| Location: | Florida |
|---|---|
| Posted: | Jul 17, 2026 |
| Due: | Jul 29, 2026 |
| Agency: | City of Panama City |
| Type of Government: | State & Local |
| Category: |
|
| Solicitation No: | PC26-014 |
| Publication URL: | To access bid details, please log in. |
| Bid Number: |
PC26-014
|
| Bid Title: |
Project Storm Group I
|
| Category: | Construction Services |
| Status: | Open |
|
Dedicated to Excellence . . .
People Serving People
Purchasing Division * 501 Harrison Avenue, Room 238, Panama City, 32401 Phone 850-691-4902 * panamacity.gov
ADDENDUM No. 2
PC26-014 Project Storm Group I
July 17, 2026
The purpose of this addendum is for the City of Panama City ("City") to provide updated
information to the Invitation to Bid Number PC26-014 ~ Project Storm Group I
and shall it become part of the Contract Documents.
Addendum 2 provides a Bid Due Date Extension and Clarifications to the Contract
Documents, and they are amended in the following particulars:
I. BID DUE DATE EXTENSION
A. The Bid Due Date is hereby extended to July 29, 2026, at 10:00 AM CT.
II. SPECIFICATIONS (NOT APPLICABLE)
III. PLANS / DRAWINGS (NOT APPLICABLE)
IV. CLARIFICATIONS
A. Additional Information
1. Under Section 02578 Lift Station Bypass Pump, 2.01, Mersino pumps are
accepted as an equal for this project. Fuel capacity, and other metrics shall
be maintained throughout the specifications. Priming and engine
characteristics may be varied.
B. The following RFIs were received:
1. RFI: Regarding Lift Station 15, and as Sheet No. LS15.1 is N.T.S. please
confirm the overall length (PE to face of flange) of the 3" SS PE x FLG
suction riser.
RESPONSE: The length of the suction riser shall be approximately 8.5'.
PC26-014 Addendum 2 Page 1 of 4
2. RFI: Regarding Lift Station 15, Sheet No. LS15.1, please confirm (a) the
overall length (face of flange to face of flange) of the 2" Flg x Flg spool piece
to be installed from the new 2" SS tee at the existing 2" effluent line through
the cored hole in the existing concrete lift station top to the point of connection
of the new 2" DI x 90 bend. Also, (b) is this spool piece SS or DI?
RESPONSE: The spool piece shall be approximately 4' Stainless Steel.
Responsibility of the Contractor to field verify spool length. The suction piping
shall be elevated approximately 10" above the station concrete slab.
3. RFI: Per Section 09900, Painting, 2.06 IMMERSION COATING SCHEDULE
- WASTEWATER TREATMENT PLANTS, Section B. Ductile Iron pipe,
Submerged (Wastewater). In that the majority (if not all) ductile iron pipe is
not "submerged" in wastewater but buried and/or above ground what is the
required paint product and color for the ductile iron/above ground pipe
associated with this project?
RESPONSE: Per the project documents and City standards, the coating
manufacturer shall be Tnemec. The product and color selection is the
responsibility of the Contractor. Please reference 09900 Painting, 2.01 and
2.03 for more information.
4. RFI: Per City of PC Detail PS-4B, please confirm which pipe support (1 or 2)
is to be used for this Project. Please confirm.
RESPONSE: Both pipe supports will be required throughout the project and
may be used interchangeably.
5. RFI: Will the City of PC and/or EOR accept/allow BBA by-pass pumps as an
equal to Godwin by-pass pumps for this project? It is understood the City of
PC has one (1) existing BBA by-pass pump in use/operation for more than
one (1) year. Please confirm.
RESPONSE: BBA pumps are accepted as an equal for this project. Fuel
capacity, and other metrics shall be maintained throughout the specifications.
Priming and engine characteristics may be varied.
6. RFI: Simply to ensure the correct new base elbows are provided for lift
stations LS 50, LS 51, LS 66, LS 85, LS 86, LS 93, and LS 114, it is
understood the existing pumps in these specific lift stations are manufactured
by Wilo. That being the case please confirm the make and model number of
base elbow(s) to be provided for these seven (7) respective lift
stations. Please confirm.
RESPONSE: A Standard 4" Base Elbow with 2 pipes shall be the basis of bid.
