Final Design for TH 61 from CSAH 14 to Reservation River Road

Location: Minnesota
Posted: Oct 22, 2026
Due: Nov 5, 2026
Agency: State Government of Minnesota
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.
Final Design for TH 61 from CSAH 14 to Reservation River Road

Brief Description: MnDOT requests letters of interest for a final design plan with special provisions for Trunk Highway (TH) 61 in Cook County. The design will be for a mill and overlay preservation of TH 61 from County State Aid Highway (CSAH) 14 to Reservation River Road. The design will incorporate turn lanes and storm drainage improvements for approximately 16.4 miles of highway and include coordination with the Bridge office for bridge deck resurfacing at Bridges 16001 and 16002. The goal of this project is to develop complete preliminary and final design plans including all required documentation, coordination, digital Project Specific Electronic Data (P SED) deliverables, and construction ready plans for the programmed letting.

Date posted: 10/15/2026
Due date: 11/05/2026

Attachment Preview

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
Scope of Work
1. Project Overview
1.1. Independent Contractor
1.1.1. The Successful Responder (Contractor) agrees it is acting in the role of an independent
contractor. The Contractor, and its employees and subcontractors, will not be considered employees of
MnDOT (State) for any reason. The Contractor acknowledges that it is responsible for its own financial
control. The Contractor has negotiated the payment for this contract with the State, which may result in
a profit or loss for the Contractor. The Contractor also acknowledges that it is responsible for the
behavioral control of itself, its operations, and its staff. The Contractor is solely responsible for
determining the means, methods, and sequence of performing the work covered by this contract. The
State has included deliverable dates in this contract, not to provide a "sequence" of work but because
the State must coordinate these deliverables with (1) the State's financial plans, (2) other contracts
managed by the State, and (3) work performed by the State's own staff. The parties have mutually
drafted and agreed upon a scope of work. The level of detail used to describe the work is intended only
to establish minimum standards and ensure consistency across the hundreds of projects managed by
the State; the Contractor remains responsible for determining the means and methods of performing
the work to meet or exceed those requirements. The State will not directly supervise the Contractor's
work but will provide oversight and monitoring, as required by Minnesota Statutes 16C.08 and 23 Code
of Federal Regulations (CFR) Part 172.5, to ensure compliance with the terms, conditions, and
specifications of this contract. At the conclusion of this contract, the State will evaluate the Contractor's
performance under this contract for potential use in future evaluations and selections as required by
Minnesota Statutes 16C.08 and 23 CFR Part 172.5.
1.2. General Statement of Scope of Work
1.2.1. This contract includes final highway design for the preservation of Trunk Highway (TH) 61 in
Cook County. The final design work spans approximately 16.4 miles, from the junction of County State
Aid Highway (CSAH) 14 to the junction of Reservation River Road.
The final design will start with developing construction limits and a 30% design plan. The Contractor's
tasks under this contract will include, but are not limited to project management, construction limits,
final roadway design, final hydraulic and stormwater design, temporary and permanent erosion control,
temporary traffic control and staging plans, National Pollutant Discharge Elimination System (NPDES)
permit, signing plans, utility coordination, public engagement support, special provisions, cost
estimating, and construction design support.
Elements of the project to be addressed by the Contractor in final design under this contract include but
are not limited to:
a) Mainline bituminous mill and overlay (4-inch depth) from the junction of CSAH 14 to the
junction of Reservation River Road.
b) Provide new turn lanes at the following locations:
i. CSAH 14 - South Location (Reference Post (RP) 117.59) - Right turn lane
ii. CSAH 14 - East Location (RP 121.26) - Right turn lane

iii. Judge Clarence R. Magney State Park Entrance (RP 123.98) - Southbound right turn lane

