| Bid Title: |
26-051 Airfield Stormwater Improvements at Pensacola International Airport
|
| Category: | Bids |
| Status: | Open |
|
Addendum Date: August 6, 2026
CITY OF PENSACOLA, FLORIDA
ITB No. 26-051
Airfield Stormwater Improvements
ADDENDUM #1
The following items take precedence over the documents for the item named above. All
other terms and conditions shall remain the same.
A SIGNED COPY OF THIS PAGE MUST BE RETURNED WITH YOUR SUBMITTAL
AS ACKNOWLEDGEMENT OF RECEIPT OF ADDENDUM.
Company: Date:
Authorized
Representative: Title:
Printed Name
Signature:
1. The question deadline was incorrectly listed in the bid document. The correct
deadline for submitting questions is August 11, 2026.
2. The pre-bid meeting was incorrectly changed to mandatory. It was optional.
Vendors who did not attend the pre-bid meeting are able to bid on the project. The
transcript and pre-bid attendance sheets are attached.
3. The DBE Goal for this project is 0%.
4. If submitting an electronic response and IF a bid/proposal bond is required:
An insurance company's executed bond may be included with the electronic
submittal.
OR
A certified check/cashier's check must be delivered to:
City Hall (lobby)
222 West Main Street Pensacola
Florida, 32502
Attention: Purchasing
Page 1 of 1
| Bid 26-051, Airfield Improvements Pre-Bid Meeting |
|---|
| Airport Public Conference Room |
| Airport Public Conference Room 0 minutes 37 seconds |
| Is it time? It's 9:39. I'll wait one minute. |
| Airport Public Conference Room 0 minutes 46 seconds |
| Thanks. |
| Airport Public Conference Room 0 minutes 56 seconds |
| Did everyone have a chance to call in? |
| Airport Public Conference Room 0 minutes 59 seconds |
| Yep. |
| Airport Public Conference Room 1 minute 2 seconds |
| Star. |
| Airport Public Conference Room 1 minute 4 seconds |
| OK, great. |
| Airport Public Conference Room 1 minute 15 seconds |
| Thank you all. Thank you all. |
| Airport Public Conference Room 1 minute 24 seconds |
| The. |
| Airport Public Conference Room 1 minute 26 seconds |
| Good morning, everyone. The date is August 4th, the time is 10 A.m. We are here to meet for project |
| number 26S051, airfield stormwater improvements. I'm just going to go over some procurement |
| policies, and then I'll pass it over to Kip and Mimi, who will go into more |
| Airport Public Conference Room 1 minute 46 seconds |
| project details. |
| Airport Public Conference Room 1 minute 49 seconds |
| It. |
| Airport Public Conference Room 1 minute 51 seconds |
| I just want to note the first thing in here is the question deadline is incorrect in the bid document. |
| The correct question deadline is August 11th at 10 A.m. |
| Airport Public Conference Room 2 minutes 3 seconds |
| So please note that. And we'll be issuing an addendum as well, correcting that date in the bid |
| document. |
| Airport Public Conference Room 2 minutes 11 seconds |
| The submittal deadline for this project is August 20th at 2.30 P.m. You can submit it three ways. You |
| can submit a hard copy version, or you could submit it digitally, either or whichever works easier for |
| your company. The 2 online ways you can submit is either Demand Star or Central Bidding. |
| Airport Public Conference Room 2 minutes 31 seconds |
| So you have a hard copy version or you can do digital, whichever works best. |
| Airport Public Conference Room 2 minutes 38 seconds |
| Again, that was that submittal deadline is August 20th. We'll have that and then we'll have the |
| opening August 21st via Teams. |
| Airport Public Conference Room 2 minutes 48 seconds |
Bid 26-051, Airfield Improvements Pre-Bid Meeting
Airport Public Conference Room
Airport Public Conference Room 0 minutes 37 seconds
Is it time? It's 9:39. I'll wait one minute.
Airport Public Conference Room 0 minutes 46 seconds
Thanks.
Airport Public Conference Room 0 minutes 56 seconds
Did everyone have a chance to call in?
Airport Public Conference Room 0 minutes 59 seconds
Yep.
Airport Public Conference Room 1 minute 2 seconds
Star.
Airport Public Conference Room 1 minute 4 seconds
OK, great.
Airport Public Conference Room 1 minute 15 seconds
Thank you all. Thank you all.
Airport Public Conference Room 1 minute 24 seconds
The.
Airport Public Conference Room 1 minute 26 seconds
Good morning, everyone. The date is August 4th, the time is 10 A.m. We are here to meet for project
number 26S051, airfield stormwater improvements. I'm just going to go over some procurement
policies, and then I'll pass it over to Kip and Mimi, who will go into more
Airport Public Conference Room 1 minute 46 seconds
project details.
