CUNY John Jay College Haaren Hall Athletic Facility Restoration and HAZMAT Abatement

Location: New York
Posted: Sep 18, 2026
Due: Oct 16, 2026
Agency: State Government of New York
Type of Government: State & Local
Category:
  • F - Natural Resources and Conservation Services
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: 380550
Publication URL: To access bid details, please log in.
CUNY John Jay College Haaren Hall Athletic Facility Restoration and HAZMAT Abatement
Solicitation #: 380550
Issue Date: 09/18/2026
Proposal Due: 10/16/2026 - 10:15 AM
Classification: Construction Contracts
Type: Expression of Interest (EOI)
Status: New
Subcontracting Provisioning Goals (%)
Minority Owned: 18
Women Owned: 12
Service Disabled Veteran Owned: 6
Equal Employment Opportunity: 45
Contract Terms
October 31, 2027
Location Where Goods to be Delivered or Service Performed
John Jay College, Haaren Hall, 899 10th Avenue, New York, New York 10019

THIS SOLICITATION IS FOR EXPRESSIONS OF INTEREST (EOI) ONLY

See the Eligibility Requirements further down in this document.

The scope of work includes but is not limited to the following:

The rehabilitation and refurbishment for the Roof and recreational areas of the John Jay College Harren Hall Complex. The work will address critical issues related to waterproofing integrity, building envelope deterioration, code compliance, and the enhancement of active use areas such as sports courts, children's play spaces, and rooftop programming zones.

Cost Range: $11 million – 12 million

Project Labor Agreement

The successful low bidder as a condition of being awarded this Contract, must execute the PLA included in the Contract Documents following the Form of Bid. The Work undertaken in connection with this Project will be governed by, and subject to the conditions set forth in the PLA. All Subcontractors of every tier, will be required to execute a Letter of Assent, included in the enclosed PLA, agreeing to be bound by the PLA. The PLA has been approved by the Building and Construction Trades Department, AFL-CIO.

Bidders for the construction of this project will be selected only after the review and evaluation of the qualification packages received in response to this notice.

Please note that the project drawings and specifications attached to DASNY’s website associated with this solicitation do not reflect 100% construction / bid documents. The documents provided are for reference only. Finalized construction / bid documents shall be distributed to the qualified contractors invited to bid.

Please find links to the specifications and drawings below:

Specifications

Drawings

General Conditions for Construction dated February 4, 2026, will apply to the Contract Documents.

The anticipated goals for EEO and M/WBE participation in the Work of the Contract are as follows:

Percent of Total Work Force (EEO):

Minority & Women Workforce Goal (for all trades) 45%

Percent of Total Contract (M/WBE):

Minority Business Enterprise Goal 18%

Women's Business Enterprise Goal 12%

Service-Disabled Veteran Owned Businesses 6%

Please note the Owner will determine the goals for EEO and M/WBE participation when the finalized construction / bid documents are distributed to the qualified contractors invited to bid.

Firms shall provide one (1) copy in pdf format of the EOI package via e-mail to ccontracts@dasny.org .

Upon receipt, confirmation of delivery will be provided by email for each submission. If a firm does not receive confirmation of receipt, the EOI package shall be deemed not received. Firms are responsible for ensuring that confirmation of receipt is obtained and should follow up promptly if confirmation is not received.

Instructions for Submission of the EOI Packages:

Each firm responding to this solicitation shall submit an EOI package organized and assembled in a clear, logical and professional manner consistent with the requirements set forth herein. Failure to comply with these instructions may render the submission non-responsive and subject to rejection.

Each package shall be submitted with:

  1. A Cover Page that clearly identifies:
  • The Legal Name of the Company submitting the EOI
  • The Project Name for which the EOI is being submitted
  • The Date of Submission
  1. Immediately following the Cover Page, the contractor shall provide a Table of Contents listing all Tabbed sections, exhibits and attachments contained in the submission with the corresponding page number.
  2. The EOI package shall be divided into clearly labeled tabbed sections, each separated by a Cover Sheet identifying the contents that follow. Tabs should correspond to the order of the items specified in the solicitation.
  3. All items outlined in each Tab must be provided. The Owner may reject any EOI package not prepared and submitted in accordance with the provisions as stated in this solicitation.

