| Location: | North Carolina |
|---|---|
| Posted: | Oct 15, 2026 |
| Due: | Nov 6, 2026 |
| Agency: | City of Monroe |
| Type of Government: | State & Local |
| Category: |
|
| Publication URL: | To access bid details, please log in. |
City of Monroe Goldmine
Substation Relay Panel Replacement
Request for Proposal (RFP)
October 14, 2026
1
| Section | Title | Page |
|---|---|---|
| 1 | Purpose | 3 |
| 2 | City of Monroe | 3 |
| 3 | Goldmine Substation | 3 |
| 4 | Project Scope | 4 |
| A. Removal of old panel | 4 | |
| B. Installation of new panel | 4 | |
| C. Programming of relays | 4 | |
| D. Relay communications | 4 | |
| E. Testing and commissioning | 5 | |
| F. Return to service | 5 | |
| G. Drawings and redlines | 5 | |
| 5 | Project Schedule | 5 |
| 6 | Deliverables | 6 |
| 7 | Questions, Clarifications, and Notifications | 6 |
| 8 | Submittal Requirements | 6 |
| 9 | Selection Process | 7 |
| 10 | Alternative Proposals | 7 |
| 11 | RFP Timeline | 8 |
| 12 | Contact Information | 8 |
| 13 | Appendices | 8 |
| Appendix A - Station Electrical Drawings | ||
| Appendix B - SEL Panel Drawings | ||
| Appendix C - Goldmine T1 Transformer Nameplate | ||
| Appendix D - Proposer Questions Submittal Form | ||
| Appendix E - City of Monroe Sample Contract |
Table of Contents
Section Title Page
1 Purpose 3
2 City of Monroe 3
3 Goldmine Substation 3
4 Project Scope 4
A. Removal of old panel 4
B. Installation of new panel 4
C. Programming of relays 4
D. Relay communications 4
E. Testing and commissioning 5
F. Return to service 5
G. Drawings and redlines 5
5 Project Schedule 5
6 Deliverables 6
7 Questions, Clarifications, and Notifications 6
8 Submittal Requirements 6
9 Selection Process 7
10 Alternative Proposals 7
11 RFP Timeline 8
12 Contact Information 8
13 Appendices 8
Appendix A - Station Electrical Drawings
Appendix B - SEL Panel Drawings
Appendix C - Goldmine T1 Transformer Nameplate
Appendix D - Proposer Questions Submittal Form
Appendix E - City of Monroe Sample Contract
2
Goldmine Relay Panel Replacement Request for Proposal
1. Purpose:
The City of Monroe is seeking proposals for the installation of one (1) new SEL transformer
and buss protection relay panel, the programming of two (2) transformer and buss
protection relay panels, transition of SCADA inputs from the old QEI RTU cabinet to the
transformer relay cabinets, and a complete station drawing update package for the
Goldmine substation located at 600 Dale St., Monroe NC.
2. City of Monroe:
The City of Monroe is the county seat of Union County, North Carolina within the rapidly
growing Charlotte metropolitan area. The Energy Services department is committed to
providing cost-effective, courteous, and customer-oriented operations to continually
enhance the quality of life for citizens of Monroe.
The City of Monroe Energy Services owns and operates an electric system that provides
power to approximately 14,000 customers consisting of residential, small commercial and
industrial customers with up to 17.5 MW electric loads. Monroe's Electric Division maintains
19.5 miles of 100 kV transmission lines, 323 miles of distribution lines and eight substations.
Energy Services owns and operates a fiber communication system for City facility
communications. Monroe has 102 miles of overhead and underground fiber.
3. Goldmine Substation:
Monroe's Goldmine substation is a major distribution point for Monroe, receiving 100 kV power
and serving 3739 customers via two (2) 100/35 kV transformers and one (1) 100/13.2 kV
transformer which feed a total of five (5) feeder breakers. It has a heavy residential load.