Airport Public Conference Room 1 minute 49 seconds
It.
Airport Public Conference Room 1 minute 51 seconds
I just want to note the first thing in here is the question deadline is incorrect in the bid document.
The correct question deadline is August 11th at 10 A.m.
Airport Public Conference Room 2 minutes 3 seconds
So please note that. And we'll be issuing an addendum as well, correcting that date in the bid
document.
Airport Public Conference Room 2 minutes 11 seconds
The submittal deadline for this project is August 20th at 2.30 P.m. You can submit it three ways. You
can submit a hard copy version, or you could submit it digitally, either or whichever works easier for
your company. The 2 online ways you can submit is either Demand Star or Central Bidding.
Airport Public Conference Room 2 minutes 31 seconds
So you have a hard copy version or you can do digital, whichever works best.
Airport Public Conference Room 2 minutes 38 seconds
Again, that was that submittal deadline is August 20th. We'll have that and then we'll have the
opening August 21st via Teams.
Airport Public Conference Room 2 minutes 48 seconds
| There is a... |
|---|
| Airport Public Conference Room 2 minutes 51 seconds |
| 5% bid bond of your base bid. And that will have that has to be into purchasing at the time of |
| submittal. So if you submit it digitally, if you're going to be doing a certified check, cashier's check, it |
| has to be to purchasing by that deadline. |
| Airport Public Conference Room 3 minutes 10 seconds |
| or in your package if it's a bid bot. |
| Airport Public Conference Room 3 minutes 14 seconds |
| All questions, please submit them in writing to purchasing at cityofpensacola.com. So anything you |
| ask here verbally, we ask that you follow up in writing as well just to make sure we're getting all the |
| questions answered and everything. |
| Airport Public Conference Room 3 minutes 28 seconds |
| Right, does anyone have any questions for purchasing? Yes, sir. Do you need a hard copy for the bid |
| button? |
| Airport Public Conference Room 3 minutes 37 seconds |
| I will double check, but I think an electronic copy should suffice, but I will double check and we will |
| have that in writing in an addendum. So any questions asked here today will be answered in an |
| addendum as well. |
| Airport Public Conference Room 3 minutes 50 seconds |
| If there's other questions for purchasing, then I will give it to Kipen. Well, good morning, everybody. |
| I'm Kip Jordans. I'm with Atkins Realis, who's the design engineer firm for this project, supporting the |
| airport with some of the overall stormwater needs. I'll go into things, but I'll let Mimi. |
| Airport Public Conference Room 4 minutes 9 seconds |
| introduce herself here as well. My name is Mimi Tsai. I'm Assistant Director of Planning and |
| Engineering. Just to note everyone, there's an optional tour after this meeting. So we'll be meeting |
| down, we'll take you down to the ramp. Go ahead. |
| Airport Public Conference Room 4 minutes 27 seconds |
| Brief agenda, we'll cover all these items in the next slides. So for the first slide with the overview of |
| the project, this is more or less a rehash of what's in the bid documents, but we're installing roughly |
| 1800 linear feet of large diameter, 84 and 96 inch drainage pipe. |
| Airport Public Conference Room 4 minutes 47 seconds |
| 6 manholes and inlets and one outfall into the regional pond. And the pipe, most part, is parallel to |
| taxiway Alpha on the south side of runway 826. It goes past the airport maintenance facility around |
| the control, in the proximity of the control tower, and also past the ARF. |
| Airport Public Conference Room 5 minutes 8 seconds |
| fire station, and then we'll cross under Airfield Road to get to the regional pond. |
| Airport Public Conference Room 5 minutes 16 seconds |
| You can see there's about 8 or 10 bullets there for some of the major scope items. Again, things from |
| the plans, demolishing miscellaneous asphalt driveways. One is an old taxiway that's at the north end |
| of the project. There's the current maintenance access to taxiway alpha that the pipe gets installed |
| under that is getting demolished and not restored. |
| Airport Public Conference Room 5 minutes 38 seconds |
There is a...
Airport Public Conference Room 2 minutes 51 seconds
5% bid bond of your base bid. And that will have that has to be into purchasing at the time of
submittal. So if you submit it digitally, if you're going to be doing a certified check, cashier's check, it
has to be to purchasing by that deadline.
Airport Public Conference Room 3 minutes 10 seconds
or in your package if it's a bid bot.
Airport Public Conference Room 3 minutes 14 seconds
All questions, please submit them in writing to purchasing at cityofpensacola.com. So anything you
ask here verbally, we ask that you follow up in writing as well just to make sure we're getting all the
questions answered and everything.
