SO-1860 Hill EV Elec Infrastructure Addendum 1

Location: Michigan
Posted: May 28, 2026
Due: Jun 4, 2026
Agency: Lansing School District
Type of Government: State & Local
Category:
  • D - Automatic Data Processing and Telecommunication Services
Publication URL: To access bid details, please log in.
SO-1860 Hill EV Elec Infrastructure Addendum 1

Attachment Preview

PRE-BID ADDENDUM NO. 1
TO SPECIFICATION 28172.00
OWNER:
Lansing Public School District
519 West Kalamazoo Street
Lansing, Michigan 48911
PROJECT:
Electric Vehicle Charger and Battery Storage Integration
with Hill Center Resiliency Project #SO-1860
CONTRACT FOR: Construction
ENGINEER:
CTC Engineering, LLC
3915 Research Park Dr., Ste. A-8
Ann Arbor, Michigan 48108
INTENT:
The following is intended to be a clarification to the Contract Documents
based upon the questions offered as a result of the Pre-Bid Walk Through
on May 20, 2026.
DRAWINGS:
The submittals for the EV Chargers are attached herewith for reference only.
The following drawings accompany this Addendum:
Sheet 28172.00, E-2
Sheet 28172.00, E-2.1
Sheet 28172.00, E-5
PROJECT MANUAL: -No sections are reissued with this Addendum-
CLARIFICATIONS:
A. Note that the bid proposals can be hand delivered, or mailed, and must be received no later
than 2:00 pm, June 4, 2026 at: Lansing School District, Attn: Purchasing/Sealed Bid SO-
1860, 519 W. Kalamazoo St, Lansing, Michigan 48933.
B. Attached is the bidders list of those Contractors that attended the pre-bid walk through held
on May 20, 2026.
C. The following questions and associated clarifications are made part of and binding to the
Contract documents:
1. Are the EV chargers part of this Contract?
Response: The acquisition of the EV chargers is not under this Contract, as they have
already been purchased by the Owner. The installation of the chargers is under this
Contract and shall be assigned to the Contractor at the site.
2. Will there be for construction drawing issued for bidding or are we to bid from the
drawings labeled “preliminary – Not to be used for construction”?
Response: You are to bid from the documents issued as part of this package. The “For
Construction” documents will be issued at the time of award.
3. Will yellow Ideal plastic bollard protection sleeves be allowed in lieu of painting the
bollards?
Response: Yes.
4. Where are TR-1 and Panel GA-1 located?
Response: Sheet E-2 shows the overall equipment locations. Please see Sheet 28172.00
E-2.1 for more specific locations.
5. Please provide specs or a submittal of the owner provided bus EV chargers.
Response: Please see the attached submittals for the EV Chargers.
6. Who is responsible for final installation and startup of the Bus EV chargers?
Response: The final installation is under this Contract but the startup will be performed
by others.
7. Do the EV chargers require a data connection?
Response: Yes.
8. Is the fencing included in this project? The civil drawings show it as by others, but
the electrical drawings have details on how to install it. Are there further details on
the fencing? Fabric type? Post thickness? Gate dimensions?
Response: The fencing is part of this project in its entirety. In the Project Manual, please
see section #32 3100, for the specific specifications for the fencing and operators.
9. Who is responsible for the gate operator? If contractor, please provide specs on it.
Response: In the Project Manual, please see section #32 3100.
10. Will the gate operators require a traffic loop for exit?
Response: In the Project Manual, please see section #32 3100, page 3.
11. What will open the gate operators?
Response: In the Project Manual, please see section #32 3100, page 3.
12. Will there be civil specs provided for this project? The only specs are electrical.
Response: Civil specifications are provided on the civil sheets.
13. Is civil testing part of this project? Who is responsible for paying the cost of civil
testing?
Response: Civil testing is by a third party, obtained and paid for by the Owner.
14. What is expected for pavement markings or are these by others?
Response: Pavement markings are under this contract and shall conform to MDOT
specifications.
15. Please provide a base detail for the bus EV chargers.
Response: The base detail is shown in the submittals herewith. The base plate of the
charger is to be bolted in place direct to the concrete.
16. Please provide a more detailed/larger plan for the bus charger arrangement showing
the bollard spacing and bus EV charger layout
17. Response: Please see Sheet 28172, E-2.1 for an enlarged view of this area.
18. Please clarify how the tap in the existing switch is to be made and where this
equipment is on the plans. Can plans be provided indicating what and where each
piece of equipment is?
Response: These have been provided and are attached.
19. How long do you anticipate the Note #3 (sheet E-1) to be? It appears the tap length
may dictate overcurrent protection is needed for the tap conductors prior to reaching
the location shown for the 600A ATS.
Response: The is using the tap rule as indicated in Section 240.21 (B)(5) of the National
Electrical Code. The over-current protection in the ATS would be the required device
as identified in Section 240.21 (B)(5)(3).
20. The drawings indicate the solar array will not operate during a utility outage,
however it appears if you are back feeding the school switchboard from the
buses/BESS then the array will in fact see power at the tap and start pushing power
back to the system. No electronics are indicated to be added to the existing solar
switch to accept a signal from the SEL-751 to open it if there is a utility loss and the
buses/BESS are sent to a back feed scenario.
Response: The control of the solar array invertors, automatic transfer switches, EV
chargers and the future BESS is not under this Contract. The control conductors and
the termination thereof are however, under this Contract. The point-to-point
terminations will be issued after all submittals have been made.
21. Can you indicate where on the drawings the “Existing switch” below (left side) is located
that the 600 Amp tap will be made?
a. Does this tap need overcurrent protection?
Response: Please see response to [22] below.
22. Can the 600 Amp tap be completed anywhere in the existing main switchboard sections?
Does this tap need to be designed by Eaton or be UL field listed?
Response: It is anticipated that the tap at the existing switch would
be made at the load side of the switch with additional lugs with
respect to the existing switch feeding the existing solar panels. With
respect to the existing indoor distribution panel, it is anticipated that
a direct connection can be made to the low voltage bus, and then
by the tap rule, fed to the ATS.
23. Please clarify what is wanted for mesh reinforcement in the heavy duty concrete? We
assume this means W6x6 W2.9 but are unclear on what the SV stands for.
Response: The SV notation stands for
“smooth wire with deformed wire”, with the
W2.9 referring to the wire size.
- END OF PRE-BID ADDENDEM #1 -
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Follow U.S. Army Contracting Command - Detroit Arsenal (ACC-DTA) Strategic Services Branch Commercial

DEPT OF DEFENSE

Bid Due: 6/30/2030

Description: Prisoner Store and Friends and Family Care Packages Department: Technology, Management and

State of Michigan

Bid Due: 6/15/2026

due date & time bid description bid # primary contact status June 8,

City of Ann Arbor

Bid Due: 6/08/2026

Follow Z1DA--Copy of Upgrade TV System IFB 553-22-209 - Amendment 002 Active Contract

VETERANS AFFAIRS, DEPARTMENT OF

Bid Due: 6/11/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.