Statement of Work
1100-71890 SCI Huntingdon New Yard Exercise Track Area Paving
Project
I. CERTIFIED MICRO BUSINESS NOTIFICATION
ONLY CERTIFIED MICRO BUSINESSES ARE ELIGIBLE FOR AWARD. The Department of
Corrections has designated this bid opportunity as a Mirco Business Procurement to
provide DGS-certified micro businesses with opportunities to compete against other
DGS-certified micro business for Commonwealth agency and DGS statewide Purchase
Orders. Only certificated micro businesses are eligible to submit a bid and receive an
award. The micro business requirements and certification process can be found on
the following site. The Micro Business Certification will be provided after the self-
certification process on the MCBR site. A valid Department of General Services (DGS)
Micro Business certificate will be required as part of the bid in order to be deemed a
responsive bidder. Any business without a valid certificate on the bid due date and
time may be rejected as non-responsive. This Purchase Order will be monitored for
compliance by the Bureau of Diversity, Inclusion, and Small Business Opportunities
(BDISBO).
II. ELECTRONIC BID RESPONSE
Only electronic bid responses will be accepted. Registered vendors may find
solicitation on the PA Supplier Portal. All bidders are responsible for monitoring
eMarketplace to view any change notices to this IFB. The change notices shall
become incorporated as part of this solicitation. Interested vendors must be
registered to submit a bid. To register and obtain a vendor number, visit the PA
Supplier Portal. Information about the registration and bidding process can be found
at the Supplier Service Center.
III. SCOPE OF WORK
The Commonwealth of Pennsylvania, Department of Corrections (DOC), requires the
paving of approximately 16,488 square feet of the exercise track area at SCI
Huntingdon, located at 1100 Pike Street, Huntingdon, PA 16654. The existing surface
consists of compacted limestone dust. Refer to Appendix A – New Yard Track Paving
Aerial for satellite image of area.
IV. ISSUIING OFFICER
Questions regarding the bid should be directed towards Christina Zambotti
(czambotti@pa.gov). All questions regarding the IFB must be submitted by email.
Subject line of the email must reference: “6100065677 SCI Huntingdon New Yard
Exercise Track Area Paving Project”. Questions received within 48 hours prior to the
bid due date and time will be answered at the discretion of the Commonwealth. All
questions received will be answered, in writing, and such responses shall be posted to
eMarketplace as an addendum to the IFB. The Issuing Office shall not be bound by
any verbal information, nor shall it be bound by any written information that is not
1
Statement of Work
1100-71890 SCI Huntingdon New Yard Exercise Track Area Paving
Project
either contained within the IFB or formally issued as an addendum by the Issuing
Office.
V. MANDATORY SITE VISIT
A mandatory site visit will be held on Thursday, April 9th, 2026 at 10:30 AM, at SCI
Huntingdon located at 1100 Pike Street, Huntingdon, PA 16654. Each prospective
bidder must attend the site visit. Prospective bidders must email Mike Wenrick at
(mwenrick@pa.gov) to confirm attendance and identify participation 5-days prior to
visit. The Department of Corrections requires that all person(s) attending the site
inspection receive a Security Clearance Check in advance. More information about
the Pennsylvania DOC clearance certificate process can be found on the following
site.
Prospective bidders must attend mandatory site visit to submit a bid. Prospective
bidders who submit a bid without attending the mandatory site visit will be rejected
as non-responsive.
VI. TRADES INVOLVED
The following contractor trades will be required for this project: General Contractor
specializing in paving operations.
VII. CONTRACTOR TASK REQUIREMENTS
The General Contractor will be responsible for the paving of the track area in the New
Yard area of SCI Huntingdon.
To accomplish this task, the contractors are responsible for, but not limited to:
General Contractor:
a. Paving Operations
i. Base coat will be applied.
ii. Top coat of asphalt will be applied following the placement of the base
coat.
b. Unloading, rigging and leveling of materials equipment.
c. Proper disposal of all waste and debris off-site with documentation to
demonstrate compliance.
d. Complete installation of services within a 14-working day period to include at a
minimum:
i. All labor, equipment, and materials necessary for completion of work.
ii. Safe work in accordance with OSHA regulations.
2
Statement of Work
1100-71890 SCI Huntingdon New Yard Exercise Track Area Paving
Project
iii. Work per Department of Corrections security protocols and procedures.
iv. Applicable O&M procedures for any newly provided equipment under
this scope of work.
v. Supervision of crews and subcontractors in accordance with this
purchase order.
e. Return services and inspection visit within six (6) months of start of operation.
VIII. SPECIFICATIONS
Additional requirements are included in Appendix B – Specifications. The contractor
must adhere to all requirements.