PC26-014 Addendum 2 Page 2 of 4
| Station # | Depth (ft) | Diameter (ft) |
|---|---|---|
| 15 | 8 | 4 |
| 40 | 6 | 6x11 |
| 50 | 21 | 7 |
| 51 | 21 | 9 |
| 66 | 17 | 6 |
| 73 | 10 | 6 |
| 81 | 21 | 16x18 |
| 85 | 14 | 6 |
| 86 | 19 | 6 |
| 90 | 6 | 6x11 |
| 93 | 15 | 6 |
| 114 | 16 | 6 |
| 200 | 5 | 4 |
| 203 | 12 | 4 |
7. RFI: Per City of PC Plan Sheets CD3.0, CD3.1, CD3.2, and CD3.3, please
confirm the make, model, fuel type, etc.. for each STYLE PUMP specified.
RESPONSE: Sheets CD3.0, CD3.1, CD3.2, and CD3.3 contain general
structural information for the bypass pump pads based on a general size of a
pump. The sheets do not represent a specific bypass pump make and model.
8. RFI: Most of the drawings associated with this project are NTS, please
confirm the depths and diameters of the wet wells associated with lift stations
50, 51, 66, 73, 81, 86, 90, 93, 114, 200 & 203.
RESPONSE: The depths and diameters of the wetwells are as follows:
Station # Depth (ft) Diameter (ft)
15 8 4
40 6 6x11
50 21 7
51 21 9
66 17 6
73 10 6
81 21 16x18
85 14 6
86 19 6
90 6 6x11
93 15 6
114 16 6
200 5 4
203 12 4
9. RFI: Per the Summary of Work, Addendum #1, Lift Station 93 calls for
geofabric and #57 stone. Please confirm the required thickness of the #57
stone and the square yardage of geofabric. Regarding the geofabric please
confirm the required material (i.e. manufacturer, type, etc.)
RESPONSE: The thickness of the #57 stone shall be 4" as referenced on
sheet LS93.3 of the project plans. The area of the #57 stone shall be 640
square feet or approximately 71 square yards as referenced on sheet LS93.3
of the project plans. Geofabric shall be a weed barrier per the project
specifications.
PC26-014 Addendum 2 Page 3 of 4
10. RFI: The bid form states that all iron and steel is to comply with AIS
requirements while attachment 1 in addendum 1 #12 states that AIS will not
be enforced. Can you clarify if AIS requirements will be enforced on this
project?
RESPONSE: American Iron and Steel (AIS) requirements ARE NOT enforced
on this project.
11. RFI: Confirm which diesel pumps at which lift stations the COPC will be
supplying and which pumps at which stations need to be included in the
contractors bid?
RESPONSE: The City will be supplying a GODWIN Model CD100S diesel
pump for the Contractor to install at Lift Station #85. The City will be supplying
a GODWIN Model CD80M diesel pump for the Contractor to install at Lift
Station #200. The City will be supplying a GODWIN Model NC80 diesel pump
for the Contractor to install at Lift Station #203. All diesel pumps supplied by
the City will be available for the Contractor to pickup at the City yard located
at 3126 West 19th St. The Contractor is required to supply a mounted bypass
pump at Lift Station #81 based on requirements set forth in the project bid
documents.
END OF ADDENDUM No. 2
Bidders must acknowledge receipt of Addenda in accordance with C-200 Instructions to
Bidders and C-410 Bid Form.
For RFIs regarding this Addendum, please email the City of Panama City's Purchasing
Division at purchasing@panamacity.gov.
PC26-014 Addendum 2 Page 4 of 4

With GovernmentContracts, you can:
...The Department of Juvenile Justice is requesting RFSQ/RFQ for Continuing Construction Management... Codes ...
State Government of Florida
Bid Due: 10/06/2026
...Ryan Title CONSTRUCTION MANAGEMENT AT RISK MANATEE ELEMENTARY CAMPUS WIDE HVAC RENOVATION, SDMC ...
Manatee County School District
Bid Due: 10/01/2026
...to provide Construction Management services for the North Cape Government Complex - Fleet ...
Florida Department of State
Bid Due: 9/10/2026
...Description: PROFESSIONAL EMERGENCY MANAGEMENT CONSULTING SERVICES Department: Facilities Dev &... for Prequalifications (RPQ) ...
Palm Beach County
Bid Due: 3/30/2029