Goldmine serves as a 100 kV "Point of Delivery" from Duke Energy, and feeds the city's
transmission loop to our "601 South" and "Airport" substations. Protection for 100 kV
transmission is provided by SEL microprocessor relay panels. The existing transformer and buss
protection relays are older electromechanical units that will be replaced with the new panel
designed and constructed by Schweitzer Engineering Laboratories.
3
4. Project Scope:
A) Removal of old 35kV transformers T1 relay panel
1) Review old drawings.
2) Verify "As-found" wiring.
3) Test existing cables. (Megger, point-to-point, etc.)
4) Confirm de-energized status and place "Lockout-Tag out" (LOTO) devices and tags as
needed.
5) Label cables as they are disconnected. (temporary labels with descriptive info)
6) The firm will remove the old panel from control house. Monroe will dispose of old panel.
B) Installation of new 35kV transformers T1 relay panel
1) All labeling shall be Brady Perma-sleeve or equivalent heat-shrink (tube) type. Labels shall
be left loose (unshrunk) on the wiring. All labeling shall have far and near-end terminal
landing point information to match the drawing package. This will be audited for accuracy.
2) All terminations shall use ring lugs.
3) Intra-panel wiring shall use gray sis wire of appropriate gauge for application.
4) Inputs and outputs from the old QEI RTU cabinet will be moved to the SEL Transformer
panels. IFC drawings for this transition shall be supplied to the Substation Engineering
Manager for review no later than February 22, 2027.
C) Programming of relays/ protection curve development
1) This step shall apply to 35kV transformers T1 and T2.
2) Relay protection curves shall be developed and installed to match the transformer's
damage curves in accordance with IEEE C37.91 and any other applicable standards. The
transformer nameplates are available in the appendices.
3) Transformer damage curve / TCC charts shall be provided to Monroe for review and
approval prior to relay programming.
4) These curves shall coordinate with all other high and low-side protective relays. Buss relay
curves shall be developed to coordinate with transformer and feeder relay settings.
5) Program inputs on SEL relays for SCADA inputs from old QEI RTU.
D) Relay Communications
1) Connect new SEL panel relay to an existing SEL RTAC. Serial cables will be pre-existing
behind the relays and terminated with RJ45 connectors. The vendor shall use RJ45 to
DB9/RS232 converters to make the final serial connection to the relays.
2) All communications shall use the SEL "fast messaging" protocol.
3) Inputs from the old QEI cabinet will be mapped into the DNP table to communicate with
the RTAC.
4) All relay communications shall be commissioned in coordination Monroe's substation
engineer. Commissioning will entail point-to-point verification by ensuring that
communications match relay registers to the SCADA master station.
4
E) Testing and commissioning
1) Relay testing and commissioning.
2) Functional testing and commissioning shall include testing and operation of all equipment
including breakers and circuit switchers in the following zones of protection for T1 and T2:
3) 100 KV Bus Differentials
4) 34.5 kV Transformer Differentials
5) 34.5 kV Bus Differentials
6) 34.5 kV Transformer Overcurrents
7) 13.2 kV Transformer Differentials
F) Return to service
1) During energization, partially - loaded (phase-angle) differential balance test shall be
performed on all differential zones of protection mentioned above.
2) After energization, SCADA communications and point mapping shall be commissioned to
ensure accuracy.
G) Drawings and red-lines
1) The firm shall develop "issued for construction" (IFC) drawings to guide the installation of
the relay panel. These drawings shall be made available to Monroe no Later than February
22, 2027. (One month prior to construction kickoff.)
2) Redlines of any type shall be submitted in an easily legible package suitable for use as
records for the creation an "as-built" drawing set.
3) Submitted redlines will be subject to verification by Monroe prior to incorporation in the
as-built package.
4) A complete and total consolidated station electrical drawing package is within this project's
scope. This drawing package shall include ALL substation equipment, field wiring, junction
cabinets, devices, components, etc. The firm shall use industry standard symbology and
consistent formatting across all drawings.
