District 9 – Canopy and Yard

Location: Idaho
Posted: Nov 4, 2026
Due: Nov 12, 2026
Agency: State Government of Idaho
Type of Government: State & Local
Category:
  • F - Natural Resources and Conservation Services
Solicitation No: FM92713
Publication URL: To access bid details, please log in.
Number Name Status Bid Close Public Bid Opening Resources & Details Bid Results
FM92713 District 9 – Canopy and Yard Open 11/12/2026

01:59:59 P.M. MT
11/12/2026

02:00:00 P.M. MT
Bid Packet

Attachment Preview

BIDDING REQUIREMENTS &
CONDITIONS OF AGREEMENT

BIDDING REQUIREMENTS &
CONDITIONS OF AGREEMENT
ITD - District 9
FM92713
Canopy & Yard
Architect
CSHQA
200 Broad Street
Boise, ID 83702
(208) 343-4635
Construction Manager/General Contractor
CM Company, Inc.
431 West McGregor Drive
Boise, Idaho 83705
(208) 384-0800

TABLE OF CONTENTS
PART A - BIDDING REQUIREMENTS
Part A:1 Advertisement for Bids
Part A:2 Request for Proposal and Bid
Part A:3 Notice Concerning Public Works Contractors State Licenses
Part A:4a Instructions to Bidders
Part A:4b Bid Envelope Label
Part A:5 Bidders Checklist
Part A:6 Bid Package Index
Part A:7 Contractor Bid Proposal Forms
Part A:8 Bidder Certification Form (Not Used - See Part A:7 for Bidder Certifications)
Part A:9 Construction Schedule
Part A:10 Substitution Request Form
Part A:11 Subcontractor Prequalification Form
PART B - CONDITIONS OF AGREEMENT
Part B:1 CM/GC Contractor-Owner Agreement
Part B:2 General Conditions to Owner Agreement (Not Used - See Part B:1)
Part B:3 Subcontract with Terms and Conditions
Part B:4 Purchase Order with Terms and Conditions
Part B:5 Temporary Facilities and Controls
Part B:6 Consent of Surety to Final Payment (if required)
Part B:7 Insurance Requirements
Part B:8 Contractor Affidavit Concerning Taxes
Part B:9 Contractor Affidavit Concerning Alcohol and Drug-Free Workplace
Part B:10 Subcontractor's Application for Payment
Part B:11 WH-5 Public Works Contract Report
ITD - D9 Canopy & Yard TOC

***The original advertisement published in the Statesman indicated that bids would be opened by
ITD on November 11. However, due to the Veterans Day holiday, the bid opening was rescheduled
to November 12, 2006, at 2:00 p.m.

Part A:1
ADVERTISEMENT FOR BIDS
Sealed bids will be received by CM Company for the ITD - D9 Canopy & Yard project. Bids will be
received, opened, and read aloud by CM Company and the Idaho Department of Transportation at the CM
Company's Office, located at 431 W. McGregor Dr. Boise, ID 83705, until November 12, 2026, at 2:00
PM local time.
***The original advertisement published in the Statesman indicated that bids would be opened by
ITD on November 11. However, due to the Veterans Day holiday, the bid opening was rescheduled
to November 12, 2006, at 2:00 p.m.
Bidders and other interested parties are invited to watch the bid opening via Microsoft Teams:
https://teams.microsoft.com/meet/2609114102974423?p=sQCxKZpRMTdlkPYZGy
Drawings and specifications, including bidding documents and conditions of agreement, are available
electronically via the Dropbox link below:
https://www.dropbox.com/scl/fo/roynx1zxnmfluhhlbvzsa/AEuCKLSKAJT4W9_t6RVe0l8
?rlkey=7d3ead2j8mla246f8lgorn64m&st=z990sxug&dl=0
All bids must be submitted on the forms furnished and must be signed by the bidder in pen and ink
with his name and mailing address. All bids must be enclosed in a sealed envelope plainly marked with the
bid package number and project title noted above.
Bids received after the time set for opening shall not be considered and no bidder may withdraw his bid
after the hour set for opening or before award of contract unless said award is delayed for a period
exceeding sixty (60) days.
CM Company reserves the right to reject any or all bids, waive any informalities, or to accept the bid or bids
deemed to be in the best interest of Idaho Transportation Department.
Each trade package will be treated as a stand-alone bid. Each bid must be marked with the bid package
number outlined in the Instructions to Bidders. Firms may submit bids for multiple trade packages, but each
bid must be submitted independently (separate bid envelope). Contractors wishing to submit bids must
hold a current Public Works Contractors License commensurate with the size of the subcontract
amount, unless the subcontract amount is less than $100,000.
Bidders shall be registered in the State of Idaho, in accordance with the Department of Self-Governing
Agencies as a "Contractor" licensed in the State of Idaho, in accordance with provisions of an act known
as "Public Works Contractor's State License Law, Title 54, Chapter 19, Idaho Code Amended". The term
"Public Works Contractors" includes the general, sub or specialty contractor.
Before any contract is awarded for the work contemplated herein, CM Company shall conduct such
investigation, as it deems necessary to determine the performance record and ability of the apparent low
bidder to perform the type and size of project specified under this contract. Upon request, the bidder shall
submit such information as deemed necessary for such evaluation.
End of Advertisement for Bids
ITD - D9 Canopy & Yard A:1 Advertisement for Bids
Page 1 of 1