Tabs must be in the following sequence:

Tab 1 – Company Profile

Provide a company profile that includes the following information:

  • Company Contact – Name, Title, E-mail address, and Phone Number of primary point of contact for this project.
  • Date Established – When the company was founded.
  • Company Address – Primary business location.
  • Ownership Information – Name and resumes of all principal owners.
  • Client List – Summary of public and private sector clients.
  • Employee Breakdown – Number of employees by role: Architects, Engineers, Project Managers, Administrative Staff, Superintendents and Foremen, Trade Laborers.
  • Equipment - Overview of all equipment owned by the company.
  • Self-Performed Services - Description of all services the company performs directly (not subcontracted).

Tab 2 – Experience

Provide documentation showing a minimum of five (5) years of experience with projects similar in size, scope, and complexity to the one being proposed.

Provide details for the five (5) relevant projects that have been completed- or substantially completed- within the last ten (10) years.

For each project, include the following information:

  • Name of the project designer
  • Firm name and contact information
  • Project title and location/facility
  • Brief description of the project
  • Total construction cost
  • Construction start date
  • Substantial completion date
  • Indicate role as prime contractor or subcontractor
  • Percentage of the work that was self-performed

If applicable, also include a list of all DASNY projects completed within the last 5 years.

Tab 3 – Project Schedules

Provide three (3) sample project schedules for the same projects listed in Tab 2. These schedules should reflect projects of similar size, scope, and complexity to the referenced project.

Tab 4 – Safety Program

Provide the firm’s written safety program or site safety plan. Include the résumé of the person responsible for overseeing project safety.


Tab 5 – Résumés

Provide names and résumés for the proposed project team. Each résumé should demonstrate experience with at least one project of similar size, scope, and complexity to the referenced project. Team members should include, at minimum: Project Manager, Site Superintendent, Project Engineer, and Quality Control Representative.


Tab 6 – Potential Subcontractors

Provide a list of potential subcontractors for this project. For each potential subcontractor, identify anticipated M/WBE subcontract participation, the subcontractor’s trade, and brief description of their scope of work.


Tab 7 – Anticipated Workload

Provide a list other projects you firm will be working on during this project’s construction period. Include a statement explaining how your firm will successfully complete this project within the required timeframe.

Tab 8 – Experience Modification Rating

Provide a letter from your insurance provider indicating the firm’s Experience Modification Rating (EMR) over the past three (3) years. If your EMR is above 1.00, include a written explanation.

Tab 9 – Bonding Capacity

Provide a signed letter from a Surety Company attesting to your firm’s single, aggregate and available bonding capacity. If your available bonding capacity does not to meet the bonding requirements of this contract, you must explain how your firm will meet the bonding requirements.

Tab 10 – NYS Vendor Responsibility Questionnaire

Provide your online or hardcopy NYS Vendor Responsibility Questionnaire For-Profit Construction (CCA-2) certified within the last five (5) months. Firms shall provide the Certification page for the online version or the full questionnaire, if submitting a hardcopy.

Eligibility/Qualifications Requirements/Preferences:

Tabs 1 through 7 will be scored by a DASNY committee. Firms deemed qualified from this solicitation will be included on a short list and invited to submit a bid in the near future. Firms not following the EOI package requirements as noted shall be considered non-responsive to the advertisement. The construction contract will be held by DASNY.

Contract Security, EEO/AA Insurance, NY State Vendor Responsibility Questionnaire (Executive Order 125). See Contract Documents for details.

