Pre-Solicitation Notification for upcoming Request for Proposals for a Construction Manager-At Risk project delivery.

Location: Texas
Posted: Dec 13, 2025
Due: Feb 19, 2026
Agency: Texas Parks and Wildlife Department
Type of Government: State & Local
Category:
  • U - Education and Training Services
  • Y - Construction of Structures and Facilities
Publication URL: To access bid details, please log in.
Due Date: February 19, 2026 2:00 PM
Park Name: Bear Creek State Park, Uvalde County Texas
Project No: 1112553
Description: Pre-Solicitation Notification for upcoming Request for Proposals for a Construction Manager-At Risk project delivery. Solicitation and final due date to be determined.

*****************************************************************

Attachment Preview

NOTICE OF INTENT TO PROCURE
In accordance with Texas Government Code 2262.051 The Infrastructure Division of Texas Parks
and Wildlife Department (TPWD) intends to issue a Request for Proposal for Construction
Manager-at-Risk (CMR).
Project Name
Project Location
Project Number
Centennial Park Development
Bear Creek State Park
1112553
925-44 General Construction Management,
Scheduling, Cost Estimation Engineering
918-31 Construction Consulting
NIGP Class / Item Codes
914-00
914-84
Construction Services, Trades, New
Construction
Trade Services, Construction (Not otherwise
specified
Construction Estimate
$65,000,000 - $75,000,000
This is a pre-solicitation notice for the Construction Manager at Risk (CMR) solicitation, to be
advertised in January 2026. This notice is not a request for proposal or qualifications submission.
General Scope of Work
Project No. 1112553 titled “Centennial Park Developmentis being solicited to develop a newly
acquired 1,720.77-acre ranch tract in Uvalde County for a new Texas State Park. The acquired
property is situated ten miles southeast of existing Garner State Park at Latitude 29°33’19.21”N;
Longitude 99°40’59.79”W.
TPWD plans for the fully constructed park to include but not be limited to:
Park entry and monument signage
Electrical access gate(s)
Paved Roadways
Gravel Roadways
Parkwide directional signage
Operational Facilities to include Park Headquarters, staff residences, park host sites,
maintenance yard and supporting buildings
Day Use Facilities to include trailheads, multi-use trails, picnic areas, group pavilion(s),
amphitheater, Nature Center, playground, wildlife viewing areas, restrooms and associated
parking areas
Overnight Facilities to include developed and primitive camping areas, mini-cabins, screened
shelters, restrooms and associated parking areas
Site utilities including a public water system, wastewater treatment facilities, electrical
infrastructure, telecommunications infrastructure, radio tower and associated infrastructure
Notice of Intent to Procure 2023_0818
Page 1 of 3
Bear Creek State Park
New Park Development
Sustainable systems
Site demolition
Historic structures renovation / reuse
Project No. 1112553
Construction Manager-at-Risk Deliverables
PRE-CONSTRUCTION SERVICES associated with CONSTRUCTION PACKAGE 1 (Early Work
Package): The project calendar allows a limited period for Pre-Construction Services associated
Construction Package 1; the Early Work Package. At the time of anticipated CMR contract award,
Construction Documents are expected to be developed to the stage of 75% completion. However,
the Contractor shall collaborate with TPWD and its Architects and Engineers to review and comment
on the Construction Documents, provide guidance on constructability, value engineering,
construction phasing and schedule optimization. The services during Pre-Construction shall include
attending meetings, plan reviews, constructability reviews and cost estimating.
TPWD plans for the Pre-Construction effort for Construction Package 1 (Early Work Package) to
begin mid-June 2026 and conclude at the end of July 2026.
CONSTRUCTION PACKAGE 1; the EARLY WORK PACKAGE
Following the limited Pre-Construction Services phase for Construction Package 1, the Contractor
will receive completed construction drawings and specifications for Construction Package 1; the
Early Work Package. The Contractor shall facilitate bidding and selection of labor in accordance with
state requirements for good faith effort to engage Historically Underutilized Businesses and provide
a complete price for the construction of the work that includes any construction management and
general conditions fees.
The components of Package 1 are minimal facilities needed for initial public day use and operational
supports at the site. These include but are not limited to:
Demolish existing fencing, gates, and small structures
New entry drive and turnaround with electric automatic gate
Entry and wayfinding signage
New fencing
Trailhead and parking for up to 50 vehicles
Vault toilet (2 single use toilets with storage)
Accessible trail loop
Picnic sites
Refurbishing existing two-track roads (2 miles) for natural surface trails
Revegetation and landscaping
TPWD expects to award costs of work by September 2026 and estimates an approximate 180-day
performance period, resulting in the Park opening for initial public use in February 2027.
PHASE 2 PRE-CONSTRUCTION:
The awarded Contractor shall collaborate with TPWD and its Architects and Engineers during the
completion of construction documents, including review and comment exercises on Schematic
Design; 50% and 100% Design Development; and 50%, 95% and 100% Construction Documents.
The Contractor’s expertise will be used to guide value engineering, constructability decisions,
construction phasing, and ultimately set the Guaranteed Maximum Price (GMP) within the limits
established by the contract. The services during Pre-Construction shall include attending meetings,
plan reviews, constructability reviews and cost estimating. TPWD plans for the Pre-Construction
effort to begin no later than September 2026.
Notice to Bidders (2022_0215)
Bear Creek State Park
New Park Development
Project No. 1112553
PHASE 2 CONSTRUCTION:
In accordance with the approved schedule and GMP, the Contractor shall facilitate bidding and
selection of labor in accordance with state requirements for good faith effort to engage Historically
Underutilized Businesses. The Contractor shall provide for all materials, installations, labor,
coordination, management and supervisory activities necessary to complete construction of the
project in accordance with the drawings, specifications and other contract documents that will be
prepared by the Architect, Engineers and TPWD. TPWD plans for Phase 2 construction to conclude
by August 2029 to allow for the opening of the full Park in September 2029.
Detailed information about the requirements and selection process will be provided in the
solicitation documents.
Upon issuance of the solicitation, information will be available electronically on Texas’ Electronic
State Business Daily.
Notice to Bidders (2022_0215)
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Bid Number: RFP #2026-0018-181 Bid Title: RFP - Traffic Signal Construction Category: RFP/RFQ...

Cedar Park

Bid Due: 6/26/2026

...Bid Number Bid Title Bid Type Organization Bid Issue Date Bid Close Date ...

City of College Station

Bid Due: 7/09/2026

...Bid Number Bid Title Bid Type Organization Bid Issue Date Bid Close Date ...

County of Brazos

Bid Due: 7/09/2026

...General Construction at Lubbock SSLC Solicitation ID: HHS0017375 Due Date: 6/26/2026 Due Time: ...

State Government of Texas

Bid Due: 6/26/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.