Beaver Ruin Diversion Pump Station Grinders Replacement Project

Location: Georgia
Posted: Aug 12, 2026
Due: Sep 23, 2026
Agency: Gwinnett County
Type of Government: State & Local
Category:
  • 43 - Pumps and Compressors
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: BL117-26 NOT
Publication URL: To access bid details, please log in.
  • BL117-26 NOT

    Beaver Ruin Diversion Pump Station Grinders Replacement Project

    Buyer Contact : Anna.West@GwinnettCounty.com

    Opening Date : 09/23/2026 03:00 PM EST

    Virtual Bid Opening

    Addendum : BL117-26 Addendum 01 (1)

  • Attachment Preview

    CONTRACT DOCUMENTS
    FOR CONSTRUCTION OF
    BEAVER RUIN DIVERSION PUMP
    STATION
    GRINDERS REPLACEMENT
    PROJECT
    GCDWR Project No. M00748.67
    BL117-26
    Volume 1 of 2
    Prepared For:
    Gwinnett County
    Department of Water Resources
    684 Winder Highway
    Lawrenceville, GA 30045
    Prepared By:
    Ardurra
    1305 Mall of Georgia Blvd., Suite 160
    Buford, GA. 30519
    GA. COA: PEF004730
    AUGUST 2026
    00 11 16
    INVITATION TO BID
    General Notice
    The Gwinnett County Board of Commissioners (Owner) is requesting Bids for the construction of the
    following Project pursuant to O.C.G.A. §36-91-20:
    Beaver Ruin Diversion Pump System Grinders Replacements
    GCDWR Project No.: #M00748.67
    This Project includes the following Work:
    1) Replacement and installation of the three (3) existing grinder units with new rail systems,
    channel modifications, and control panels.
    2) Replacement and installation of the three (3) existing influent slide gates with actuators.
    3) Replacement and installation of the three (3) existing effluent slide gates.
    4) Replacement and installation of the two (2) existing influent wet well slide gates.
    5) Replacement and installation of one (1) existing wet well crossover slide gate.
    6) Raising of concrete wet well baffle wall and platform elevations.
    7) Relocation and re-installation of existing flushing system.
    8) Installation of electrical conduit and designed routing with MCC configuration.
    The Project is to be substantially complete and ready for operation within 450 days after the date when
    the Contract Times commence to run as provided in the General Conditions. The Project is to be
    completed and eligible for final payment 30 days after the date for Substantial Completion.
    All competitive, sealed bidding shall conform to O.C.G.A. §36-91-2, -20 to -22.
    Obtaining Bidding Documents
    Drawings and Specifications must be purchased from Ardurra Group Inc. at the below address for a non-
    refundable fee of $250. Only complete sets will be issued.
    Ardurra Group Inc.
    1305 Mall of Georgia Blvd.
    Buford, GA
    256-508-9083
    cwclark@ardurra.com
    Bidders are responsible for ensuring that a complete set of documents, as defined in Section 00 52 13
    “Agreement,” are used in the preparation of their Bids.
    Printed copies of the Contract Documents, Technical Data, and other information may be examined free
    of charge, pursuant to O.C.G.A §36-91-20(4), at the following addresses:
    Beaver Ruin Diversion Pump Station Grinders Replacements
    M00748.67
    August 2026
    Invitation to Bid
    00 11 16 - 1
    Gwinnett County Department of Financial Services
    Purchasing Division - 2nd Floor
    75 Langley Drive
    Lawrenceville, Georgia 30046
    Hours Available for Viewing: 8am-5pm
    Pre-bid Date and Location:
    A non-mandatory pre-bid conference for the Project is scheduled for 10:00 AM local time on September
    1st, 2026 onsite at the Beaver Ruin Diversion Pump Station (3530 Cruse Rd NW, Lawrenceville, GA
    30044). All visitors are required to bring Personal Protection Equipment (PPE) for the site visit. PPE
    includes but is not limited to ANSI Class 2 or 3 safety vests, Class E hard hats, ANSI approved eye
    protection, safety toe boots and hearing protection where required. All interested parties are urged to
    attend. The Pre-bid conference is to be utilized by contractors and subcontractors to ask any questions
    in order to submit a bid for this project.
    Instructions on Submitting Questions:
    Questions regarding bids should be submitted to Anna West at Anna.West@GwinnettCounty.com no
    later than 3:00 P.M. local time on September, 8th, 2026. Bids are legal and binding upon the bidder
    when submitted.
    Obtain the Plan-Holders List
    The plan-holders list is available from Ardurra Group, Inc.
    Delivery of Bids
    Sealed Bids must be delivered to Owner as specified in Section 00 21 13 “Instructions to Bidders” no
    later than 2:50 P.M. local time on September 23, 2026 to be accepted.
    Instructions to Bidders
    See Section 00 21 13 “Instructions to Bidders” included in the Bidding Documents for detailed
    requirements for preparing and submitting a Bid and award of the Contract.
    This Invitation to Bid is issued by:
    Gwinnett County Board of Commissioners
    Anna West
    Purchasing Associate II
    August 12th, 2026
    END OF SECTION
    Beaver Ruin Diversion Pump Station Grinders Replacements
    M00748.67
    August 2026
    Invitation to Bid
    00 11 16 - 2
    This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
    Daily notification on new contract opportunities

    With GovernmentContracts, you can:

    • Find more opportunities and win more business
    • Receive daily alerts for all new bid opportunities
    • Get contract opportunities matched to your business
    ONE WEEK FREE TRIAL

    See also

    ...City of Adairsville Water Plant Backwash Pump Adairsville, City Of Sep 21, 2026 ...

    State Government of Georgia

    Bid Due: 11/03/2026

    ...pumps currently installed at multiple Water Reclamation Centers. These parts are required to ...

    State Government of Georgia

    Bid Due: 10/02/2026

    ...BL117-26 NOT Beaver Ruin Diversion Pump Station Grinders Replacement Project Buyer Contact...-26 Addendum ...

    Gwinnett County

    Bid Due: 10/07/2026

    ...miles of gravity sewer and force main piping, four pump stations and a ...

    State Government of Georgia

    Bid Due: 10/05/2026

    * Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.