Guaranteed Energy Savings Performance Contract

Location: Georgia
Posted: May 5, 2026
Due: Jun 3, 2026
Agency: Charlton County
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
  • R - Professional, Administrative and Management Support Services
  • Y - Construction of Structures and Facilities
Publication URL: To access bid details, please log in.
Bid Title: Guaranteed Energy Savings Performance Contract
Category: Invitation to Bid
Status: Open
Description:

Charlton County requests qualifications from interested Energy Services Companies (ESCO’s) for the design and implementation of a Guaranteed Energy Savings Performance Contract in various facilities, in accordance with (OCGA Title 50, Ch. 37) or other Georgia legislation.

This Request for Qualifications requires the selected ESCO to conduct an investment grade audit.  The selected firm will be required to identify, engineer, design, install, maintain, and provide financing options for approved energy conservation measures in a fixed cost scenario.

The intent of this project is to provide Charlton County with the means to improve its designated facilities through guaranteed energy, operational, maintenance and capital cost avoidance savings, as well as new revenue sources.

Publication Date/Time:
5/4/2026 12:00 AM
Closing Date/Time:
6/3/2026 11:00 AM
Submittal Information:
Three (3) paper copies and One (1) electronic copy must be submitted
Bid Opening Information:
June 3rd, 2026 at 11:00 AM
Contact Person:
Becky Harden
County Administrator
bharden@charltoncountyga.gov
68 Kingsland Drive, Suite B
Folkston, GA 31537
Business Hours:
Monday- Friday 8:00 AM-5:00 PM
Qualifications:
Information about RFQ procedures, format and content requirements, and a schedule of events can be found in the RFQ documents attached.
Related Documents:

Attachment Preview

Request for Qualifications
Guaranteed Energy Savings Performance Contract
for
Charlton County
RFQ for Guaranteed Energy Savings Performance Contract
Release date: May 4, 2026
Due Date: June 3, 2026
Time: 11:00am
Right to Reject: In submitting a response to this RFQ, it is understood by the respondent that the right is reserved by Charlton
County to accept or reject any and all responses, and to waive any irregularities or informalities when doing so is in the best
interest of Charlton County.
I. INTRODUCTION AND BACKGROUND
Charlton County requests qualifications from interested Energy Services Companies (ESCOs) for the
design and implementation of a Guaranteed Energy Savings Performance Contract in various
facilities, in accordance with (OCGA Title 50, Ch. 37) or other Georgia legislation.
This Request for Qualifications requires the selected ESCO to conduct an investment grade audit. The
selected firm will be required to identify, engineer, design, install, maintain, and provide financing
options for approved energy conservation measures in a fixed cost scenario.
The intent of this project is to provide Charlton County with the means to improve its designated
facilities through guaranteed energy, operational, maintenance and capital cost avoidance savings, as
well as new revenue sources.
II. RFQ PROCEDURES
A. Point of Contact
Questions concerning this RFQ and the procedures for responding to the RFQ should be
directed to:
Becky Harden
bharden@charltoncountyga.gov
B. Submission of Responses
Responses must be received by 11:00am on June 3, 2026. Respondents should submit three
(3) paper copies and one (1) electronic copy of the response to:
Becky Harden
County Administrator
68 Kingsland Drive, Suite B
Folkston, GA 31537
Proposals Enclosed Guaranteed Energy Savings Contract
Responses received after the time and date specified above will be disqualified as
unresponsive.
C. Schedule of Events
The following time frame is expected to be followed during the procurement period of this
RFQ. This is a tentative schedule, and dates are subject to change.
1
Release of RFQ May 4, 2026
RFQ proposal received June 3, 2026
Review of Submissions June 10, 2026
Formal selection of an ESCO partner June 18, 2026
Master Development Agreement executed with the selected ESCO June 2026
III. FORMAT AND CONTENTS
Responses must be submitted in the format outlined in this section. Responses must be no
more than twenty-five (25) pages total. Note: Cover Letter and Table of Contents do not count
toward the page limit. Charlton County reserves the right to eliminate from further
consideration any submittal deemed to be substantially or materially unresponsive to the
requests for qualifications contained herein.
A. Executive Summary
Responses shall include a concise abstract stating the respondents understanding of the
countys goals and objectives. The ESCO’s submission should identify their firms ability to
satisfy Charton Countys unique financial, technical and strategic goals and objectives.
B. Company Background & Experience
1. Provide a company overview / history of organization.
2. Describe prior relevant work experience and provide a minimum of five (5) references
of Guaranteed Energy Savings Programs implemented by your organization. Provide
the customers name, total project cost, name and telephone number of contact
person, and a brief description of the project.
3. Provide a comprehensive list of all Guaranteed Energy Savings Programs implemented
by your organization in the state of Georgia.
C. Project Development
1. Provide a description of your organizations project development process and typical
schedule.
2. Provide an overview of any additional service offerings currently being offered by your
company. Highlight the specific ways that you believe Charlton County could benefit
from these services.
3. Describe the process that your company uses to select the products and materials that
will be proposed as part of this project. Include a comprehensive list of any products
or materials that would be offered by your company as part of this project which are
manufactured, produced, owned, or otherwise controlled by your company or its
affiliates.
2
D. Project Management
1. Provide a description of your organizations approach to project management.
2. Provide a description of your organizations approach to the on-going maintenance
(service) of the installed equipment.
3. Provide a description of your organizations approach to warranty issues.
E. Financial
Provide a summary of your financial statements for the previous five (5) years.
3
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...Request for Proposals - Ulmer Park Mural Design & Installation by Jennifer Smith ...

City of SpringField

Bid Due: 7/31/2026

...26-049-LH Pleasant Hill Urban Design Master Planning Services (06/18/2026) May 18, 2026 Published... ...

Macon Bibb County

Bid Due: 6/18/2026

...Engineering and Design Services - Event No. 12300 Savannah, City Of May 27, ...

State Government of Georgia

Bid Due: 6/30/2026

...Project: Kentmere Lift Station Modifications and Force Main Design Ref. #: 26-68-3320 Type: ...

Forsyth County

Bid Due: 7/02/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.