F--OR - Klamath Marsh NWR -FUEL REDUCTION Site A
Active
Contract Opportunity
Department/Ind. Agency
INTERIOR, DEPARTMENT OF THE
Sub-tier
US FISH AND WILDLIFE SERVICE
Office
FWS, OVER SAT G/S
Looking for contract opportunity help?
General Information View Changes
-
Contract Opportunity Type: Combined Synopsis/Solicitation (Updated)
-
Updated Published Date: Aug 25, 2026 01:00 pm PDT
-
Original Published Date: Aug 17, 2026 02:32 pm PDT
-
Updated Date Offers Due: Aug 27, 2026 10:00 am PDT
-
Original Date Offers Due: Aug 26, 2026 07:00 am PDT
-
Inactive Policy: 15 days after date offers due
-
Updated Inactive Date: Sep 11, 2026
-
Original Inactive Date:
Sep 10, 2026
-
Initiative:
Classification
-
Original Set Aside: Total Small Business Set-Aside (FAR 19.5)
-
-
Product Service Code: F099 - NATURAL RESOURCES/CONSERVATION- OTHER
-
NAICS Code:
-
238910 - Site Preparation Contractors
-
Place of Performance:
Description View Changes
Klamath Marsh NWR, OR - Hazardous Fuels Reduction and Habitat Enhancement - Site A
It is highly recommended that the Contractor visit the site prior to quoting.
See SOW attached.
Vendor will submit a statement that the vendor understands the work and understands the environment and condition the work will be performed in and fill out the quote sheet on the first page of the attachment.
Send packets and questions to Robert_Sung@ios.doi.gov with "140F0S26Q0057 - Klamath Marsh - A" in the subject line
RFI questions:
Q1. Please confirm that we only need to cut brush if it is acting as a ladder fuel.
A1. Yes, only cutting brush that acts as a ladder fuel
Q2. Is there a certain distance from the drip line that the brush should be cut?
A2. There isn¿t a definitive spacing, part of this is a case by case basis that depends on items like how tall is the brush? If it were lit on fire would carry up into the crown? Example: a five foot tall brush that is only six inches away from the drip line will need to be cut.
Q3. Please also confirm that dead and down material up to 16" diameter should be piled.
A3. Only dead and down (under 16" diameter) that acts as a ladder fuel needs to be cut/piled.
Attachments/Links
Contact Information
Contracting Office Address
-
FWS, Over SAT G/S 5275 Leesburg Pike
-
Falls Church , VA 22041
-
USA
Secondary Point of Contact
History
Daily notification on new contract opportunities
With GovernmentContracts, you can:
- Find more opportunities and win more business
- Receive daily alerts for all new bid opportunities
- Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
See also
Follow USACE SPK Construction - Natomas PP5, Sacramento, CA Active Contract Opportunity Notice
DEPT OF DEFENSE
Bid Due: 9/01/2026
Follow CIRCUIT CARD ASSEMB Active Contract Opportunity Notice ID N0010426QUC02 Related Notice Department/Ind.
DEPT OF DEFENSE
Bid Due: 9/10/2026
Follow RING,RETAINING Active Contract Opportunity Notice ID N0010426QFG17 Related Notice Department/Ind. Agency DEPT
DEPT OF DEFENSE
Bid Due: 9/08/2026
Follow Calcasieu River and Pass, LA, Maintenance Dredging FY26, Mile 5.0 to Mile
DEPT OF DEFENSE
Bid Due: 9/16/2026
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.