PUBLIC UTILITIES DEPARTMENT
Request for Proposals
Scum Well Chain and Flight Equipment
Installation Services
Proposal
The City of St. Cloud, Minnesota is soliciting proposals from qualified vendors for the
removal of the existing Polychem chain and flight equipment and installation of newly
procured Polychem chain and flight equipment within an existing scum well.
Background Information
The original Polychem scum skimmer drive system, manufactured by Brentwood
industries, was installed in 1974 at the St. Cloud Nutrient, Energy, and Water (NEW)
Recovery Facility. This skimmer drive gear system is operated to divert fats, oils and
greases and scum from the facility’s primary clarifier tanks. The current daily average flow
to the facility is 10 million gallons per day, MGD, and the scum and grease are
concentrated and collected by rotating weirs, which then flows by gravity to the scum
well. The drive mechanism in the scum well conveys the scum and grease to a sump
where it is pumped by pneumatic scum ejectors to the anerobic digesters for further
processing.
Location: 525 60 Street South, St. Cloud, MN 56301
Existing system details:
15 FT Long x 8 FT Wide x 3 FT AWD, 3 Shaft System
Equipment Submittals
Available upon request. See contact details in Additional Information below.
Removal and Installation labor:
Please include itemized equipment, materials, labor, travel and per-diem related
expenses to remove existing and install newly procured equipment and components.
Completion of removal and installation shall not exceed ten (10) working days after a
pre-approved start date with the customer.
Existing equipment shall be returned to the customer upon removal.
Page 1 of 2
Resources Available
Site visits are available upon request. See Additional Information section below.
Submission Requirements
Proposals will be accepted until 4:00 PM(CST) on the date listed below and are to be
submitted in PDF format via email to:
Wastewater@ci.stcloud.mn.us
Attention: Jacob Ethen, Wastewater Services Manager
Subject Line to Read: RFP for Scum Well Chain and Flight Equipment Installation Services
Vendor Selection Process
The proposals will be evaluated based on qualifications and experience of the
vendor/contractor, the anticipated cost of services and other appropriate factors (see
below).
Selection criteria shall include, but shall not be limited to, the following factors:
1. Related professional experience, specific project responsibility and availability of
key personnel assigned to the project.
2. Vendor/supplier recent experience in the provision of comparable wastewater
clarifier collector systems and design services including references.
3. Current lead times.
4. Anticipated cost.
As the contracting authority, the City of St. Cloud shall make the final decision concerning
vendor selection. The City reserves the right to negotiate professional services from the
selected consultant(s) as deemed necessary to fulfill the complete project intent. The
City reserves the right to terminate the contract and delete all remaining work tasks at its
discretion.
Schedule
Request For Proposals Advertised
Site Visit Deadline
Question Deadline
Proposals Due
Tentative Selection Announced
Finalize Work Plan, Fees and Contract
July 9, 2026
July 16, 2026
July 17, 2026
July 23, 2026, 4:00 PM(CST)
August 2026
Approximately August 30, 2026
Additional Information
Submit any questions, in writing, to Jacob Ethen, Wastewater Services Manager, by July
17, 2026. A written response will be provided to all interested firms by 11:00 AM(CST) on
Tuesday, July 21, 2026.
Jacob.Ethen@ci.stcloud.mn.us
Contact Jacob Ethen, Wastewater Services Manager, at (320) 255-7226 to schedule any
site visits regarding this Request for Proposal.
Page 2 of 2