INVITATION FOR BIDS
The City of Rock Island Public Works is soliciting bids from qualified contractors to install a
commercial grade automated entry gate at the Utilities Maintenance Complex, 1430 24th Street,
Rock Island, IL 61201.
Sealed bids shall be mailed to or dropped of at the Public Works Administration building addressed
with the following information clearly displayed on the envelope:
UMD Automatic Gate RFP, ATTN: Pat O’Brien, 1309 Mill Street, Rock Island, IL 61201.
AUTOMATED ENTRY GATE INSTALLATION
For questions on this contract please contact Nick Hartman – Utilities Maintenance Crew Leader,
309-732-2253.
A digital copy of the specifications may be downloaded from the City's website at:
https://rigov.org/bids.aspx
The Contractor will be responsible for complying with all local, state, and federal regulations
pertaining to this project.
The City of Rock Island is committed to preserving equal rights for all of its citizens during the
construction of its public works projects and encourages minority contractors to submit bids for this
work. The City also encourages bidders to consider hiring subcontractors and employees of all racial
and ethnic backgrounds.
It is the intent of the City of Rock Island to award a contract to the lowest responsible bidder provided
the bid has been submitted in accordance with the bidding requirements. The City reserves the right
to reject any or all bids and to waive informalities or technicalities.
BIDS DUE BY:
Monday, February 2, 2026
09:00 (AM), CST
City of Rock Island Public Works Department
1309 Mill Street
Rock Island, IL. 61201
PROJECT:
Automated Entry Gate
OWNER:
City of Rock Island
1528 3rd Avenue
Rock Island, IL. 61201
Sealed bids will be received, and publicly opened at 09:01 (AM) on Monday, February 2nd, 2026; at the City of
Rock Island Public Works Department, 1309 Mill Street, Rock Island, IL. 61201, or at such later time and place
as may then be fixed.
Bids may be hand carried or mailed and will be received at the City of Rock Island Public Works Department
until 09:00 (AM) on Monday, February 2, 2026. Bid envelopes must be sealed and marked “Bid – Automated
Entry Gate.”
Each Bidder shall accompany the Bid with a Bid security, in a separate envelope, as security that the
successful bidder will enter into a contract for the work bid upon. The bidder's security shall be in an amount
equivalent to five percent (5%) of the bid amount, and shall be in the form of a cashier's or certified check
drawn on a bank in Illinois or a bank chartered under the laws of the United States of America, or a certified
bank share draft drawn on a credit union in Iowa or chartered under the laws of the United States of America or
a bid bond with corporate surety satisfactory to the Owner.
Contractors are required to visit the site. Contact Nick Hartman, Utilities Maintenance Crew Leader at 309-
732-2253 or Email at Hartman.nick@rigov.org for an appointment to visit the site prior to submitting the bid.
Automated Commercial Rolling Gate System Bid Specification
At the Utilities Maintenance Division Complex (1430 24th ST, Rock Island, IL 61201)
1. General Requirements
1.1 Scope: The contractor shall furnish and install a complete automated rolling gate system, including
the gate frame, chain link fabric, rollers, gate operator, and all specified access control accessories
(keypad, Wi-Fi, and smartphone integration). The contractor shall be responsible for removing the
existing manual gate and any additional fencing, posts, etc. that may need to be removed, modified,
upscaled, etc. in order to facilitate the installation of the new automated rolling gate system.
1.2 Standards & Compliance:
o UL 325: The gate operator and all safety devices must be UL 325 compliant for Class II
(Commercial) or Class III (Industrial) applications.
o ASTM F2200: The gate construction must meet ASTM F2200 standards for automated
vehicular gates to prevent entrapment and injury.
1.3 Warranty: The system shall include a minimum 2-year manufacturer’s warranty on the operator
and a 1-year labor warranty on the installation.
2. Gate Material, Construction & Quantities
2.1 Gate Type: Horizontal Sliding/Rolling Gate.
2.2 Frame: 2" O.D. (Outer Diameter) Schedule 40 galvanized steel pipe. All joints shall be welded and
coated with cold-galvanizing spray.
2.3 Fabric: 9-gauge galvanized steel chain link wire with a 2" diamond mesh. Fabric must be secured to
the frame with tension bars and 9-gauge tie wires.