Part A:2
REQUEST FOR PROPOSAL AND BID
Bid Date: November 12, 2026, at 2 pm
From: CM Company, Inc.
431 W McGregor Drive,
Boise, ID 83705
You are hereby invited to submit a bid for goods and services for:
PROJECT TITLE: ITD - D9 Canopy & Yard
PROJECT LOCATION: 3311 W. State Street Boise, Idaho 83703
There will not be a Pre-Bid Conference for this project.
Questions regarding the Request for Proposal and Bid must be submitted in writing and received
by CM Company, Inc, NO LATER THAN Wednesday, November 4, 2026, at 5:00 PM. Questions
received after this date will not be considered.
Idaho Transportation Department, CM Company, Inc. or CSHQA will not be responsible for verbal
interpretations. Questions will be answered by written addenda and be emailed to all Bidders on the plan
holder list. All addenda issued during the bid period will be incorporated into the Contract. Addenda issued
prior to bidding shall be acknowledged on the Bid Form. Failure to acknowledge addenda may be cause
for rejection of bid as non-responsive.
Submit questions in writing via email or fax to:
CM Company, Inc.
Attn: Jairo Orellana
431 W McGregor Dr.
Boise, ID 83705
F: 208-345-5323
jorellana@cmcompany.com
ITD - D9 Canopy & Yard
A:2 Request for Proposal and Bid
Page 1 of 1

Part A:3
NOTICE CONCERNING PUBLIC WORKS CONTRACTORS STATE LICENSES
The Idaho Law requires that prime contractors, subcontractors, and specialty contractors alike must hold
licenses as "Public Works Contractors" before submitting bids on public works projects.
The only exception to the basic rule is that a bidder on a project that is to be financed by a direct federal grant-
in-aid program need not hold a license to bid, however, he/she must obtain a license PRIOR to the AWARD
on any contract or subcontract or the performance of any work. (Use of federal "revenue sharing" funds do
not, however, qualify a project as being financed in whole or in part by a direct federal grant-in-aid program.)
Some projects may attract general contractors, subcontractors, and specialty contractors from outside the
state who may not be familiar with Idaho licensing requirements. In these instances, it is especially important
that reasonable steps be taken to ensure that all prospective bidders be made aware of licensing requirements
before the bid opening. The following list of agency references is included for the general information of all
interested parties.
Refer to Idaho Statute 54-1904 for current public works contractors state license limits.
SUBJECT ADDRESS/TELEPHONE
FOREIGN CORPORATION (208) 334-2301 Secretary of State
Statehouse - Room 203
Boise, Idaho 83720
LICENSING - PUBLIC WORKS (208) 334-4057 Public Works Contractors
CONTRACTORS State License Bureau
1090 E. Watertower Street
Meridian, Idaho 83642
LICENSING - ELECTRICAL (208) 334-2183 Electrical Safety Bureau Division
CONTRACTORS & 277 North 6th Street
JOURNEYMEN Boise, Idaho 8372
TAXES - (208) 334-7660 Tax Commission
INCOME/WITHHOLDING 800 Park Boulevard
Boise, Idaho 83706
WORKMEN'S COMPENSATION (208) 334-6000 Industrial Commission
317 Main Street
Boise, Idaho 83702
UNEMPLOYMENT (208) 334-6316 State Department of Employment
COMPENSATION 317 Main Street
Boise, Idaho 83702
LABOR AND LIEN LAWS (208) 334-2327 Department of Labor & Industrial Services
277 North 6th Street
Boise, Idaho 83702
ITD - D9 Canopy & Yard A:3 Notice Concerning Public Works Contractors State Licenses
Page 1 of 1