In accordance with State Finance Law § 139-j and § 139-k, this solicitation includes and imposes certain restrictions on communications between Dormitory Authority personnel and an Offerer during the procurement process. Designated staff for this procurement are: The Project Manager and ccontracts@dasny.org . Contacts made to other Dormitory Authority personnel regarding this procurement may disqualify the Offerer and affect future procurements with governmental entities in the State of New York. Please refer to the Authority's website ( www.dasny.org ) for Authority policy and procedures regarding this law, or the OGS website ( www.ogs.state.ny.us/aboutogs/regulations/defaultAdvisoryCouncil ) for more information about this law. All proposers, domestic and foreign, must be in compliance with New York State business registration requirements. Contact the NYS Department of State regarding compliance. In addition, business entities proposing to provide professional engineering services must obtain a Certificate of Authorization to Provide Engineering Services in New York State from the State Education Department. Proposals must be submitted in the full legal name of the proposer, or the full legal name plus a registered assumed name of the proposer, if any.

Primary Contact

Dominick Donadio

Sr. Procurement Administrator

Dormitory Authority of the State of New York

Procurement

Construction Contracts

515 Broadway

Albany, NY 12207-2964

Phone: 518-257-3000

Email: ccontracts@dasny.org

Submit To Contact

Dominick Donadio

Sr. Procurement Administrator

Dormitory Authority of the State of New York

Procurement

Construction Contracts

515 Broadway

Albany, NY 12207-2964

Phone: 518-257-3000

Email: ccontracts@dasny.org

Attachment Preview

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
SECTION 02 41 19
SELECTIVE DEMOLITION AND REMOVAL
PART 1 -GENERAL
1.01 GENERAL REQUIREMENTS
A. All work shall conform to the latest industry practices and standards as applicable.
B. All work shall be performed by competent workmen trained and experienced in the
particular type of work.
C. This Contractor shall employ a full time competent person with a 30-hour OSHA to
implement this Contractor's safety program.
D. The Contractor will provide at its own cost a daily inspection of all demolition
operations by a license professional engineer to insure that they comply with
approved demolition methods, that structural stability is maintained, that the fire
standpipe and sprinklers on floors not being demolished and remain operational, and
that there is an elevator in readiness for emergency use, all of which is in accordance
with applicable governmental regulations.
E. All workers operating torches must have proper certification from local, state and
federal jurisdictions. The Contractor shall provide Fire Guards as required and
certified by local, state and federal jurisdictions. All costs associated with Fire Guards
are included in the Contract Price.
F. Inspection reports will be provided to the NYCHA on a daily basis.
G. The Contractor shall maintain two (2) unobstructed means of egress all times
ESPECIALLY FOR ANY WORK PERFORMED ON THE MAIN ROOFS.
H. This Contractor will develop a written Respiratory Protection Program in accordance
with local, state and federal regulations to be submitted to the NYCHA a minimum of
4 weeks prior to mobilization on Site. All costs associated with the Respiratory
Protection program are included in the Contract Price.
I. This Contractor will develop a written Project specific Dust Control Program in
accordance with local, state and federal regulations to be submitted to the NYCHA a
minimum of 4 weeks prior to mobilization on Site. All costs associated with the Dust
Control Program and its maintenance is included in the Contract Price.
J. This Contractor shall perform all demolition and removal work required for the
Selective Demolition and Removal 024119 - 1

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
installation of the new specified work
1.02 SCOPE OF WORK
A. Prior to start of demolition and removal of any item, Contractor shall first perform
asbestos abatement and follow lead-safe work practices of affected items as
indicated in sections 02 82 14 and 02 83 19 respectively of Division 2.
B. This section includes demolition and removal of selected portions of a building or
structure. Existing items to be removed and disposed of include but are not limited to:
1. Existing roofs at all indicated locations down to structural deck including but not
limited to:
a. Initial membrane
b. Insulation
c. Protection board
d. Built up roofing membrane
e. Stone ballast
2. Perimeter and penetration flashings at all indicated locations.
3. Existing door saddles.
4. Existing metal edge flashing, scupper, and leaders (U.O.N).
5. Salvage of existing items to be placed in storage and/or reinstalled.
6. Saw cut and remove without damaging existing brickwork, the deteriorated mortar
joints of existing brickwork to be re-pointed at scattered locations at roof
bulkheads, and compactor stacks as shown on contract drawings and as directed
by Authority's Representative.
1. Protection of existing structure, windows, fixtures, electrical, mechanical and plumbing
items to remain, finishes, and any other equipment or objects scheduled to remain.
2. Remove demolished materials from the site as works progresses and maintain the site
unencumbered of materials and equipment. Provide dumpsters and closed chutes as
required to dispose of all debris and demolished materials.
3. All other labor and materials and work described in the contract drawings and I or
specifications herein or required to make the work complete.
Selective Demolition and Removal 024119 - 2

