CITY OF SALEM, MISSOURI
REQUEST FOR BIDS
Title:
Date Issued:
Due Date and Time:
Submit Sealed Bid To:
Control Panel Improvements
February 20, 2026
March 4, 2026; 3:00 PM
City of Salem, Missouri
Office of City Clerk
400 N. Iron Street
Salem, MO 65560
INTRODUCTION
The city of Salem is soliciting bids from qualified contractors to replace Digester Aerator 1 & 2 Control Panel
Improvements and elevating New Panels 6 Feet on Platform..
Any questions regarding this request should be addressed to Josh Hunt, wwtp@salemmo.com, 573-247-9249.
Please check our website at https://www.salemmo.com/city/government/bids/index.php for the latest updates to this
packet prior to submitting your bid.
BACKGROUND INFORMATION
The City of Salem, Missouri, is in the middle of the Missouri Ozarks. The 2021 US Census, American Community
Survey estimates approximately 4,623 residents. The City of Salem, Missouri, is a fourth-class city and operates
under a Mayor/Board of Aldermen/City Administrator form of government, providing a wide variety of public
services, including police, parks and recreation, a municipal airport, street maintenance, electric, water and
wastewater treatment services.
SPECIFICATIONS
Contractor shall furnish all materials, supplies, equipment, and labor to complete the installation:
Project: Digester aerator 1 & 2 control panel improvements in elevating new panels 6 Feet on platform
• Build appropriate elevated deck with stairs and handrailing to safely access the elevated electric panels
utilizing treated lumber and pier blocks or a concrete pad
(Quantity 2) Simplex panel for (1) 25HP, 34FLA, 460VAC, 3-Phase, 60Hz motor
NEMA 4X 304SS, live front, wall mount enclosure with 3-point padlockable latch panel to include:
Main non-fused disconnect with padlockable handle on door
TVSS
Condensation heater with adjustable thermostat
Pump circuit breaker
IEC starter with adjustable overload
Fused control power transformers
Off-On switch
Run pilot light
Dry contact: Running
Red strobe alarm light and horn with silence switch activated on pump overload
Terminal blocks for field control connections
AutoCAD drawings and electronic submittals
Labor, Mileage, and Materials for Service Technicians to:
Deenergize Power and LOTO for Safety
Removal of Existing Control Panel
Run New Conduit and Wiring to New Location (estimated 220 foot run/contractor will need to verify
distance for quote)
Cable Entry into New Panel to be Side Mounted
Mount and Install New Control Panel
Reconnect Power and Pump Cable
Test System to Ensure Proper Operation
Documentation and end user training as required
Project needs to be finished by 30 June 2026, if not then an estimated timeline to finish must be added
to the bid packet for consideration (FEMA may provide an extension)
*Warranty of one year required
The City reserves the right to reject any or all quotes submitted, waive any informalities or irregularities in the
quotes received, and to accept any quote which, in the opinion of the City, is in the best interest of the City.
Project: Main breaker panel improvements in elevating new panels 6 Feet onto platform
Build platform 6 feet tall in shop to access these controls to be mounted on wall 6 feet up to be accessible
safely from platform
(1) I-Line MB panel (INTERIOR)-I-Line panelboard
Panel consisting of:
240/120V 3Ph 4W 60Hz SCCR: 65kA
Single main: 600AS/600AT/3P LG circuit
Breaker 80% rated
Main trip function: LSI
Main trip unit: Standard trip unit
Incoming conductors: 1 - (2) 2/0 - 500 kcmil
AL ground bar
Bus: 600A Rated copper: Tin plated
Type 1,Box: 73H x 32W x 9.5D
Incoming: Top trim: Four-piece surface
2 - 250A/3P JG | 1 - 80A/3P BG | 4 - 20A/3P BG | 1 - 45A/3P BG
1 - HC3273DB9-PNLBD ENCLOSURE I-LINE 32W 73H 9D
1 - HCM73TS-PANELBOARD COVER/TRIM ILINE 4PC
Service Technicians to:
Deenergize power and LOTO for safety
Removal of existing panel
Run new conduit and feeder wires to new location Approximately 160 feet to leachate pump station
and approximately 250 feet to #1 clarifier
Mount and install new panel
Reconnect power and cables
Test system to ensure proper operation
Documentation and end user training as required
Project needs to be finished by 30 June 2026, if not then an estimated timeline to finish must be added
to the bid packet for consideration (FEMA may provide an extension)
*Warranty of one year required
Project: North Sludge Tank Control Panel Improvements in Elevating New Panels 6 Feet on Platform
(1) Simplex Panel for (1) 10HP, 28FLA, 230VAC, 3-Phase, 60Hz motor
NEMA 4X 304SS, live front, wall mount enclosure with 3-point padlockable latch
Panel to Include:
Main non-fused disconnect with padlockable handle on door
TVSS
Condensation heater with adjustable thermostat
Fused control power transformer
IEC starter with adjustable overload
Fused control power transformer
Off-On switch
Run pilot light
PMR-1 seal/thermal monitoring relay mounted on back panel
Reset pushbutton
Dry contact: Running
