CHILLER REPLACEMENT-GICC

Location: Georgia
Posted: May 11, 2026
Due: May 14, 2026
Agency: City of College Park
Type of Government: State & Local
Category:
  • 41 - Refrigeration, Air Conditioning and Air Circulating Equip.
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: 26-52
Publication URL: To access bid details, please log in.
Bid Number: 26-52
Bid Title: CHILLER REPLACEMENT-GICC
Category: CP - Training
Status: Open
Description:

The purpose of this solicitation is to obtain qualified contractors to provide turnkey chiller installation services, including equipment, labor, materials, and all related work necessary for complete installation and operational functionality.

Publication Date/Time:
5/7/2026 3:00 AM
Closing Date/Time:
5/14/2026 3:00 PM
Submittal Information:
www.bidnetdirect.com//cityofcollegepark
Related Documents:

Attachment Preview

CITY OF COLLEGE PARK Contracts and Procurement Department
Attention: Carl Hall, Purchasing Department
3667 Main Street. City Hall
College Park, Georgia 30337
Email: Carlton.Hall@collegeparkga.gov Phone: (404)-767-1537ext. 1500
RE: REQUEST FOR QUOTE NO. 26-52
CHILLER REPLACEMENT
OBJECTIVE
PURPOSE
The purpose of this solicitation is to obtain qualified contractors to provide turnkey chiller installation
services, including equipment, labor, materials, and all related work necessary for complete installation
and operational functionality.
MINIMUM QUALIFICATIONS & GENERAL REQUIREMENTS
Respondents must demonstrate experience with commercial HVAC and chiller installation projects
of similar size and scope and possess all required licenses and insurance coverage. The selected
contractor shall provide all labor, materials, equipment, supervision, permits, and related services
necessary for a complete turnkey chiller installation in accordance with applicable codes,
manufacturer specifications, safety standards, and City requirements.
SCOPE of SERVICE
1. General Scope
Provide all labor, materials, equipment, supervision, engineering coordination, and
incidentals necessary to furnish and install a complete, operational chiller plant system.
Work shall be executed as a fully coordinated turnkey installation, including demolition,
replacement, integration, testing, and commissioning.
All work shall comply with:
Manufacturer requirements (including Trane installation standards where applicable)
Applicable mechanical, electrical, and building codes
Industry best practices
2. Demolition, Removal & Disposal
Remove and properly dispose of existing chiller plant equipment, including:
Existing chillers (2)
Condenser water pumps and chilled water pumps
Associated starters, VFDs, actuators, and controls
Existing chiller plant control system
Existing air compressor (if present)
Chiller isolation and head pressure control devices
Contractor shall:
Recover refrigerant per EPA regulations
Disconnect and safely remove mechanical and electrical systems
Provide rigging, cranes, and lifting operations
Dispose of all equipment and refrigerants legally and responsibly
3. New Mechanical Equipment Installation
Furnish and install:
(2) new centrifugal chillers (Trane or approved equal)
Condenser water pumps (qty per design basis)
Chilled water pumps (qty per design basis)
Cooling tower fan motors and belts (as required)
Heat exchanger cleaning and recommissioning (existing plate frame HX)
Include:
Setting, alignment, and securing of equipment on existing or new pads
Verification of service clearances
Equipment pad modifications as required
Minimum flow bypass provisions
4. Piping, Valves & Hydronic Systems
Provide complete chilled water and condenser water system modifications including:
New and modified piping for chillers, pumps, cooling towers, and heat exchanger
Condenser head pressure control valves
Isolation valves for:
o Chillers
o Cooling towers
o Heat exchanger
o Pumping systems
Minimum flow bypass piping
Pressure testing of all new and modified piping systems
System flushing and preparation for startup
Insulation replacement where removed or modified
5. Electrical Scope
Provide complete electrical integration including:
New power feeds to all mechanical equipment
Disconnect/reconnect of existing electrical services as required
New or reused breakers as applicable
Installation of:
o VFDs for chilled water pumps
o VFDs for cooling tower fans (if applicable)
Control wiring between equipment and BAS
All conduit, wire, fusing, relays, and terminations required for a complete system
6. Controls / Building Automation System (BAS)
Provide a fully functional control system including integration of all chiller plant
components.
System shall include a Trane Tracer-based BAS or approved equivalent:
Central system controller with web interface
Integration of:
o Chillers
o Pumps
o Cooling towers
o Heat exchanger
Control valves and end devices as required
Monitoring of temperatures, pressures, and equipment status
Alarms and safeties for system protection
Outside air temperature/humidity monitoring
Minimum flow bypass control logic
7. Refrigerant Monitoring & Safety Systems
Provide a dual-zone refrigerant monitoring system including:
Sensors at each chiller
Audible/visual alarms inside mechanical room
Audible/visual alarms outside mechanical room
Integration with BAS or standalone alarm system
Testing and commissioning of all alarm functions
8. Start-Up, Testing & Commissioning
Provide complete system startup including:
Factory-authorized startup assistance (Trane or equivalent)
Functional performance testing
Pressure testing of piping systems
Verification of controls and interlocks
Load testing under normal operating conditions
Final system balancing and verification
9. Documentation & Closeout
Provide:
Equipment submittals
O&M manuals
Startup reports
Warranty documentation
As-built documentation (if available)
Owner training session
Final site cleanup
10. Environmental & Regulatory Compliance
EPA-compliant refrigerant handling and disposal
Proper disposal of removed mechanical/electrical equipment
Compliance with all federal, state, and local environmental requirements
11. Safety Requirements
All work shall comply with OSHA and site safety standards including:
PPE requirements (hard hats, gloves, safety glasses, etc.)
Lockout/Tagout procedures
Rigging and lifting safety protocols
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Douglas County Board of Commissioners is seeking a design/ build contractor to provide ...

State Government of Georgia

Bid Due: 6/30/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.