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
4. It must be noted that demolition and removal of certain items will require the abatement
of lead and asbestos. Demolition and removal of these materials will require the use of
qualified licensed technicians. All abatement must be as per abatement procedures
described in the abatement sections of Division 02, in accordance with the latest rules
and regulations of all agencies having jurisdiction.
5. Dust control: Follow Dust Control specifications as described in Section 01 56 00.
1.03 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site,
unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Items indicated on Drawings for removal and salvage. Detach
items from existing construction in a manner to prevent damage, and deliver as indicated
in this Section.
C. Remove and Reinstall: Items indicated on Drawings for removal and reinstallation (e.g.,
fixtures, equipment, building elements, etc.). Detach items from existing construction in a
manner to prevent damage, prepare them for reuse, and reinstall them where indicated.
D. Existing to Remain: Existing items of construction that are not to be removed and that
are not otherwise indicated to be removed, removed and salvaged, or removed and
reinstalled.
1.04 QUALITY ASSURANCE
A. Comply with the following:
A. ANSIIASSE A10.6 "Safety Requirements for Demolition Operations."
B. NFPA 241 "Standard for Safeguarding Construction, Alterations and Demolition
Operations."
1.05 MATERIAL OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise
indicated to remain Authority's property, demolished materials shall become Contractor's
property and shall be removed from Development site.
1.06 SUBMITTALS
A. Qualification Data: For firms and persons specified in "Quality Assurance" Article to
demonstrate their capabilities and experience. Include lists of completed projects with
Selective Demolition and Removal 02 41 19 - 3

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
project names and addresses, names and addresses of architects and owners, and
other information specified.
B. Schedule of Selective Demolition Activities: Indicate the following:
1. Ensure Authority's on-site operations are uninterrupted.
2. Coordination for shutoff, capping, and continuation of utility services.
C. Inventory: After selective demolition is complete, submit a list of items that have been
removed and salvaged.
1.07 QUALITY ASSURANCE
A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition
work similar in material and extent to that indicated for this Project.
B. Contractor's hired Professional Engineer Qualifications: A Professional Engineer who is
legally qualified to practice in the State of New York and who is experienced in providing
engineering services of the kind of Work indicated.
C. Regulatory Requirements: Comply with governing EPA notification regulations before
beginning selective demolition. Comply with hauling and disposal regulations of
authorities having jurisdiction.
D. Standards of compliance: Conform to the requirements of the Building Code of the City
of New York, DEP rules and regulations, and the requirements of governing codes such
as which affect the conduct of the Work, except where a stricter requirement is specified
herein, such stricter requirement shall apply. Comply with applicable regulatory and
jurisdictional requirements governing the work, materials, or project, even though such
requirements are not listed.
E. Pre-demolition Conference: Conduct conference at Project site to comply with
requirements of this Contract. Review methods and procedures related to selective
demolition including, but not limited to, the following:
1. Inspect and discuss condition of construction to be selectively demolished.
2. Review structural load limitations of existing structure.
3. Review and finalize selective demolition schedule and verify availability of materials,
demolition personnel, equipment, and facilities needed to make progress and avoid
delays.
Selective Demolition and Removal 02 41 19 - 4