Part A:4a
INSTRUCTIONS TO BIDDERS
GENERAL PROVISIONS
HEADINGS: Headings used in these Instructions are for convenience only.
REJECTION OF BIDS, WAIVER OF INFORMALITIES OR CANCELLATION: Prior to the effective date of
a Subcontract, CM Company Inc. shall have the right to accept or reject all bids, to waive any minor
deviations/informalities or to cancel the bid.
ORAL INFORMATION: Questions concerning a bid must be directed in writing to CM Company no later
than November 4, 2026, at 5:00 PM local time unless provided otherwise via an addendum. Oral
information is not binding and any reliance by a bidder on any oral information or representation is at the
bidder's sole risk. Any information given a prospective bidder in response to a written question will be
provided to all prospective bidders by an addendum, if such information is necessary for purposes of
submitting a bid or if failure to give such information would be prejudicial to uninformed bidders.
PUBLIC RECORDS: The Idaho Public Records Law, Sections 9-337 through 9-348, Idaho Code, allows
the open inspection and copying of public records. Public records include any writing containing
information relating to the conduct or administration of the public's business prepared, owned, used or
retained by a State or local agency regardless of the physical form or character. Unless exempted by the
Public Records Law, your bid will be a public record subject to disclosure under the Public Records Law.
Any questions regarding the applicability of the Public Records Law should be addressed to your legal
counsel prior to submission.
FORM OF AGREEMENT: Unless otherwise specified in the bid documents, the Subcontract between the
successful bidder and CM Company shall be the 'Standard Subcontract Terms of Agreement.' See part
B:3 of Standard Subcontract Form.
PERFORMANCE AND PAYMENT BONDS: Once a specified Subcontractor is selected, CM Company
reserves the right to require a payment and performance bond as security from the Subcontractor until job
completion.
BID SUBMISSION PROCESS
BID DOCUMENTS: The bid documents are available as stated in the Advertisement for Bid. The
responsibility is on the bidder to use a complete set of bid documents to prepare its bid and neither CM
Company, the Owner nor the Design Professional shall incur any liability for the bidder's failure to do so.
Bidders obtain no ownership interest or any use rights, except to use in preparation of their bid, by
issuance of the bid documents.
Anything mentioned in the specifications and not shown on the Drawings or shown on any Drawings and
not mentioned in Specifications, shall be of like effect as if shown or mentioned in both. In case of
discrepancy in the figures, in the Drawings or in the Specifications, the matter shall be promptly submitted
to the CM/GC. Failure to report a conflict in the Contract Documents prior to bidding shall be deemed
evidence that the Bidder has elected to proceed in the more expensive matter.
Bidders and Sub-bidders shall field verify all dimensions pertaining to the Work and shall be responsible
for the determination of all quantities of materials required for the completion of the Work. The bidder
shall not rely on the scale drawings of the Bidding Documents in his determination of required materials
quantities. No allowance shall be made for Bidder's failure to field-verify dimensions.
If a deposit is required, the deposit will be returned to a bidder returning the complete bid documents in
good condition no more than ten (10) days of the bid opening date and the amount of any deposit
returned may be reduced if the bid documents returned are not complete or are damaged. A bidder
awarded a Subcontract may also keep the bid documents and any deposit will be returned.
ITD - D9 Canopy & Yard A:4a Instructions to Bidders
Page 1 of 5