& northbound bypass lane

1

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
iv. County Road (CR) 69 - South Location (RP 124.62) - Right turn lane
v. CR 88 - (RP 128.30) - Right turn lane

vi. CR 69 - North Junction (RP 129.47) - Right-turn lane

vii. Horseshoe Bay Boat Launch / Lake Access (RP 130.13) - Right turn lane
c) Bridge 16001 - Flute Reed River:

i. Coordinate roadway grading design with Bridge Office design of proposed deck mill and
overlay.
ii. Remove and replace approach panels. Assume semi-integral abutment.
iii. Remove and replace guardrail.
d) Bridge 16002 - Brule River:
i. Coordinate roadway grading design with Bridge Office design of proposed deck mill and
overlay.
ii. Remove and replace approach panels. Assume semi-integral abutment.
iii. Remove and replace guardrail.
iv. Place rip rap at southwest corner of bridge.
e) Bridge 16004 - Kadunce River:
i. Remove and replace guardrail. Coordinate with District and Central Office (CO) design for
custom barrier/rail attachment to accommodate inplace architectural parapet surface
texture.
f) Drainage Improvements:
i. Centerline Culvert Replacements:
a. RP 123.977 - 36-inch Corrugated Metal Pipe (CMP)
b. RP 125.098 - 24-inch CMP
ii. Culvert Rehabilitation at approximately 48 sites including Cured-In-Place Pipe (CIPP) liners,
inlet/outlet cleaning, apron replacements/repairs, joint repairs, floor repairs, and culvert
extensions.
iii. New drainage features (special ditching, new culverts, culvert extensions) at turn lane and
bypass locations as required.
iv. New drainage features (catch basins, inslope protection, etc.) at new bridge approach
panels as required.
g) Guardrail:
i. Remove and replace inplace guardrail - approximately 19,000 Lineal Feet (LF).
ii. Evaluate length of need and provide modifications to meet standards.
iii. Provide long post guardrail to minimize shoulder widening and inslope impacts.
iv. Provide guardrail post in rock details.
2

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
h) The Contractor will identify all tree clearing needs to accomplish the work and will prepare a
separate tree clearing plan for tree removal by the State prior to letting.
i) Remove and replace mailbox supports (approximately 90 each)
j) Remove and replace all signs and supports within the project extents.
k) Remove and replace all pavement markings.
l) Provide centerline and shoulder rumble strips.
m) Temporary Traffic Control and Staging:
i. Temporary signals at:
a. Flute Reed River (16001)
b. Brule River (16002)
c. RP 123.977 (centerline culvert replacement)
d. RP 125.098 (centerline culvert replacement)
ii. Temporary widening / bypass sections at culvert replacements.
iii. Field manual layouts for mill & overlay operations.
iv. Staged construction sheets for centerline culvert replacement, bridge overlays, and turn

lanes (especially staging coordination at State Park entrance due to overlapping turn lane
work and culvert replacement and park traffic).

1.3. Project Background
1.3.1. State Project (SP) 1603 54 is a pavement preservation and roadside infrastructure project on
TH 61 extending approximately 16.4 miles between CSAH 14 and Reservation River Road. The project

corridor is located northeast of Grand Marais in Cook County, passing through the communities of
Hovland and numerous rural residential and recreational areas along the Lake Superior North Shore.
TH 61 is a rural two lane principal arterial that provides the primary connection between Grand Marais,
Hovland, Grand Portage, and the international border at Canada. The corridor carries through traffic,

local residents, recreational users accessing multiple state parks and trailheads, and seasonal tourist

traffic.
1.3.2. Within the project limits, TH 61 includes numerous driveway entrances, several county road
intersections (including CSAH 14, CR 69, and CR 88), and multiple bridge crossings over trout streams.
Existing shoulders vary between 5 and 10 feet and provide bicycle accommodation. The project area
includes important recreational destinations such as Judge Clarence R. Magney State Park, the Kadunce
River Wayside, Horseshoe Bay, and the Icelandite Coastal Fen Scientific and Natural Area (SNA).
1.3.3. This project will address pavement condition, roadside safety, drainage deficiencies, bridge
preservation needs (State Bridge Office will design the bridge plans), and operational improvements
while maintaining the rural character of the corridor and supporting multimodal users.
1.4. Web-Based Teleconferencing
1.4.1. The Contractor must provide the means for the project team to meet via web-based
teleconferencing that allows participants to view the desktop of the meeting organizer. Participants
must be able to "take control" of the virtual desktop as needed to point out things on the file being
displayed. Voice communication may occur via computer or phone.
3