IX. SCOPE OF WORK REQUIREMENTS
The Scope of work shall include, but is not limited to:
a) Submission of a Project Schedule.
b) Coordination between General Contractor and Sub-contractors to ensure the
timely completion of the project in accordance with the DOC approve Project
schedule.
c) Demolition and removal of all construction debris from the site.
d) Coordination of the work with the institution for access and
equipment/material staging.
e) All work, access, and temporary construction to be performed in accordance
with OSHA and DOC safety regulations.
f) Manufacturer’s standard warranty for new provided equipment [minimum of
one (1) year comprehensive parts and labor].
g) Submittals for DOC approval of all major equipment, materials, sub-
assemblies, assemblies, equipment/supplier’s design details.
h) A project sign is NOT required.
X.
3
REPAIR SHALL INCLUDE ALL WORK OR MATERAILS TO MEET THE FOLLOWING
a) Compliance with applicable portions International Building Code, International
Mechanical Code, NECC.
b) OSHA Standards for installed safety devices under this project.
c) Contact Greg Powell at SCI Huntingdon for access and follow-up site visits:
(814) 643-2400 EXT 1400.
d) The desired timeframe for this work to be completed is Spring/Summer of
2026.
e) This work is located inside the secure perimeter of the facility. Tool control
tool control procedures and personnel clearances will be required for this
Statement of Work
1100-71890 SCI Huntingdon New Yard Exercise Track Area Paving
Project
work.
XI. INSTITUTION WILL PROVIDE THE FOLLOWING SERVICES & COMPONENTS
a) Upon submission of proper clearance, tool inventory and control
documentation, access to work area between 7:30AM to 3:30PM
Monday thru Friday, access to all available utilities and dining facilities
within the limitations of the institution.
b) Tool-check and check in starting after the morning count clears (between
6:30AM and 7:30AM).
c) Secure staging inside the institution for major materials and select
tools/materials subject to approval.
XII. CONTRACTOR REQUIREMENTS
Prevailing Wages. The Contractor agrees to comply with Act 442 – Pennsylvania
Prevailing Wage Act and all applicable Pennsylvania Department of Labor & Industries
rules and regulations. Prevailing wage showing in Appendix C – Prevailing Wages.
Laws. The contractor must comply with the laws set forth through the regular
construction process. These laws include:
a) The Public Works Employment Verification Act
b) The Steel Products Procurement Act
c) The Separations Act
d) Right to know Law Clause
e) Contractor Integrity Provisions
f) Contractor Responsibility Provisions
g) Nondiscrimination/Sexual Harassment Clause
h) Offset Provision
i) ADA Provision
General. Provisions of all related hardware to accomplish proper installation is the
supplier’s responsibility.
XIII. BIDDING REQUIREMENTS
Bidders must complete and attach the following documentation to the bid response
in order to be considered responsive.
a) Costs through PA Supplier Portal
b) Appendix D – Domestic Workforce Utilization Form
c) Appendix E – Worker Protection and Investment Certification Form
4
Statement of Work
1100-71890 SCI Huntingdon New Yard Exercise Track Area Paving
Project
Pursuant to Executive Order 2021-06, Worker Protection and Investment
(October 21, 2021), the Commonwealth is responsible for ensuring that every
Pennsylvania worker has a safe and healthy work environment and the
protections afforded them through labor laws. To that end, contractors and
grantees of the Commonwealth must certify that they are in compliance with
all applicable Pennsylvania state labor and workforce safety laws. Such
certification shall be made through the Worker Protections and Investment
Certification Form (BOP-2201) and the completed form must be submitted
with the bid, proposal or quote.
d) Appendix F – Reciprocal Limitations Act
e) Provide a copy of your Micro Business Certification
XIV. CONTRACTOR QUALIFICATIONS
After the bid opening, and prior to awarding the Purchase Order, the Department has
the right to request references (name, addresses and telephone numbers) of similar
work performed in the previous two (2) years as proof of qualifications to perform
the work involved.
XV. PURCHASE ORDER TERM
The term of the Contract created by the issuance of the Purchase Order shall
commence on the Original PO Effective Date printed on the Purchase Order after the
Purchase Order has been fully executed by the Commonwealth (signed and approved
as required by Commonwealth contracting procedures and sent to the Contractor). If
the Purchase Order output form does not have “Fully Executed” at the top of the first
page and does not have the name of the Purchasing Agent printed in the appropriate
box, the Purchase Order has not been fully executed. Subject to the other provisions
of the Contract, the Contract shall end on the later of: a) complete delivery and
acceptance of the awarded item(s); b) the expiration of any specified warranty and
maintenance period; c) payment by the Commonwealth for the item(s) received; or
d) any Expiration Date identified in the Purchase Order.
This is a one-year purchase order with the option of one (1) one-year renewal.
The Commonwealth reserves the right, upon notice to the Contractor, to extend any
single term of the Contract for up to three (3) months upon the same terms and
conditions.
XVI. BID AWARD
It shall be understood and agreed that any quantities listed in the solicitation are
estimated only and may be increased or decreased in accordance with the actual
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.