2.4 Hardware:
o Rollers: Heavy-duty, sealed-bearing nylon or galvanized steel rollers.
o Track: Galvanized steel ground track or overhead track (as specified by site plan).
o Safety Guards: Rollers must be equipped with safety covers to prevent finger pinch points.
2.5 Material Quantities: Materials required and quantities needed to complete the installation of the
gate will need to be determined by the Bidder/Contractor by conducting a site visit. The Bidder shall
connect with one of the listed City contacts to schedule a time to visit the installation site.
3. Gate Operator & Smart Features
3.1 Operator Motor: * Industrial-grade AC or DC motor (minimum 1/2 HP for gates up to 30ft, 1 HP
for gates over 30ft).
o Continuous duty cycle rating.
o Battery Backup: Integrated system to provide at least 50 cycles during a power outage.
3.2 Controller Interface:
o Keypad: Commercial-grade, backlit, vandal-resistant wireless or wired keypad. Must support at
least 100 unique user codes.
o WI-FI Connectivity: Integrated WI-FI bridge or cellular gateway providing real-time
connectivity to the local network.
o Phone Application: Compatible with a dedicated mobile app (e.g., myQ, LiftMaster, or
manufacturer equivalent).
Features required: Remote open/close, real-time status alerts (Gate Open/Gate Closed),
and user access logging.
o Remote Controls: 10 remote control units shall be furnished for gate operation.
3.3 Safety Devices:
o Photoelectric Sensors: Two (2) sets of "thru-beam" infrared safety eyes to prevent the gate from
closing on vehicles or pedestrians.
o Sensing Edge: A pressure-sensitive reversing edge installed on the leading edge of the gate.
4. Installation & Electrical
4.1 Power: The City is responsible for running power to the site and providing proper network
connectability; the Contractor is responsible for providing the City with the necessary specs for power
and network requirements for both the operator and gate motor before work on the gate installation by
the Contractor begins.
4.2 Footings: Operator and gate posts must be set in 3,000 PSI concrete footings at a depth below the
local frost line (typically 36"–48").
4.3 Programming: The contractor shall assist the owner in setting up the mobile app, connecting the
system to the facility’s Wi-Fi, and programming initial user codes.
5. Legal & Financial Requirement:
4.1 Construction Standards: This contract shall be in accordance with the IDOT Standard
Specifications for Road and Bridge Construction, where applicable.
4.2 Insurance: The contractor shall obtain and keep in force the insurance coverage specified in
article 107.27 of the Standard Specifications. The insurance coverage shall name the City of Rock
Island, its’ officers and employees as additional insured with respect to the liability coverage. Certified
copies of the original policy, or certificate(s) of insurance, by the issuing insurer(s) the policies and
endorsements shall be submitted to the City prior to the beginning of the work. All costs for insurance
specified herein shall be incidental to this contract.
4.3 Bonding: The winning bidder shall be required to provide a Performance, Labor, Material, and
Maintenance Bond.
4.4 Equal Employment Opportunity Policy: Federal and State laws prohibit
discrimination against any employee or applicant for employment because of race,
creed, color, national origin, sex, political affiliation, age and physical or mental handicap
unrelated to ability. They further require elimination of discrimination in employment with
regards to upgrading, demotion, transfer, recruitment, advertising, layoff, termination,
rates of pay, forms of compensation, selection for training (including apprenticeship) of
employees, as well as any other personnel actions.
4.5 Scheduling of Work, Completion Time: The winning bidder (“Contractor”) must
begin work within 60 calendar days of winning the bid and accepting the contract,
weather permitting. The contractor shall make contact with the City representative a
minimum of 5 working days before beginning work to ensure there are no scheduling
conflicts. Once work commences on site, full installation of all components shall be
completed within 5 working days, weather permitting. Flexibility to the above noted
timelines may be granted via written request (letter or email) from the Contractor and
consent by the City.
4.6 Permitting & Code of Ordinances: It is the responsibility of the Contractor to
follow any and all pertinent City of Rock Island Code of Ordinances. The Contractor is
also responsible to acquire any necessary construction and/or building permits that may
be required by the City’s Inspections Division.
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.