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
1.5. Source Type Codes and Primavera 6 (P6) Activity Codes
1.5.1. Every deliverable must list a source type code. The source type code will be used in the
Contractor's invoice to subtotal the deliverables together under that source type code.
1.5.2. Every deliverable must list a P6 activity code that matches the P6 activity in the P6 schedule.
The Contractor may use this code to understand the due dates for that deliverable in the schedule and
how the activity relates to other activities in the schedule.
1.5.3. The Contractor is not required to know how to use P6 or work within the program itself unless
stated in Project Management section. The Contractor is, however, expected to understand the concept
of Critical Path Method scheduling, understand hardcopy reports printed by the P6 schedule, update the
hardcopy reports, and recommend changes to the schedule to reflect changes in the scope or flow of
work.
1.6. Milestones and Contract Completion Timeline
1.6.1. The late start and the late finish dates included in the project schedule are the contractual due
dates for this contract.
a) Anticipated Notice to Proceed: March 9, 2027
b) Construction Limits: December 7, 2027
c) 30% Plan Submittal: May 18, 2028
d) 60% Plan Submittal: October 25, 2028
e) 90% Plan Submittal: March 23, 2029
f) 95% Plan Submittal: May 25, 2029
g) Letting: December 5, 2029
1.7. Format of Deliverables
1.7.1. All deliverables must be provided in electronic file format.
1.7.2. Software
a) Report source files must be in current versions of Microsoft Word and Microsoft Excel. Files
must be delivered to the State by using ProjectWise.
b) Computer-Aided Design and Drafting (CADD) deliverable source files must meet the State's Level
2 Enhanced CADD Data Delivery Specifications.
c) All applicable spatial data and maps created in Geographic Information System (GIS) software
must be provided in a standard shapefile format (.shp) that is compatible with current versions
of ArcMap software.
d) All source files also must be converted to a portable document format (PDF)(.pdf extension),
and the PDF must be searchable, with scanned pages eliminated except for signature pages.
1.7.3. Plain Language
a) All documents or exhibits specifically designed to be used by the public must be developed in
"plain language." Executive Order 14-07 requires the Office of the Governor and all Executive
Branch agencies to communicate with Minnesotans using plain language and defines plain
language as a communication that an audience can understand the first time they read or hear
it. Additional information is available at
4

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
(https://www.dot.state.mn.us/consult/adaplainlanguage.html). To meet the requirements of
this executive order, the Contractor will:
i. Use language commonly understood by the public
ii. Write in short and complete sentences
iii. Present information in a format that is easy to find and easy to understand
iv. Clearly state directions and deadlines to the audience
b) Technical documents, presentations, spreadsheets, and drawings used by technical staff do not
need to be in plain language.
1.7.4. Accessibility Standards
a) The Contractor must comply with the State of Minnesota's Accessibility Standard
(http://mn.gov/oet/images/Stnd_State_Accessibility.pdf) for all documents or exhibits
specifically designed to be used by the public. The State of Minnesota's Accessibility Standards
are based on the Web Content Accessibility Guidelines (WCAG) 2.0 (Level AA) and Section 508 of
the Rehabilitation Act, as amended. Additional requirements can be found at
(http://www.dot.state.mn.us/ada/accommodation.html) and include:
i. Providing interpreters, translators, or other special accommodations.
ii. Providing documents in an alternative format.
iii. Following the PDF accessibility guidance.
b) The State of Minnesota's Accessibility Standard also includes:
i. All videos must include closed captions, audio descriptions, and a link to a complete
transcript.
ii. All documents, presentations, spreadsheets, drawings, and other material must be
provided in an accessible format. Native files must be provided in an editable format.
Acceptable formats include InDesign, Word, and Excel.
iii. All materials intended for downloading and printing must be labeled as such, and the
content must be provided in an accessible format.
a. Technical documents, presentations, spreadsheets, and drawings used by technical
staff do not need to comply with the State of Minnesota's Accessibility Standard.
b. All outward-facing Microsoft Word documents to be used during the project must
be designed with Americans with Disabilities Act (ADA)-accessible features,
including alt text and screen-reader compatibility.
1.8. Standards and Guidance
1.8.1. All field data must be provided in Lake County Coordinate System, based on the 2011
adjustment of the North American Datum of 1983 (NAD83/2011) reference frame and North American
Vertical Datum (NAVD) 88 with Geoid18 applied.
1.8.2. The Contractor will convert all design work completed or in progress to Open Roads Design
(ORD).
1.8.3. All design must be conducted by or under the direct supervision of a Professional Engineer
licensed in Minnesota.
1.8.4. All deliverables must be prepared in accordance with the Transportation Project Development
Process (TPDP): https://www.dot.state.mn.us/project-development/index.html
1.8.5. The State uses the P6 scheduling tool.
5

