ITB 2024-11
INTENT AND GENERAL INFORMATION
Mon cello High School Mi ga on – Building A
JEFFERSON COUNTY
BOARD OF COUNTY COMMISSIONERS
INTENT AND GENERAL INFORMATION
INVITATION TO BID NO: 2024-11
Monticello High School Mitigation – Building A
BID ADVERTISE DATE: December 20, 2024
BID RELEASE DATE: December 20, 2024
RESPONSE DUE DATE AND TIME: January 24, 2025, at 3:00 PM EST
MAIL OR DELIVER RESPONSE TO:
(Hand-delivery or express mail services)
Jefferson County Board of County Commissioners
ATTN: ITB 2024-11
450 W. Walnut Street
Monticello, FL 32344
Contact:
COUNTY MANAGER’S OFFICE
Theresa Sterling
450 W. Walnut Street
Monticello, FL 32344
850-342-0223
tsterling@jeffersoncountyfl.gov
1
ITB 2024-11
INTENT AND GENERAL INFORMATION
Mon cello High School Mi ga on – Building A
TABLE OF CONTENTS
INTENT AND GENERAL INFORMATION
SECTION 1.0 SCHEDULE OF EVENTS
SECTION 2.0 BID QUESTIONS
SECTION 3.0 SCOPE OF WORK
SECTION 4.0 RECEIPT AND OPENING OF THE BID
SECTION 5.0 CONE OF SILENCE
SECTION 6.0 BID RESPONSE REQUIREMENTS
SECTION 7.0 EVALUATION OF BIDS AND SELECTION PROCESS
SECTION 8.0 INTENT TO AWARD AND CONTRACT EXECUTION
SECTION 9.0 STANDARD TERMS AND CONDITIONS (STAC)
APPENDICES:
A. Legal Advertisement
B. Draft Agreement
2
ITB 2024-11
INTENT AND GENERAL INFORMATION
Mon cello High School Mi ga on – Building A
INTENT AND GENERAL INFORMATION
Jefferson County, Florida through Invitation to Bid No. 2024-10 is soliciting bids from qualified
businesses registered to do business in the State of Florida to provide repairs to private roads in
various sections throughout the County.
This project consists of the restoration and mitigation of future damage to the Monticello High
School, Building A. Requested construction services includes disassembly and storage of
reusable portions of wood floors and related historic elements on the first and second floors
and staircase; demolition and removal of existing concrete basement floor slab; installation of a
new drainage system; waterproofing of interior walls of basement spaces; Geo technical
services, including soil borings, soil testing, groundwater measurement, etc.; and a survey for
new underground piping within the building footprint and throughout the site.
It is the intent of this ITB to enter into a Contract with the successful Bidder to begin upon
approval of the Board of County Commissioners and the issuance of a Notice to Proceed (NTP),
for the Work.
Firms interested in preparing a bid for this ITB must complete the requirements set forth in this
ITB, its attached documents and documents incorporated by reference (collectively referred to
as the “ITB”). Under the bid process of Jefferson County, the conditions set forth herein are
binding on the Bidder as confirmed by the signature of a person with legal authority to bind the
Bidder on the cover letter transmitting its Bid to the County in response to this ITB.
If this ITB is amended, the County Manager’s Office will issue an appropriate addendum to the
ITB. Any addendums will be posted on the County Website. If an addendum is issued, all terms
and conditions of this ITB that are not specifically modified in the addendum shall remain
unchanged. An addendum to this ITB will be issued if any of the date and/or time change,
unless the date(s) fall after the date the ITB Bid(s) are due. Specific dates/time will be
determined at each phase.
It is understood and the Bidder hereby agrees to be solely responsible for obtaining all
materials and determining the best methods that will be utilized to meet the intent of the
specifications of this ITB. Failure by the Bidder to acquaint themselves with the available
information will not relieve them from responsibility for estimating properly the difficulty or
cost of successfully performing the work. Bidders are expected to examine the specifications
and all instructions pertaining to the required commodities/services. Failure to do so will be at
Bidder’s risk.
The County reserves the right to reject any Bid found to be non-responsive, vague, or non-
conforming. The County also reserves the right at any time to withdraw all or part of this ITB in
order to protect its best interests. The County is not liable for any costs incurred by the Bidder
in preparing its response, nor is a response an offer to contract with any Bidder. Pursuant to
Chapter 119, Florida Statutes (FS), all responses are subject to Florida’s public records laws.