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
4. Review requirements of work performed by other trades that rely on substrates
exposed by selective demolition operations.
F. Preparation: Before cutting and removing any existing work or cutting any new work,
Contractor shall coordinate that work with other work to avoid interference and over
cutting of the work. Obtain necessary permits without additional compensation.
G. Structural Work: Do not cut Structural Work in a manner that would result in a reduction
of load-carrying capacity or of load-deflection ratio.
H. Visual Requirements: Do not cut or remove work in a manner that would, in the
Authority's Representative's opinion, result in lessening the building's aesthetic
qualities. Do not remove or cut work in a manner that would result in substantial visual
evidence judged by the Authority's Representative to be visually unsatisfactory.
1.08 MAINTENANCE AND PROTECTION
A. Maintain and protect, (where necessary), both temporarily and permanently, the
structural integrity, continuous operation and use of the existing buildings. Safety and
stability shall be maintained at all times. Maintenance and protection operations shall
comply with applicable requirements of governing authorities.
B. Protection: Provide adequate and effective, suitable means of protecting Authority
employees, residents, or other persons from operations included in this section. Provide
adequate and effective temporary supports, and bracing, etc., to prevent movement of
work in place that might be affected by selective demolition.
C. Maintenance: Assume responsibility for the maintenance of safety and protection of the
existing buildings, building appurtenances, equipment including and all persons therein
and their property as more particularly provided in the General and Supplementary
General Conditions.
D. Lighting: The Electrical Sub-Contractor will maintain existing electrical lighting, power
and power facilities where work is being performed. Provide and maintain suitable
temporary electrical lighting which will be equivalent to the existing lighting levels or as
directed by the Authority's Representative.
1.09 PROJECT CONDITIONS
A. Provide not less than [72] hours notice to Authority's Representative of activities that will
affect Authority's operations.
Selective Demolition and Removal 02 41 19 - 5

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
B. Maintain access to existing walkways, corridors, and other adjacent occupied or used
facilities.
1. Do not close or obstruct walkways, corridors, or other occupied or used facilities
without written permission from authorities having jurisdiction.
C. Authority assumes no responsibility for condition of areas to be selectively demolished.
1. Conditions existing at time of inspection for bidding purpose will be maintained by
Authority as far as practical.
D. Hazardous Materials: Hazardous materials present in building to be demolished and
legally disposed of as indicated in the related sections elsewhere in the Contract
Documents. A report on the presence of hazardous materials is on file for review and
use. Examine report to become aware of locations where hazardous materials are
present. Do not disturb hazardous materials or items suspected of containing hazardous
materials except under procedures specified elsewhere in the Contract Documents.
E. Storage or sale of removed items or materials on-site will not be permitted.
F. The Contractor shall be responsible for protection of the building, existing roof
accessories and equipment, which are to remain or be reinstalled in complete
accordance with Contract requirements.
G. If the Contractor damages or fails to protect or salvage any items noted to be repaired or
replaced under this Contract, then such damaged items shall be repaired or replaced by
the Contractor to the complete satisfaction of the Authority's Representative at no
additional cost to the Authority.
H. Contractor shall conduct work in such manner and at such times and with such
precautions and safeguards as may be required for the purpose of avoiding interference
with the safe and continuous operations at each of the buildings and of avoiding
interference with or injury to Authority personnel, residents, Contractor's personnel and
other persons.
I. Contractor shall comply with the requirements of the Authority's Representative, as to
the use of the building with regard to the use of construction equipment, storing of
materials, etc., to the end that interference with the safe and continuous operation of
existing facilities and interference with or injury to Authority personnel, residents,
Contractor's personnel, and other persons, and damage to their property or that of the
Authority may be avoided.
Selective Demolition and Removal 02 41 19 - 6