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
1.8.6. Failure of this scope of work to list a specific standard under a specific deliverable does not
absolve the Contractor's obligation to comply with all laws, regulations, and standards that apply to
highway projects within the State of Minnesota. The Contractor must comply with all state, federal, and
local standards, laws, and regulations related to the scope of work and project area. Work must comply
with the latest edition or revision of that standard in effect on the proposal due date, including any
amendments in effect on that date, unless otherwise specified in the contract or otherwise directed by
the State.
1.8.7. Websites have been supplied to the Contractor for some of the standards and guidance
documents listed for convenience only in an effort to help the Contractor locate the required standard
or guidance. The websites are not guaranteed to be correct. It is ultimately the Contractor's
responsibility to locate the required standard and to determine if the standard has been modified
pursuant to this Contract.
1.8.8. Additional requirements for standards may be provided within the scope tasks that follow.
1.9. Items Provided by the State
1.9.1. The State will provide the following items. Some items must be provided at notice to proceed.
Other items are developed as the project progresses. The Contractor is responsible for requesting the
needed information when it is available during the project development.
a) Base mapping: topography, triangulated Irregular Network (tin), Digital Terrain Model (DTM),
right-of-way, property lines
b) Existing alignment/survey
c) Public and stakeholder engagement
d) Environmental documentation
e) Wetland delineation
f) Right-of-way information
g) Proposed right-of-way acquisition map
h) Pavement recommendations and material design recommendations
i) Sample plan
j) Example or existing/draft Stormwater Pollution Prevention Plan (SWPPP) and title sheet
k) Project scoping document
l) Staff approved layout with design memo
m) Special provisions template and guidance information
n) Construction cost estimate district template
o) District-modified standard detail sheets
p) Traffic data and available traffic analyses/studies
i. State Traffic Engineering Manual
ii. Minnesota Manual on Uniform Traffic Control Devices (MN MUTCD)
q) Time and Traffic special provisions
r) Process B Complex project submittal letter template
s) Draft ADA design recommendations
t) The State's risk register template
2. Project Management (Source Type 1010)
2.1. Project Coordination and Administration (P6 Activity Code OPM1000)
6

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
2.1.1. Project management includes work necessary for communicating and completing the project
tasks on time and within budget. The Contractor must not reassign the project manager or their primary
duties without the written consent of the State's project manager. The Contractor's staff must have the
training and expertise necessary for the work tasks to which they are assigned.
2.1.2. Meeting summaries must be submitted no later than 3 business days after each meeting and a
final meeting summary must be submitted no later than 3 business days after receiving comments on
summary notes.
2.1.3. The Contractor will:
a) Prepare invoices accompanied by:
i. A cover letter explaining the general status of the project, including at a minimum the
work completed to date, the anticipated remaining efforts, and required schedule changes
ii. Progress report form
iii. Supporting data for direct expenses
iv. An updated project status report reflecting P6 activities identified by the State's project
manager
b) Manage, coordinate, direct, and monitor subcontractor services, including reviewing progress
reports, deliverables, schedule, and invoices.
c) Update the State's project manager on the status of the project schedule, budget, and general
status/progress on a monthly basis.
d) Store all deliverables in an organized electronic document management system and make
deliverables available to the State's project manager as needed whether the file is incomplete,
in draft form, or the final deliverable by ProjectWise. The State will provide restricted access to a
ProjectWise document center for use as the project file transfer vehicle and repository.
e) List and track issues that develop during the project that either need resolution or
implementation. The tracking spreadsheet must prioritize issues for due dates and amount of
risk to schedule and construction budget. For example, the State's project manager may send an
email to the Contractor stating that an issue needs to be resolved or completed. The Contractor
must log that issue and track it until it is marked completed. The Contractor will review the list
with the State's project manager at the monthly progress meetings.
f) Contractor will develop a project specific Quality Management Plan (QMP) that specifies how
Contractor will perform Quality Assurance (QA) and Quality Control (QC) activities throughout
the duration of the project to ensure delivery of a quality product in a timely manner that
conforms to established contract requirements. Contractor will prepare the project specific
QMP and distribute it to all project team members, including subcontractors. Contractor must
submit the project specific QMP to State's Project Manager for approval within five business
days of Notice to Proceed.
2.1.4. Deliverables:
a) Monthly invoices and progress reports
b) Subcontractor status reports included with monthly invoices and progress reports
c) Update calls with the State's project manager
d) Document management system
e) Issue resolution tracking spreadsheet
f) Agency correspondence
g) QMP
7