3
ITB 2024-11
INTENT AND GENERAL INFORMATION
Mon cello High School Mi ga on – Building A
While every effort is made to ensure the accuracy and completeness of information in the ITB,
it is recognized that the information may not be complete in every detail and that all work may
not be expressly mentioned in the ITB. It is the responsibility of the Proposer to include in its
Proposal all pertinent information in accordance with the objectives of the ITB.
The ITB and any addenda issued are available on the Jefferson County website at
http://www.jeffersoncountyfl.gov or by contacting the County at 850-342-0223. All questions
pertaining to this ITB should be submitted in writing in accordance with the ITB instructions set
forth in Section 1.0 of the ITB.
ADA –Special Accommodations: Any person requiring accommodations by the County due to a
disability should call the County Manager’s Office at 850-342-0223 at least five (5) working days
prior to any pre-response Conference, response opening, or meeting. If you are hearing or
speech impaired, please contact the County Manager’s Office by the Florida Relay Service,
which can be reached at 1-800-955-8771 (TTY).
SECTION 1.0 SCHEDULE OF EVENTS
Failure to comply with this or any other paragraph of this ITB shall be sufficient reason for
rejection of the bid.
All times listed in the Schedule of Events are Eastern Standard Time (EST).
Event
Bid Advertisement Date
Release of Invitation to Bid
Bid Questions Due from Prospective Bidder
Responses to Bid Questions Due
BIDS DUE TO BOCC
Posting of Intended Award
Board Consideration of Intended Award
Posting of Notice of Award
Date/Time
December 20, 2024
December 20, 2024
January 3, 2025
January 10, 2025
January 24, 2025 at 3:00 PM
January 24, 2025
February 6, 2025
February 7, 2025
SECTION 2.0 BID QUESTIONS
All inquiries and questions concerning this ITB, must be in writing (e-mail is acceptable),
received in accordance with Section 1.0 Schedule of Events, and must be directed to: Theresa
Sterling, tsterling@jeffersoncountyfl.gov or mailed to 445 W. Palmer Mill Rd., Monticello, FL
32344.
Questions and responses will be posted on the County’s Website and, if necessary, an
Addendum or Addenda will be issued.
4
ITB 2024-11
INTENT AND GENERAL INFORMATION
Mon cello High School Mi ga on – Building A
SECTION 3.0 SCOPE OF WORK
This project consists of the restoration and mitigation of future damage to the Monticello High
School. Requested construction services includes disassembly and storage of reusable portions
of wood floors and related historic elements on the first and second floors and staircase;
demolition and removal of existing concrete basement floor slab; installation of a new drainage
system; waterproofing of interior walls of basement spaces; Geo technical services, including
soil borings, soil testing, groundwater measurement, etc.; and a survey for new underground
piping within the building footprint and throughout the site.
3.1 Careful disassembly of undamaged wood flooring and wainscoting located at the first and
second floors (East wing). These materials are to be stored at a dry location until
restoration/reinstallation.
3.2 Interior doors/door frames, transoms and hardware are to be carefully disassembled.
These materials are to be stored at a dry location until restoration/reinstallation.
3.3 Demolition of basement, first and second level interior wood stud walls as previously
executed on the west wing.
3.4 Careful disassembly of the eastern staircase, as well as other historic elements of the
building in this location that are yet to be restored. These materials are to be stored at a
dry location until restoration/reinstallation.
3.5 First and Second level wood floor joists are to be removed for access to basement floor
slab in accordance with the Architectural and Structural drawings in the same manner
performed on the previously restored west wing. These materials are to be stored at a dry
location until restoration/reinstallation.
3.6 Demolition of the existing basement floor slab.
3.7 Installation of below-slab drainage system at the east basement consistent with the
previously installed system at the west basement in accordance with Engineer drawings.
3.8 Both East and West under-slab drainage systems shall be joined and routed in a new
drainage line to the storm drain at the right of way north of the building.
3.9 A below slab helical pile/concrete foundation system will be required in accordance with
the structural engineer drawings as previously installed on the west wing basement floor.
5