Part A:4a
ADDENDA: In the event it becomes necessary to revise any part of the bid documents, addenda will be
issued. Information given to one bidder will be available to all other bidders if such information is
necessary for purposes of submitting a bid or if failure to give such information would be prejudicial to
uninformed bidders. It is the bidder's responsibility to check for addenda prior to submitting a bid. A bidder
is required to acknowledge receipt of all addenda by identifying the addenda numbers in the space
provided on the bid proposal form. Failure to do so may result in the bid being declared non-responsive.
No addenda will be issued less than four (4) calendar days before the closing date unless the bid closing
date is extended.
REVIEW: It is the bidder's responsibility to review the bid documents and compare them as needed,
including with regard to any other work that is or may be under construction that might affect the bidder or
its work, to examine the site and local conditions and to report, in writing, any questions, errors,
inconsistencies or ambiguities to CM Company.
PRODUCTS SPECIFIED AND PROPOSED SUBSTITUTIONS: Materials, products or equipment, if
specified by name or manufacturer, establish the standard of quality required and that must be met by
any proposed substitution. Requests for substitutions must be made in writing to CM Company or the
Design Professional no later than November 4, 2026, at 5:00 PM local time unless provided otherwise
via an addendum. Such requests must provide detailed information to allow the Design Professional to
determine if the proposed substitution is acceptable, including drawings or performance or test data and a
detailed statement of how the substitution would change any other part of the Work. It is the bidder's
obligation to satisfy this requirement and the Design Professional's decision shall be final. To be allowed,
substitutions must be approved in an addendum to the bid documents.
BID FORM: Bids must be submitted on the bid proposal forms, or copies of forms, furnished by CM
Company. Bids submitted must contain an original signature in ink. The person signing the bid must initial
any and all changes appearing on the bid form. If the bidder is a corporation or other legal entity, the bid
form must be signed by an authorized designee. See Part A:6 of bidding requirements.
BID PRICES: The bid form may require bidders to submit bid prices for one (1) or more items on various
bases, including lump sum base bid, lump sum bid alternate prices, unit prices or any combination
thereof. Bid amounts shall be expressed in words and numbers. The amount in words shall prevail if there
is a discrepancy.
ALTERNATES: If the solicitation includes alternate bid items or unit prices, failure to bid on the alternates
or unit prices may disqualify the bid. If bidding on an alternate does not change the base bid, indicate by
"No Change." If bidding on all items is not required by the Contract Documents, bidders must affirmatively
indicate that they are not bidding on those items.
TIME FOR SUBMISSION: Bids must be submitted on or before the time specified in the Invitation to Bid.
Any bid submitted late will be rejected.
SEALED ENVELOPE: Bids shall be submitted in a sealed envelope with the following clearly printed on
the outside of the envelope: the Project name; the bid package number; the name and address of the
bidder; and a statement, such as "BID ENCLOSED" to indicate that it is a bid. See attached example
label.
MAILED BIDS: When bids are mailed or shipped, the sealed envelope containing the bid shall be
enclosed in a separate mailing envelope with the notation "SEALED BID ENCLOSED" on the face
thereof. If mailed, the mailing envelope shall be addressed as follows:
Sealed Bid Enclosed - ITD - D9 Canopy & Yard
431 W. McGregor Dr.
Boise, ID 83705
Attn: Jairo Orellana
ITD - D9 Canopy & Yard A:4a Instructions to Bidders
Page 2 of 5