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
2.2. Project Meetings (P6 Activity Code OPM1000)
2.2.1. Kickoff Meeting
a) The Contractor will schedule and facilitate a project kickoff meeting to confirm the basic project
objectives, solidify a work plan, and obtain consensus on the project requirements. This meeting
must occur no later than 10 business days after notice to proceed. The meeting will be held
virtually.
2.2.2. Project Management Team (PMT) Meetings
a) The Contractor will facilitate biweekly, virtual meetings with the State's project manager and
other personnel as identified by the State's project manager. The intent of the weekly meetings
is to review overall project progress as measured by the P6 schedule and to discuss issues that
are not resolved at the design level. The meetings are intended to provide a management-level
view of project development. For this scope, assume biweekly meetings for 24 months
attended by Contractor's project manager. Other design team personnel will attend as needed.
2.2.3. Pre-Letting Meetings
a) The purpose of these meetings is to discuss plan details and coordination with the Pre-Letting
Unit to ensure plan quality and timeliness. The meetings will occur at approximately 60 percent
and 95 percent plan completion.
b) The Contractor will schedule and facilitate two virtual pre-letting meetings with the State's
project manager and State CO Pre-Letting Unit.
2.2.4. Deliverables:
a) Meeting invite, materials, agenda, and draft and final meeting summaries for each meeting
2.3. Work Plan and Schedule (P6 Activity Code OPM1000)
2.3.1. The State will provide a PDF of the draft project schedule in P6 format with all State Work
Packages included in the schedule and will include the State's P6 Work Packages Dictionary. The State
will maintain the official schedule on State servers to be updated manually based on Contractor
recommendations.
2.3.2. The Contractor will manage the schedule by:
a) Providing monthly schedule updates to the State's project manager by marking up a PDF copy of
the schedule.
b) Determining if any activities owned by the Contractor need to have their percent complete and
remaining duration updated
c) Examining the schedule and determine what activities need to start work, need to show
progress in work, or need to be completed within a month.
d) Communicating schedule update information with activity owners as needed and determine if
additional activities need to be added to the schedule
e) Sending recommended updates to the State's project manager for review
i. The schedule must not extend beyond the contractual completion dates or contain
negative float. If any activities do have negative float, the Contractor must provide a
recovery schedule recommendation within 10 business days to explain how the negative
float will be eliminated.
2.3.3. Deliverables:
8

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
a) Monthly schedule updates to the State's project manager
b) P6 schedule, updated monthly
c) Recovery schedule recommendation
2.4. Provide Plan Bidding and Construction Assistance
2.4.1. The Contractor will:
a) Provide construction design support. Be available for plan interpretation/questions during
bidding and construction (up to 80 hours)
b) Provide 20 hours for review of shop drawing submittals as part of this scope.
2.4.2. Deliverables:
a) Responses to bidding and construction questions
b) Shop drawing submittal review comments
3. Public Communication and Public & Agency Engagement (Source Type 0054)
3.1. Project Stakeholder Coordination
3.1.1. Contractor will attend and participate in up to two public information meetings. Meetings
should be assumed to be in person at location in the general project area and attended by up to two
project team representatives.
3.1.2. Contractor will attend and participate in up to 10 agency meetings with state, regional, and
local agencies. Meetings should be assumed to be a mix of in-person and virtual and attended in person
by up to two project team representatives.
3.1.3. Deliverables
a) Attend and participate in up to 12 total meetings with Stakeholders including but not limited to
City Council, County Commission, and other agency partners. Prepare meeting agenda, minutes,
and meeting materials.
3.2. Items Provided by the State
3.2.1. The State will provide the following:
a) Provide and maintain a Project website using Contractor provided exhibits and updates.
b) Schedule and participate in meetings with Agency partners.
c) Participate in Council/Board meetings.
d) Develop Public Engagement Strategies and Website Content.
e) Prepare and release traditional media press releases.
4. Environmental Management Plan (EMP)
4.1. Standards and Guidance
4.1.1. The Contractor will create an EMP for the project according to the following documents, which
are available on the TPDP Environmental Commitments website. in accordance with:
Green Sheet Template
Green Sheet Instructions
Green Sheet Process
4.2. Items Provided by the State
4.2.1. The State will provide the following items:
9