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
PART 2- PRODUCTS
2.01 REPAIR MATERIALS
A. Use repair materials identical to existing materials.
1. If identical materials are unavailable or cannot be used for exposed surfaces, use
materials that visually match existing adjacent surfaces to the fullest extent possible.
But the materials must be approved by NYCHA before using that material. Use
materials whose installed performance equal or surpass that of existing materials.
B. Comply with material and installation requirements specified in individual Specification
Sections.
PART 3- EXECUTION
3.01 GENERAL
A. EXAMINATION:
1. Survey existing conditions and correlate with requirements indicated to determine
extent of selective demolition required.
2. Inventory and record the condition of items to be removed and reinstalled and items
to be removed and salvaged.
3. When unanticipated mechanical, electrical, or structural elements that conflict with
intended function or design are encountered, investigate and measure the nature
and extent of conflict. Promptly submit a written report to Authority's Representative.
4. Contractor's hired Safety Engineer shall supervise selective demolition of structural
items in order to avoid structural deficiency or unplanned collapse of any portion of
structure or adjacent structures during demolition operations
B. Shoring, Bracing and Structural Support:
1. Provide shoring, bracing, and structural supports to preserve stability and prevent
movement, settlement or collapse of construction and finishes to be selectively
demolished and adjacent facilities to remain.
2. Retain a qualified professional engineer to design temporary shoring, bracing, and
structural support as needed.
3. Strengthen or add new supports when required during progress of selective
demolition.
Selective Demolition and Removal 02 41 19 - 7

DESIGN DEVELOPMENT 60% JOHN JAY COLLEGE - HAAREN HALL
January 28, 2026 ROOFTOP ATHLETIC FACILITY RESTORATION
4. If safety of structure appears to be endangered, cease operations immediately, notify
Owner and Architect, and take precautions to support structure until determination is
made for continuing operations.
C. Demolish and remove existing construction only to the extent required by new
construction and as indicated.
1. At any one time, remove only that portion of the existing construction that can be
immediately protected so that building interior remains watertight and weathertight.
2. Where selective demolition converges with existing construction to remain:
a. Comply with Section 017329 (Cutting and Patching).
b. Conduct operations in a manner to protect adjacent and surrounding surfaces and
material to remain from damage. Do not damage substrates to remain.
c. Neatly cut openings and holes plumb, square, and true to dimensions required.
Use cutting methods least likely to damage construction to remain or adjoining
construction. Use hand tools or small power tools designed for sawing or grinding,
not hammering and chopping, to minimize disturbance of adjacent surfaces.
d. Cut or drill from the exposed or finished side into concealed surfaces to avoid
marring existing finished surfaces.
e. Remove residual mortar, adhesives, or other matter, from material to remain, in
preparation for tie-in of new Work. (For example, where deficient brick has been
removed, remove mortar around perimeter of area in preparation for new brick
and mortar.)
3. Where whole units are being removed for replacement (e.g., masonry units, sills,
lintels, wall panels, etc.), cut out whole units from joint to joint in a manner to permit
replacement of full size units, and carefully remove without damaging surrounding
construction.
4. Do not use cutting torches until Work area is cleared of flammable materials. At
concealed spaces (e.g., duct and pipe chases, etc.}, verify condition and contents of
hidden space before starting flame-cutting operations. Maintain fire watch and
portable fire-suppression devices during flame-cutting operations. Maintain adequate
ventilation when using cutting torches.
3.02 PREPARATION
A. Dangerous Materials: Remove, collect, and dispose of chemicals, gases, explosives,
Selective Demolition and Removal 02 41 19 - 8

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...www.hcr.ny.gov 1|Page Table of Contents: 1 Introduction...

State Government of New York

Bid Due: 11/12/2026

...Avenue New York, NY 10022 www.hcr.ny.gov 1|Page Table of Contents: 1 Introduction...

State Government of New York

Bid Due: 11/12/2026

...TABLE OF CONTENTS SECTION 1 - PURPOSE AND INTRODUCTION...

City of Buffalo

Bid Due: 10/23/2026

..., the contractor shall provide a Table of Contents listing all Tabbed sections, ...

State Government of New York

Bid Due: 11/12/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.