Part A:4a
It is the bidder's responsibility to ensure that its bid is delivered to the place designated for receipt on or
before the specified closing time. CM Company assumes no responsibility for delays in the delivery of
mail by the U.S. Post Office or private couriers. Bidders should be advised the intra-state mail system
may increase delivery time from arrival at Central Postal to the place designated for receipt and should
plan accordingly. LATE SUBMISSIONS WILL BE REJECTED, WILL NOT BE OPENED AND WILL BE
RETURNED TO THE BIDDER. NO DEVIATIONS WILL BE ALLOWED.
BID CLOSING DECLARED: Immediately prior to the bid opening, the CM Company representative will
declare the official bid closing. Any part of a bid not received prior to the bid closing declared by the
designated representative will not be considered and will be returned to the bidder unopened. All bids
shall be taken under advisement.
EXECUTIVE ORDER 2009-10: Bidder shall warrant that the bidder does not knowingly hire or engage
any illegal aliens or persons not authorized to work in the United States; bidder shall take steps to verify
that it does not hire or engage any illegal aliens or persons not authorized to work in the United States;
and that any misrepresentation in this regard or any employment of persons not authorized to work in the
United States constitutes a material breach and shall be cause for the imposition of monetary penalties
and/or termination of any Subcontract resulting from this bid.
LEGAL RESIDENCY REQUIREMENT: By submitting a bid, the bidder attests, under penalty of perjury,
that he (the bidder) is a United States citizen or legal permanent resident or that it is otherwise lawfully
present in the United States pursuant to federal law. Prior to being issued a Subcontract, the bidder will
be required to submit proof of lawful presence in the United States in accordance with 67-7903, Idaho
Code.
PUBLIC WORKS CONTRACTOR'S LICENSE: This Project is not financed in whole or in part by federal
funds. Bids will be accepted from those Subcontractors only (subcontractors and/or specialty contractors)
who, prior to the bid opening, hold current licenses as public works contractors in the State of Idaho.
BID MODIFICATION
PRIOR TO BID CLOSING: If a bid has been submitted, it may be modified by the submission of a written
document contained in a separate sealed envelope marked "Bid Modification from [Name of Bidder] for
Idaho Transportation Department". THE DOCUMENT MODIFYING THE BID MUST BE SIGNED IN INK
BY AN AUTHORIZED REPRESENTATIVE OF THE SUBMITTING BIDDER. CM COMPANY
RESERVES THE RIGHT TO REQUIRE PRESENTATION OF EVIDENCE SATISFACTORY TO IT TO
ESTABLISH THE AUTHORITY TO ACT ON BEHALF OF THE SUBMITTING BIDDER. NO OTHER
FORM OF MODIFICATION (INCLUDING TELEPHONE, FACSIMILE OR ELECTRONIC MAIL) WILL BE
ACCEPTED. AFTER BID CLOSING, NO BID MAY BE MODIFIED EXCEPT IN STRICT ACCORDANCE
WITH THESE INSTRUCTIONS OR APPLICABLE LAW.
BIDDER'S REPRESENTATIONS
REPRESENTATIONS UPON SUBMITTING A BID: By submitting its bid, a bidder represents and
warrants the following:
1. The person signing the bid is authorized to bind the bidder;
2. It has all required licenses, permits or other authorizations necessary to submit its bid;
3. It has taken steps necessary to ascertain the nature and location of the Work and has
investigated and satisfied itself as to the general and local conditions which can affect the Work
or its cost, including but not limited to: (i) conditions bearing upon transportation, disposal,
handling and storage of materials; (ii) the availability of labor, water, natural gas, electric power
and roads; (iii) uncertainties of weather, river stages or similar physical conditions at the site; (iv)
the conformation and conditions of the ground; and (v) the character of equipment and facilities
needed preliminary to and during the Work;
ITD - D9 Canopy & Yard A:4a Instructions to Bidders
Page 3 of 5

