| Location: | North Carolina |
|---|---|
| Posted: | Sep 24, 2026 |
| Due: | Oct 15, 2026 |
| Agency: | State Government of North Carolina |
| Type of Government: | State & Local |
| Category: |
|
| Solicitation No: | 274-PR-2026FRPMBT-DBR |
| Publication URL: | To access bid details, please log in. |
| Solicitation Number: | 274-PR-2026FRPMBT-DBR |
| Project Title: | Re-advertisement Design Build Services Forest Ridge Park Mountain Bike Trail |
| Description: | Pursuant to NC General Statutes § 143-128.1A, the City of Raleigh is seeking one or more qualified design-build (DB) teams to provide design and construction services for the natural surface mountain bike trails at Forest Ridge Park. |
| Opening Date: | 10/15/2026 3:00 PM |
| Posted Date: | 9/25/2026 |
| Status: | Open |
| Department: | CITY OF RALEIGH |
|
Solicitation Number
*
274-PR-2026FRPMBT-DBR
|
Department
CITY OF RALEIGH
|
Status Reason
Open
|
|
|
Opening Date
2026-10-15T15:00:00.0000000
|
Posted Date
*
2026-09-24T19:42:19.0000000Z
|
Primary Commodity Code
Construction Services
|
|
|
Mandatory Conference/Site Visit
—
—
|
Special Instructions
Thomas Dawson, RLA, AICP Capital Projects Manager Email: Thomas.Dawson@raleighnc.gov
|
Solicitation Type
*
RFP
|
|
|
Owner
Nikolai Merza
|
|||
|
Description
Pursuant to NC General Statutes § 143-128.1A, the City of Raleigh is seeking one or more qualified design-build (DB) teams to provide design and construction services for the natural surface mountain bike trails at Forest Ridge Park.
|
|||
Exhibit B
Scope of Services
Forest Ridge Mountain Biking Trail
The City of Raleigh is seeking a design-build team with proven experience in development
of single-track trails which incorporate natural and built features. The trails will
accommodate a variety of riding styles, maximize ride conditions, and minimize need for
maintenance and environmental impacts. Services include design and field layout of
planned routes, survey, engineering, cost estimating, permitting at City, State and Federal
levels, and construction of trail, special features, backcountry bridges, and boardwalks.
The team will be expected to coordinate and comply regulatory constraints set by State
and Federal Agencies as appropriate including the land-owners, NC Department of
Natural and Cultural Resources, the US Army Corp of Engineers and land managers,
Raleigh Parks. Professional Trail Builders Association membership preferred.
Design-Builder Phase I milestones will include 30%, 60%, 90% permit approvals, and
final design. There shall be PRCR staff approval of the field layout of trail routes and
proposed locations and design for special features, bridges and boardwalks. Design
build scope will include cost estimation and budget reconciliation at every design
milestone, permit submission and permit approval.
This project is to be completed no later than Spring 2028 to meet the NC Department of
Natural and Cultural Resources Great Trails State Program grant deadlines.
All proposers should be familiar with the Forest Ridge Bike Trails Extension Design
Report (2023) found in Appendix V.
The Design-Builder's services for the Project will be engaged in a two-phase process,
one phase being pre-construction and the other being construction. The Design-Builder
shall perform the Phase 1 Services of design, pricing, and other services for the Project.
Design documents shall include all drawings and specifications needed to permit and
perform the work including and not limited to the following disciplines:
Civil/site
Environmental assessment
Cost Estimating
Structural, as needed for topographical crossings
Survey
Site Management, safety logistics, phasing and other construction related matters.
Design-Builder's Phase 2 Services shall consist of the completion of design services,
including permitting, for the Project; the procurement of all materials and/or equipment for
the Project; the performance of all site preparation and construction for the Project.
Permitting, Coordination, and Public Safety
The selected firm shall obtain all required permits, provide all required notifications, and
coordinate with regulatory agencies having jurisdiction. All work shall be properly
sequenced to support the overall project schedule while maintaining continuous site
safety, environmental protection and public safety. This requirement is of paramount
importance as the park will remain open and accessible to the public throughout the
duration of the work.

With GovernmentContracts, you can:
...RFQ Hay Street Parking Deck Elevator Design Build Reference number: COF1516867.2 Closing date... ...
City of Fayetteville
Bid Due: 11/24/2026
...Follow Design-Bid-Build (DBB) SOF Marine Raider Facilities Complex, Marine Corps Base (MCB) Camp... ...
DEPT OF DEFENSE
Bid Due: 10/20/2026
...Student Union - Solar Array Expansion This solicitation is for Design-Build Opening Date: ...
State Government of North Carolina
Bid Due: 11/03/2026
...is soliciting statements of Qualifications from design- build firms for the provision of ...
Hope Mills town
Bid Due: 11/03/2026