Red strobe alarm light and horn with silence switch activated on pump overload
Terminal blocks for field control connections
AutoCAD drawings and electronic submittals
(1) Materials for elevating new panel 6 feet on platform
• Build appropriate elevated deck with stairs and handrailing to safely access the elevated electric panels
utilizing treated lumber and pier blocks or a concrete pad
New location with leachate, digester aerator and South sludge tank panels
Service Technicians to:
Deenergize power and LOTO for safety
Removal of existing control panel
Run new conduit/wiring to new location approximately 80 feet to sludge pump panels
Cable entry into new panel to be side mounted
Mount and install new control panel
Reconnect power and pump cable
Test system to ensure proper operation
Documentation and end user training as required
•Project needs to be finished by 30 June 2026, if not then an estimated timeline to finish must be added to the bid
packet for consideration (FEMA may provide an extension)
*Warranty of one year required
The City reserves the right to reject any or all quotes submitted, waive any informalities or irregularities in the
quotes received, and to accept any quote which, in the opinion of the City, is in the best interest of the City.
Project: South sludge tank control panel improvements in elevating new panels 6 feet on platform
(1) Simplex Panel for (1) 10HP, 28FLA, 230VAC, 3-Phase, 60Hz motor
NEMA 4X 304SS, Live Front, Wall Mount Enclosure with 3-point padlockable latch
Panel to Include:
Main non-fused disconnect with padlockable handle on door
TVSS
Condensation heater with adjustable thermostat
Fused control power transformer
IEC starter with adjustable overload
Fused control power transformer
Off-On switch
Run pilot light
PMR-1 seal/thermal monitoring relay mounted on backpanel
Reset pushbutton
Dry contact: Running
Red strobe alarm light and horn with silence switch activated on pump overload
Terminal blocks for field control connections
AutoCAD drawings and electronic submittals
(1) Materials for elevating new panel 6 feet on platform
New location with leachate, digester aerator and south sludge tank panels
(1) Labor, mileage, and materials for service technicians to:
Deenergize power and LOTO for safety
Removal of existing control panel
Run new conduit and wiring to new location Approximately 80 feet to sludge pump panels
Cable entry into new panel to be side mounted
Mount and install new control panel
Reconnect power and pump cable
Test system to ensure proper operation
Documentation and end user training as required
•Project needs to be finished by 30 June 2026, if not then an estimated timeline to finish must be added to the bid
packet for consideration (FEMA may provide an extension)
*Warranty of one year required
The City reserves the right to reject any or all quotes submitted, waive any informalities or irregularities in the
quotes received, and to accept any quote which, in the opinion of the City, is in the best interest of the City.
SCHEDULE
Every effort will be made to adhere to the following schedule regarding this proposal, although it may be altered at
the City’s convenience.
Release of advertisements of RFB
Deadline for questions
Proposal submission deadline
Bid Opening @ City Hall
202 N. Washington St., Salem, MO 65560
Final Selection & Board Approval
February 20, 2026
February 27, 2026
March 4, 2026 @ 3 PM
March 4, 2026 @ 3:15 PM
March 10, 2026
BID SUBMISSION AND AWARD
Submission
All proposals must be received by the City Clerk, City of Salem, Missouri, 400 N Iron Street, Salem, Missouri 65560
prior to 3:00 p.m., Central Standard Time, on March 4, 2026.
Bid opening will be at 3:15 pm on March 4, 2026 at the City Hall Council Chambers, 202 N. Washington St., Salem,
MO. NOTE** Two different addresses for submittal and bid opening.
Bids shall be submitted on the forms provided and must be manually signed by the individual authorized to
legally bind the company. Additional documentation may be submitted with the Bid form.
Bids shall be submitted in a sealed envelope that is clearly marked Digester Aerator 1 Control Panel
Improvementson the outside of the mailing envelope.
Bids received after the opening date and time will be rejected.
FAXED/EMAILED BIDS WILL NOT BE ACCEPTED.
Cost of Proposal:
1. Provide the price that your company will charge the City for providing services as outlined in the
Specifications.
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Plant; including overhead lighting, conduit & conductors, filter control panels, valve actuators...

Drexel Technologies

Bid Due: 7/06/2026

...Plant; including overhead lighting, conduit & conductors, filter control panels, valve actuators...

Drexel Technologies

Bid Due: 7/06/2026

...Plant; including overhead lighting, conduit & conductors, filter control panels, valve actuators...

Drexel Technologies

Bid Due: 7/06/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.