Part A:4a
4. It has satisfied itself as to character, quality and quantity of surface and subsurface materials or
obstacles to be encountered insofar as this information is reasonably ascertainable from an
inspection of the site, including exploratory work done by the Owner as well as from the drawings
and specifications provided as part of the bid package, and that any failure of the bidder to take
such actions will not relieve the bidder from responsibility for estimating properly the difficulty and
cost of successfully performing the Work;
5. It has received, read and reviewed the Subcontract, has submitted any questions in writing
regarding the same and has received an answer to such questions;
6. Its bid is based upon the requirements of the Subcontract without exception;
7. It is in compliance with Title 18, Chapter 83, Idaho Statute, Sexual Offenders Registration
Notification and Community Right-To-Know Act.
8. Its bid is in compliance with Executive Order 2009-10 regarding employment of persons not
authorized to work in the United States;
9. It will hold and honor all base bid prices for sixty (60) calendar days from the date of bid
opening, and cannot be withdrawn after the bid opening;
10. Its bid prices shown for each item on the bid proposal form include all labor, material,
equipment, overhead and compensation to complete all of the Work for that item; and
11. It has included in its bid amount Idaho sales and/or use taxes on all materials and equipment and
all other taxes imposed by law.
BID AWARD
AWARD METHOD: It is the intent of CM Company to award a Subcontract to the lowest responsive
qualified bidder. The low bidder, for purposes of award, shall be the bidder offering the low aggregate
amount for the base bid item, plus any additive or deductive bid alternates selected by CM Company. It is
the bidder's responsibility to conform to all applicable federal, state and local statutes or other applicable
legal requirements.
DETERMINATION OF QUALIFIED: CM Company reserves the right to make reasonable inquiry about or
from the submitting bidder or from third parties to determine whether a submitting bidder is qualified. Such
inquiry may include, but not be limited to, inquiry regarding experience and expertise related to the
Project, manpower and other resources, financial stability, credit ratings, references, potential
subcontractors and past performance. The unreasonable failure of a submitting bidder to promptly supply
any requested information may result in a finding of non-qualified.
NOTICE OF EFFECTIVENESS: No Subcontract is effective until CM Company has signed the
Subcontract and the Notice to Proceed has been issued. The bidder shall not provide any goods or
render services until the Subcontract has been signed and the Subcontract has become effective.
Furthermore, CM Company is in no way responsible for reimbursing the bidder for goods provided or
services rendered prior to the signature of CM Company and the arrival of the Notice to Proceed.
INCURRING COSTS: CM Company is not liable for any cost incurred by bidders prior to the Notice to
Proceed.
PRIOR ACCEPTANCE OF DEFECTIVE BIDS OR PROPOSALS: CM Company will not completely
review or analyze bids that appear to fail to comply with the requirements of the bid documents, nor
investigate the references or qualifications of those who submit such bids. Therefore, any
acknowledgment that the selection is complete shall not operate as a representation by CM Company
that an unsuccessful bid was responsive, complete, sufficient or lawful in any respect.
POST-AWARD SUBMITTALS: Upon receipt of a Notice of Intent to Award, the apparent low responsive
and responsible bidder shall provide documentation required in such Notice. Such Notice of Intent to
Award shall generally require the bidder to return to CM Company, within ten (10) days of receipt, a
signed Subcontract, all required bonds, and proof of insurance.
ITD - D9 Canopy & Yard A:4a Instructions to Bidders
Page 4 of 5

Part A:4a
RIGHT TO REJECT: Prior to execution of the Subcontract, CM Company shall provide written notice of
any reasonable objection to any person or entity proposed by the bidder. Upon receipt of such notice, the
bidder will or propose a substitute and identify any change in any bid amount caused by such substitution
within three (3) days. CM Company may accept or reject the substitution or the adjusted price.
END OF INSTRUCTIONS
ITD - D9 Canopy & Yard A:4a Instructions to Bidders
Page 5 of 5

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Event: RFQu2610CPDEQ Cyanidation Permitting Event: 1479-0 Category: AGENCY MANAGED Sub Category: DPA Type:

State Government of Idaho

Bid Due: 12/12/2026

Follow End of the World Long Term Stewardship Active Contract Opportunity Notice ID

AGRICULTURE, DEPARTMENT OF

Bid Due: 12/11/2026

Event: RFQu2610CPDEQ Cyanidation Permitting Event: 1479-1 Category: AGENCY MANAGED Sub Category: DPA Type:

State Government of Idaho

Bid Due: 12/12/2026

Post Date 11/05/2026 Quest Number 10437051 Category Code Street, Road, HWY - Median

State Government of Idaho

Bid Due: 12/08/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.