Addendum No. 1
RE: Contract # C205167
WBS # 2026CPT.05.08.20391.1
STATE FUNDED
Granville County
10 SECTIONS OF SECONDARY ROADS
March 17, 2026 Letting
To Whom It May Concern:
Reference is made to the sketch maps and proposal furnished to you on this project.
The following revisions have been made to the Sketch Maps.
Sheet No.
5
6
10
Revision
Pavement schedule revised (see Sheet 6 below)
Typical Section No. 2 and Pavement Schedule revised. P1
removed. J1 changed from 8” Aggregate Base Course to 6”
Class IV Subgrade Stabilization. D1 added. V1 revised to
10.5” milling
SOQ revised to reflect quantity changes below
Please void the above listed Sheets in your sketch maps and staple the revised Sheets
thereto.
The following revisions have been made to the proposal.
Page No.
Proposal Cover
Revision
Note added that reads
“Includes Addendum No. 1 Dated 02-26-2026”.
Letting date revised
G-1
The Project Special Provision entitled CONTRACT TIME
AND LIQUIDATED DAMAGES has been revised.
The Project Special Provision entitled SCHEDULE OF
G-7
ESTIMATED COMPLETION PROGRESS has been
revised.
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
CONTRACT STANDARDS AND DEVELOPMENT
1591 MAIL SERVICE CENTER
RALEIGH, NC 27699-1591
Telephone: (919) 707-6900
Fax: (919) 250-4127
Customer Service: 1-877-368-4968
Website: www.ncdot.gov
Location:
1020 BIRCH RIDGE DR.
RALEIGH, NC 27610
C205167 (2026CPT.05.08. 20391.1, etc.)
Granville County
Please void the above listed Pages in your proposal and staple the revised Pages thereto.
On the item sheets the following pay item revisions have been made:
Item
0003- 1121000000-E
520
0011- 1575000000-E
620
0020- 1099700000-E
505
0021-1503000000-E
610
0008-1297000000-E
607
0008-1297000000-E
607
Description
AGGREGATE BASE
COURSE
ASPHALT BINDER FOR
PLANT MIX
CLASS IV SUBGRADE
STABILIZATION
ASPHALT CONC
INTERMEDIATE
COURSE, TYPE I19.0C
MILLING ASPHALT
PAVEMENT, 9-1/2"
DEPTH
Has been revised to
MILLING ASPHALT
PAVEMENT, 10-1/2"
DEPTH
Old Quantity
6,301 TON
1,125 TON
NEW ITEM
NEW ITEM
NO
QUANTITY
CHANGE
NO
QUANTITY
CHANGE
The Contractor’s bid must include these pay item revisions.
New Quantity
DELETED
1,250 TON
4,727 TON
2,513 TON
The electronic bidding file has been updated to reflect these revisions. Please download
the Addendum File and follow the instructions for applying the addendum. Bid Express
will not accept your bid unless the addendum has been applied.
The contract will be prepared accordingly.
Sincerely,
Ronald E. Davenport, Jr., PE
State Contract Officer
RED/jjr
C205167 (2026CPT.05.08. 20391.1, etc.)
Attachments
cc: Mr. Wiley W. Jones III, PE
Ms. Becca J. Gallas, PE
Mr. Ken Kennedy, PE
Mr. Malcolm Bell
Granville County
Mr. Forrest Dungan, PE
Ms. Jaci Kincaid
Mr. Jon Weathersbee, PE
Project File (2)
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
RALEIGH, N.C.
PROPOSAL
INCLUDES ADDENDUM No.1 DATED 02-26-2026
DATE AND TIME OF BID OPENING: Mar 17, 2026 AT 02:00 PM
CONTRACT ID
WBS
C205167
2026CPT.05.08.20391.1
FEDERAL-AID NO. STATE FUNDED
COUNTY
GRANVILLE
T.I.P NO.
MILES
17.404
ROUTE NO.
LOCATION
10 SECTIONS OF SECONDARY ROADS.
TYPE OF WORK MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION
NOTICE:
ALL BIDDERS SHALL COMPLY WITH ALL APPLICABLE LAWS REGULATING THE PRACTICE OF GENERAL CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE
GENERAL STATUTES OF NORTH CAROLINA WHICH REQUIRES THE BIDDER TO BE LICENSED BY THE N.C. LICENSING BOARD FOR CONTRACTORS WHEN BIDDING
ON ANY NON-FEDERAL AID PROJECT WHERE THE BID IS $30,000 OR MORE, EXCEPT FOR CERTAIN SPECIALTY WORK AS DETERMINED BY THE LICENSING BOARD.
BIDDERS SHALL ALSO COMPLY WITH ALL OTHER APPLICABLE LAWS REGULATING THE PRACTICES OF ELECTRICAL, PLUMBING, HEATING AND AIR CONDITIONING
AND REFRIGERATION CONTRACTING AS CONTAINED IN CHAPTER 87 OF THE GENERAL STATUTES OF NORTH CAROLINA. NOTWITHSTANDING THESE LIMITATIONS
ON BIDDING, THE BIDDER WHO IS AWARDED ANY FEDERAL - AID FUNDED PROJECT SHALL COMPLY WITH CHAPTER 87 OF THE GENERAL STATUTES OF NORTH
CAROLINA FOR LICENSING REQUIREMENTS WITHIN 60 CALENDAR DAYS OF BID OPENING.
BIDS WILL BE RECEIVED AS SHOWN BELOW:
THIS IS A ROADWAY PROPOSAL
5% BID BOND OR BID DEPOSIT REQUIRED
C205167 2026CPT.05.08.20391.1
G-1
Granville County
PROJECT SPECIAL PROVISIONS
GENERAL
CONTRACT TIME AND LIQUIDATED DAMAGES:
(7-1-95) (Rev. 12-18-07)
108
The date of availability for this contract is April 27, 2026.
SP1 G10 A
The completion date for this contract is October 27, 2027.
Except where otherwise provided by the contract, observation periods required by the contract
will not be a part of the work to be completed by the completion date and/or intermediate
contract times stated in the contract. The acceptable completion of the observation periods that
extend beyond the final completion date shall be a part of the work covered by the performance
and payment bonds.
The liquidated damages for this contract are One Thousand Six Hundred Dollars ($ 1,600.00)
per calendar day.
INTERMEDIATE CONTRACT TIME NUMBER 1 AND LIQUIDATED DAMAGES:
(2-20-07)
108
SP1 G14 A
The Contractor shall complete the required work of installing, maintaining, and removing the
traffic control devices for lane closures and restoring traffic to the existing traffic pattern. The
Contractor shall not close or narrow a lane of traffic on Maps #5, #6, or #7 during the following
time restrictions:
DAY AND TIME RESTRICTIONS
Monday thru Sunday, 5:00 PM to 8:00 AM
In addition, the Contractor shall not close or narrow a lane of traffic on Any Map, detain and/or
alter the traffic flow on or during holidays, holiday weekends, special events, or any other time
when traffic is unusually heavy, including the following schedules:
HOLIDAY AND HOLIDAY WEEKEND LANE CLOSURE RESTRICTIONS
1. For unexpected occurrence that creates unusually high traffic volumes, as directed by
the Engineer.
2. For New Year's Day, between the hours of 6:00 AM December 31st and 7:00 PM
January 2nd. If New Year's Day is on a Friday, Saturday, Sunday or Monday, then until
7:00 PM the following Tuesday.
3. For Easter, between the hours of 6:00 AM Thursday and 7:00 PM Monday.
4. For Memorial Day, between the hours of 6:00 AM Friday and 7:00 PM Tuesday.