McNary Potable Water Upgrades

Location: Federal
Posted: Mar 9, 2026
Due: Mar 24, 2026
Agency: DEPT OF DEFENSE
Type of Government: Federal
Category:
  • Z - Maintenance, Repair or Alteration of Real Property
Solicitation No: W912EF26RSS14
Publication URL: To access bid details, please log in.
Follow
McNary Potable Water Upgrades
Active
Contract Opportunity
Notice ID
W912EF26RSS14
Related Notice
Department/Ind. Agency
DEPT OF DEFENSE
Sub-tier
DEPT OF THE ARMY
Major Command
US ARMY CORPS OF ENGINEERS
Sub Command
ENGINEER DIVISION NORTHWESTERN
Sub Command 2
ENDIST WALLA WALLA
Office
US ARMY ENGINEER DISTRICT WALLA WAL
Looking for contract opportunity help?

APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.

APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.

The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).

General Information
  • Contract Opportunity Type: Sources Sought (Original)
  • Original Published Date: Mar 09, 2026 05:02 am PDT
  • Original Response Date: Mar 24, 2026 03:00 pm PDT
  • Inactive Policy: 15 days after response date
  • Original Inactive Date: Apr 08, 2026
  • Initiative:
    • None
Classification
  • Original Set Aside:
  • Product Service Code: Z1KA - MAINTENANCE OF DAMS
  • NAICS Code:
    • 237990 - Other Heavy and Civil Engineering Construction
  • Place of Performance:
Description

The US Army Corps of Engineers (USACE), Walla Walla District is seeking business sources for a construction project entitled: McNary Lock & Dam Potable Water Upgrades.





The work is located at McNary Dam on the south shore of the project footprint located in Umatilla County, Oregon. 100% performance and payment bonds will be required. The North American Industry Classification System (NAICS) code for this project is 237990 and the associated small business size standard is $45,000,000.





This sources-sought announcement is a tool to identify concerns with the capability to accomplish the work. This is not a solicitation. Only those companies which respond to this announcement by submitting the following information (items one through five) will be used in determining whether to set aside this requirement.






  • Provide a Capability Statement expressing interest in this requirement, capability of performing a contract of this magnitude and complexity, list any special qualifications and certifications held by the company, as well as any in-house personnel capabilities related to accomplishing the summary scope of work for this requirement.


  • Provide a list of your company’s technical experience similar to or the same as the summary scope of work for this requirement. Include a brief description of the project scope, schedule, dollar value and the firm’s role in the project. If any of the experience is that of a subcontractor, please specify that information in your response.


  • Provide a statement of your company’s bonding capacity. A statement from your surety is NOT required.


  • Provide a statement of your company’s business size and type (HUBZone, Service Disabled Veteran Owned, 8(a), woman-owned).


  • Provide the percentage of work you (as the price) intend to perform. If you intend to subcontract a major portion of the work (defined as at least 20% of the work), please include this information in your response.





Submit this information to Preston Jones, Contract Specialist, 201 North 3rd Avenue, Walla Walla, Washington 99362 or via email to Preston.E.Jones@usace.army.mil. Your response to this notice must be received on or before 3:00PM on March 24, 2026.







Summary of Scope of Work:





Using USACE supplied plans and specifications, upgrade the existing McNary Dam Potable Water Distribution System through a construct contract to replace existing potable water piping.





The existing potable water system must continue to operate during the construction upgrades and remain on-line until testing and commissioning of the upgraded system are completed.





The new water distribution system construction effort will include:




  • Pipe trench excavations for the new potable water distribution pipelines;

  • Valves and valve groups subsurface enclosures (concrete manholes);

  • During the construction phase to upgrade the water distribution system, demolition will be required for some existing valve groups and piping.





The new potable water pipeline will be fed from an existing common tie-in point. Demolition will be required on some of the old pipelines locations. Modifications to existing concrete vaults, as well and provision of a new valve vault will be required. The work includes the installation of two parallel 8-inch pipelines along a 1,400-foot section and a third 8-inch redundant line approximately 240 feet long. The total project involves installing approximately 3,040 linear feet of new pipe.





Ancillary site work to include demolition of abandoned rail road ties, earthwork repairs to areas of gravel settlement, and replacement of an adjacent concrete slab. The concrete pad replacement will be approximately 852 square feet of reinforced concrete.





The total construction disturbance area is estimated to be just over 1 acre, with an approximate 0.5-acre contractor staging area.



Requirements during construction include the presence of a Site Safety and Health Officer (SSHO), who must be assigned no other duties during the duration of this construction contract and a Contractor Quality Control Manager (CQC) on site at all times when work is performed. The SSHO is required to have 30 hour OSHA training and the CQC will be required to have taken the Corps of Engineers course entitled Construction Quality Management for Contractors. The Contractor will be required to develop and maintain a network analysis system (NAS) schedule for this project. A scheduler will be required to develop and maintain the required schedule. All on-site work will be subject to the Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1). The Contractor will be required to utilize the Corps of Engineers electronic system (Quality Control System) to manage and transmit certain records to the Government.






Attachments/Links
Contact Information
Contracting Office Address
  • CONTRACTING DIVISION 201 NORTH 3RD AVE
  • WALLA WALLA , WA 99362-1876
  • USA
Primary Point of Contact
Secondary Point of Contact
History
  • Mar 09, 2026 05:02 am PDTSources Sought (Original)
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...4610010229970 CARTRIDGE,WATER DEMINE: Line 0001 Qty 750 UI EA Deliver To: W1A8 DLA ...

DEPT OF DEFENSE

Bid Due: 6/11/2026

...4610013136086 DEMINERALIZER,WATER: Line 0001 Qty 80 UI EA Deliver To: DLA DISTRIBUTION DEPOT ...

DEPT OF DEFENSE

Bid Due: 6/05/2026

...Follow 45--TANK,WATER CLOSET Active Contract Opportunity Notice ID SPE8E826T3834 Related Notice... Manufacturing Place ...

DEPT OF DEFENSE

Bid Due: 6/08/2026

...Follow 45--SEAT,WATER CLOSET Active Contract Opportunity Notice ID SPE8E826T4072 Related Notice... Manufacturing Place ...

DEPT OF DEFENSE

Bid Due: 6/15/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.