Lowest or any bid not necessarily accepted
If bid deviates from supplied specifications, those deviations must be clearly noted.
Completion prior to July 21, 2025
Testing of concrete and subbase paid for by Town of Rocanville
Construction plan must allow limited access to the aforementioned facilities during the entire time
Contractor plan should minimize interruption to the school
Curb contractor and earthworks contractor must work together to allow for simultaneous work
Following dates will have restrictions due to bookings at facilities
April 25 & 26, May 2 & 3, June 6 & 7, June 25, 26, 27, 28, & 29, July 11, 12, & 13, July 18, 19, & 20
Dates to be noted:
On site tour April 1, 2025
Bids close April 8, 2025
Award date April 15, 2025
|