide title commitments for
affected properties.
Environmental: RES submittals at milestones and
informational support as requested.
Surveying: Perform all survey pickup work. Professional land
surveying to establish land corners, property lines, monument
new right of way, prepare boundary surveys and write deeds
as necessary.
Roadway Design: Consultant to prepare all preliminary, right
of way, final roadway design and plan preparation as
necessary to submit final roadway plans, specifications, and
estimates. (PS&E). Hydraulic analysis of all drainage
structures, reporting and coordination with any drainage
districts, municipalities, railroad and other government
agencies.
The following item may be completed through supplemental
agreement.:
Bridge: Tentatively – All preliminary bridge design, final
bridge design and plan preparation as necessary to submit
final bridge plans, specifications, and estimates. (PS&E).
Hydraulic analysis of all drainage structures, reporting and
coordination with any drainage districts and railroad as
needed.
Other Comments:
Interviews or presentations will not be required for
the consultant selection.
Tentative Date of Consultant Selection – 7/15/2026
Tentative Letting Date – 10/1/2028
!
Rating Criteria w/Weighted Values
Project Understanding & Innovation
25 Points Max
Past Performance
25 Points Max
Qualifications of Personnel Assigned
20 Points Max
General Experience of Firm
10 Points Max
Familiarity/Capability
10 Points Max
Accessibility of Firm & Staff
10 Points Max
100 Points Max Total
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.