County Administration Building Electrical Assessment

Location: Florida
Posted: Jun 11, 2026
Due: Jul 31, 2026
Agency: County of Lake
Type of Government: State & Local
Category:
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: Q2026-00105
Publication URL: To access bid details, please log in.
Number Title Status Due Date Contact
Q2026-00105
County Administration Building Electrical Assessment
Open

7/31/2026 3:00:00 PM William Ponko Details Tabulation

Attachment Preview

OFFICE OF FACILITIES MANAGEMENT SCOPE OF WORK
Project Name: County Administration Building
Address: 315 W Main St., Tavares, Fl 32778
Project Manager: Paul Doran
Unless otherwise noted, the Contractor shall provide all required labor, material, equipment, plans, engineering, surveys,
permitting, and local and state inspections to provide 100% turnkey project. Change orders shall not be issued for incidental
items or tasks that should have been reasonably construed to be part of the project by the Contractor.
PURPOSE
The purpose of this solicitation is to select a Certified Electrical Contractor to perform a comprehensive electrical system
assessment for the County Administration Building located at 315 W Main St., Tavares, FL 32778. The assessment is to
evaluate safety, code compliance, operational reliability, and capacity of existing electrical infrastructure. The assessment
shall identify deficiencies, verify system ratings, and provide recommendations for corrective action and capital planning.
The assessment shall be performed after business hours.
SCOPE OF WORK
The Contractor shall provide all labor, supervision, equipment, tools, and materials necessary to perform a comprehensive
electrical system assessment including, but not limited to, the following:
1. Load and Overcurrent Protection Evaluation
* Verify amperage requirements of existing electrical loads
* Confirm conductor sizing and ratings
* Evaluate overcurrent protective devices for proper sizing and coordination
* Identify overloaded circuits and undersized components
2. Plans and Specifications Review
* Compare existing installation to available plans and specifications
* Identify deviations from design documents and as-built drawings
* Document undocumented field modifications
3. Code Compliance Assessment
* Identify electrical code violations in accordance with applicable codes
* Review installation methods for compliance
* Document improper connections and installations
* Identify potential safety hazards
4. Panelboard and Equipment Verification
* Verify proper panel sizes and configurations
* Confirm available capacity and spare breaker space
1

* Verify rating of all electrical equipment including panels, disconnects, transformers, and switchgear
* Confirm compatibility of connected loads with equipment ratings
5. Testing and Performance Checks
* Perform operational testing of electrical distribution equipment
* Evaluate system performance under normal operating conditions
* Identify abnormal operating conditions or load imbalances
6. Infrared (Thermographic) Testing
* Perform infrared scanning of electrical panels, switchgear, transformers, and major connections
* Identify overheating components and loose connections
* Provide thermographic images and analysis
7. Ground Integrity Testing
* Test grounding electrode system
* Verify continuity of equipment grounding conductors
* Identify deficiencies in grounding system
8. Insulation Resistance Testing
* Perform insulation resistance testing on feeders and selected circuits
* Identify deteriorated insulation and potential failure points
9. Equipotential Bonding Testing
* Verify equipment bonding where applicable
* Confirm bonding between electrical equipment and grounding system
* Identify missing or inadequate bonding
10. Panel Schedule and Circuit Accuracy
* Verify panel schedules for accuracy
* Confirm circuit labeling matches field conditions
* Identify unidentified or mislabeled circuits
* Document available spare capacity
11. Documentation and Reporting
* Provide written report summarizing findings
* Include photographs and thermographic images
* Provide testing data and measurements
* Identify code violations and safety concerns
* Provide prioritized recommendations for corrective actions
* Identify capacity concerns and future planning considerations

This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Project ID: Title: Median Holiday Lights Phase 3C Addenda: 0 Release Date: 9/11/2026

City of Dania Beach

Bid Due: 10/02/2026

Project ID: 26-8677 Title: Adaptive Traffic Control System-Grant Funded Addenda: 0 Release Date:

Collier County

Bid Due: 10/12/2026

Solicitation Details You can review the detailed information about the solicitation here. If

Manatee County

Bid Due: 10/07/2026

NOTICE OF INVITATION TO BID STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION BID

State Government of Florida

Bid Due: 10/13/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.