MnDOT Contract No. 1064419
Exhibit A: Specifications, Duties, and Scope of Work
a) Guidance documents
b) 30% EMP, consisting of a partial list of initial commitments based on responses to the Early
Notification Memo (ENM) and other commitments that are known so far
4.3. Develop EMP (P6 activities EMP1000, EMP1010, EMP1020)
4.3.1. The Contractor will:
a) Review all ENM responses and ensure that all relevant commitments are added to the draft
EMP. Coordinate with subject matter experts on specific commitments as needed.
b) Ensure that commitments are updated when new information becomes available from field
reviews or permit requirements. Coordinate with subject matter experts as needed to update
specific commitments.
c) Provide a draft EMP to be included in the environmental document as the Mitigation
Commitments Table.
d) Provide draft EMPs for inclusion in the plans at the 30%, 60%, and 90% plan review stages.
e) Update a copy of the EMP that displays only construction commitments to be included in the
plan set for 100% plan submittal. Do this according to the description of the Construction Green
Sheet in the Green Sheet Instructions document.
f) Provide the full spreadsheet version of the EMP as a separate Excel document upon 100% plan
submittal.
4.3.2. Deliverables:
a) Draft EMP to be included in the environmental document as the Mitigation Commitments Table
b) Draft EMPs for inclusion in the plans at the 30%, 60%, and 90% plan review stages.
c) Copy of the EMP showing only construction commitments to be included in the plan set for
100% plan submittal.
d) Full spreadsheet version of the EMP as a separate Excel document upon 100% plan submittal.
5. NPDES Construction Stormwater (CSW) General Permit (Source Type 1071)
5.1. Standards and Guidance
5.1.1. All deliverables must be prepared in accordance with:
a) Minnesota general permit: MN R1OOOO1 for stormwater associated with construction activity
b) Minnesota Pollution Control Agency (MPCA) Stormwater Compliance assistance Tool Kit for
Small Construction Operators: www.pca.state.mn.us/publications/wq-strm2-09.pdf
c) MPCA Industrial Stormwater Best Management Practices Guidebook:
www.pca.state.mn.us/water/stormwater/stormwater-manual.html
d) MPCA Protecting Water Quality in Urban Areas: www.pca.state.mn.us/water/pubs/sw-
bmpmanual.html
5.2. Prepare NPDES Permit Application (P6 Activity Code NPP1040)
5.2.1. The Contractor will:
a) Determine if the project disturbs one or more acres of soil and/or adds one or more acres of net
new impervious.
b) If yes, prepare and provide the NPDES CSW General Permit application form to the State.
5.2.2. The State will submit the permit application electronically.
5.2.3. Deliverables:
10

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Construction Administration PFP0000557 Professional Services 21 days 11/10/2026 02:00 PM CST 12/01/2026 02:00 ...

Hennepin County

Bid Due: 12/01/2026

...Bid Title: RFP for 2027 Construction Services Category: Washington County Public Works Status... ...

Washington County

Bid Due: 11/18/2026

...Bid Title: RFP for 2027 Construction Services Category: Washington County Public Works Status... ...

Washington County

Bid Due: 11/20/2026

...Street / Midtown Station Renovation Construction Roundtable 11/3/2026 12/31/2026 RFI PRE...-SOLICITATION CONTRACTOR ROUNDTABLE ...

Metropolitan Council

Bid Due: 12/31/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.