5) This drawing package shall include .dwg and .pdf drawings, and shall include a "Table of
Contents." Source drawings will include existing drawings included in the appendices and
any redlines developed up to the project's close. The firm shall ensure drawings related to
this project's construction are complete and accurate. Source drawings may be used "as-
published" from the appendices, so long as all cable numbers and landing points are
updated accurately based on this project's scope.
6) Project will not be considered complete without delivery of a complete and total station
electrical drawing package.
5. Project Schedule:
The firm's proposal shall include a project schedule detailing the timeline for each project milestone.
The outage for this work is tentatively scheduled to begin March 22, 2027. Monroe's substation
team's normal hours are Monday-Thursday 6:30 am - 5:00 pm. After first-day safety and site
introduction meetings occur, the contractor will be allowed to work uninterrupted unless safety or
quality concerns arise. The contractor will supply a padlock to be inserted in series with Monroe's
on a gate chain. Monroe will observe the Good Friday holiday March 26, 2027, and Memorial Day
on May 31, 2027.
5
6. Deliverables:
1. A full issued for construction (IFC) drawing package.
2. Project progress reports, to be delivered at weekly intervals at a minimum.
3. All relay test records, to be presented in .pdf and excel formats.
4. All relay settings, to be presented in .pdf and SEL's .rdb database format.
5. Copies of all redlines to original drawings.
6. A complete and total "as-built" consolidated station electrical drawing package. The drawing
package shall include a "Table of Contents" with descriptive titles for each drawing, and
drawings shall be made available in .dwg and .pdf formats.
7. Questions, Clarifications, Notifications, and Site Preview Availability:
Interested firms may notify the City of Monroe Energy Services by email to scureton@monroenc.org
due by 10/14/2026. For access to the appendices, a signed copy of the non-disclosure agreement
(NDA) MUST be emailed to scureton@monroenc.org by 10/19/2026. The NDA must be signed by an
authorized company official, with a clearly legible printed name and company title. The firm's name
shall be written-in on the blank line noted as "Recipient" on page one of the document.
Questions and clarifications are to be submitted via email to scureton@monroenc.org by
10/26/2026. These questions shall be listed in the workbook as provided in Appendix D - Proposer
Questions Submittal Form. The City of Monroe will respond via email on 10/29/2026. The
responses to questions and clarifications will be sent to all interested responders to the RFP.
Interested firms who have signed the NDA shall visit the project site before submitting bids.
Vendors will be allowed to photo-document any part of the work site for estimation purposes. Firms
are also encouraged to inspect the SEL panels at our office located at 2201 Walkup Ave. Monroe, NC
28110.
8. Submittal Requirements
Proposals shall be marked "City of Monroe Goldmine Substation Relay Panel Replacement". All
proposals must be sealed. Bidders shall mail or hand deliver their proposals no later than 3:00 pm EST
Friday, November 6, 2026 to:
City of Monroe Energy Services
Attn: Scott Cureton, Substation and Transmission Engineering Manager
2201 Walkup Ave.
Monroe, NC 28110
Additionally, an electronic PDF shall also be emailed no later than 3:00 PM EST on 11/6/2026 to Scott
Cureton, City of Monroe Substation and Transmission Manager Engineer at scureton@monroenc.org
Proposals submitted late will not be considered or accepted. The City will not be liable to any
Proposer for any unforeseen circumstances or delivery delays. Each Proposer is fully responsible for
submission of their Proposal. Additional time will not be granted to a single Proposer; however,
additional time may be granted to all Proposers if/when the City determines that circumstances are
6
warranted. A proposal may be deemed non-responsive and disqualified if it does not include all
material information requested.
No request for modification of the Proposal will be considered after the Proposal Deadline.
The City assumes no responsibility or liability for costs incurred by the Proposer prior to the
execution of an agreement. By submitting a Proposal, the Proposer agrees to bear all costs incurred
or related to the preparation, submission, and selection process for the proposal.
Qualifications to be submitted:
This section shall include the firm's name, area(s) of expertise, a brief history of the firm, size, number
of office locations, and business address of the office responsible for the contract. The name, address,
and telephone number of the contact person responsible for their submittal shall be included. In
addition, the following shall be included:
a. General description of firm's history providing relay panel installation, programming, testing,
and commissioning services.
b. List of three (3) references for like-kind projects.
c. Brief biographical summaries for staff members working on the project.
d. Your firm's organizational chart.
e. List of any proposed subcontractors.
f. Any additional information in support of our project and your services.
Proposals shall include the following information:
a. Technical Approach: Description of the firm's technical approach for this panel replacement
process.
b. Work Approach: How many team members will you have on this project at any given time
and what their assigned role(s) would be.
c. Risk assessment and mitigation plan: Please provide your firm's policies and procedures as it
relates to projects of this type, and what measures you take to maintain installation quality
standards and timeline management.
d. Communication plans: How does your firm convey project status, timeline deviation issues,
request for information, etc., internally and with customers?
e. Any observations noted as part of the firm's required site visit.
Pricing of the following:
The following projects segments shall be priced in an itemized fashion:
a. Cost for issued-for-construction drawings.
b. Cost for relay panel installation.
c. Cost for a complete and total consolidated station-drawing package including all
modifications.
d. Cost for all relay commissioning and functional testing to include communications.
e. The firm's standard rate sheet.
9. Selection Process
The City of Monroe will evaluate and select a firm based upon the responses submitted to this request.
The City of Monroe reserves the right to seek additional information. The City of Monroe reserves
7
| Advertise RFP | 10/14/2026 |
|---|---|
| Notice of Firm's Interest, Non-Disclosure Agreement due date | 10/19/2026 |
| Deadline for RFP Questions | 10/26/2026 |
| Send Questions/Answers to Interested Firms | 10/29/2026 |
| Deadline for Submittals | 11/6/2026 |
| Review Proposals and Qualifications/ Select Firm | 11/9/2026 |
| City Council Review/ Approval | 12/8/2026 |
| Award Contract to Selected Firm | 12/15/2026 |
the right to reject any and all proposals and waive any formalities as may be permitted by law. The
award will be made based on the most responsive/responsible offer.
10. Alternative Proposals:
Alternative proposals are acceptable, but must be clearly marked as alternative proposals.
Alternative proposals will only be accepted from firms that submit proposals as requested.
11. RFP Timeline
Advertise RFP 10/14/2026
Notice of Firm's Interest, Non-Disclosure Agreement due date 10/19/2026
Deadline for RFP Questions 10/26/2026
Send Questions/Answers to Interested Firms 10/29/2026
Deadline for Submittals 11/6/2026
Review Proposals and Qualifications/ Select Firm 11/9/2026
City Council Review/ Approval 12/8/2026
Award Contract to Selected Firm 12/15/2026
12. Contact Information:
Scott Cureton
City of Monroe Substation & Transmission Engineering Manager
704-201-2435
scureton@monroenc.org
13. Appendices:
Appendix A: Station Electrical Drawings
Appendix B: SEL Panel Drawings
Appendix C: Goldmine Transformer Nameplate
Appendix D: Proposer Questions Submittal Form
Appendix E: City of Monroe Sample Contract
8

With GovernmentContracts, you can:
Follow Z2DA--FY27 NRM 558-24-160, Domestic Water, Chilled Water and Steam Piping (VA-26-00066009) Active
VETERANS AFFAIRS, DEPARTMENT OF
Bid Due: 12/09/2026
CM@R-Public Safety Answering Point (PSAP) 911 Call Center Reference number: COF1517015 Closing date
City of Fayetteville
Bid Due: 11/17/2026
Solicitation Number: 322-MAINT092926 Project Title: RFB FOR PARKING LOT PATCHING, SEALCOATING, AND RESTRIPING
State Government of North Carolina
Bid Due: 12/10/2026
Solicitation Number: 354-UT27-12 Project Title: Request for Qualifications - Master Plan & Rerating
State Government of North Carolina
Bid Due: 11/18/2026