Airport Public Conference Room 3 minutes 28 seconds
Right, does anyone have any questions for purchasing? Yes, sir. Do you need a hard copy for the bid
button?
Airport Public Conference Room 3 minutes 37 seconds
I will double check, but I think an electronic copy should suffice, but I will double check and we will
have that in writing in an addendum. So any questions asked here today will be answered in an
addendum as well.
Airport Public Conference Room 3 minutes 50 seconds
If there's other questions for purchasing, then I will give it to Kipen. Well, good morning, everybody.
I'm Kip Jordans. I'm with Atkins Realis, who's the design engineer firm for this project, supporting the
airport with some of the overall stormwater needs. I'll go into things, but I'll let Mimi.
Airport Public Conference Room 4 minutes 9 seconds
introduce herself here as well. My name is Mimi Tsai. I'm Assistant Director of Planning and
Engineering. Just to note everyone, there's an optional tour after this meeting. So we'll be meeting
down, we'll take you down to the ramp. Go ahead.
Airport Public Conference Room 4 minutes 27 seconds
Brief agenda, we'll cover all these items in the next slides. So for the first slide with the overview of
the project, this is more or less a rehash of what's in the bid documents, but we're installing roughly
1800 linear feet of large diameter, 84 and 96 inch drainage pipe.
Airport Public Conference Room 4 minutes 47 seconds
6 manholes and inlets and one outfall into the regional pond. And the pipe, most part, is parallel to
taxiway Alpha on the south side of runway 826. It goes past the airport maintenance facility around
the control, in the proximity of the control tower, and also past the ARF.
Airport Public Conference Room 5 minutes 8 seconds
fire station, and then we'll cross under Airfield Road to get to the regional pond.
Airport Public Conference Room 5 minutes 16 seconds
You can see there's about 8 or 10 bullets there for some of the major scope items. Again, things from
the plans, demolishing miscellaneous asphalt driveways. One is an old taxiway that's at the north end
of the project. There's the current maintenance access to taxiway alpha that the pipe gets installed
under that is getting demolished and not restored.
Airport Public Conference Room 5 minutes 38 seconds
| And then also a phased installation around the ARF driveway. The importance there, if I don't touch |
|---|
| on it later, is to always have the fire department with a way to get to the airfield. So that will be |
| something that is important. There is a temporary extension widening of that |
| Airport Public Conference Room 5 minutes 57 seconds |
| that driveway to help with that phased installation to maintain their access, but install the pipe. |
| Airport Public Conference Room 6 minutes 4 seconds |
| And then a new asphalt driveway that's in reference to with the maintenance area. And I do plan to |
| actually flip to the plans because the mouse is not showing up. With the maintenance area, that |
| driveway, when that goes away, the new connection will be from |
| Airport Public Conference Room 6 minutes 23 seconds |
| their shed to the ARF driveway, and they'll use the ARF driveway to access the airfield from that point |
| into the future. So that's that new asphalt driveway. Of course, there's the 84 and 96 inch pipes plus |
| the structures. A phased installation as well under Airfield Road. So Airfield Road provides access to |
| Airport Public Conference Room 6 minutes 44 seconds |
| the aircraft control tower to maintenance and for the fire department to get to that fire station that is |
| air side. So keeping that road open is important. It's not high traffic, but we do need to have a way |
| for people to get back and forth because it is the only Rd. to provide them access in their personal |
| vehicles. |
| Airport Public Conference Room 7 minutes 4 seconds |
| So that phased installation is shown in the plans. It does include, and I'll actually go into it on the |
| next slide, some temporary, what we call AOA, air operations area fence, secure perimeter fencing, in |
| order, in a bypass Rd. in order to allow that installation. And then the installation of the U-wall and |
| the riprap within the pond bottom. |
| Airport Public Conference Room 7 minutes 25 seconds |
| and then your backfill grading and re-stabilization, as well as some bioswale grass to be installed on |
| a pond on the east side. So this project is funded in part by FDEP grant, and that is one of the |
| improvements to the |
| Airport Public Conference Room 7 minutes 44 seconds |
| you know, the natural habitat that kind of comes with that grant. So if you're wondering why that is |
| separate from everything else, that is that is kind of the basis for that. |
| Airport Public Conference Room 7 minutes 57 seconds |
| So project staging and access. Like I mentioned, this project is around the air traffic control tower. |
| That area is accessed off of Summit Boulevard via Airfield Road. So right near the Roger Scott Tennis |
| Center is where Airfield Road is. So the typical gate access is |
| Airport Public Conference Room 8 minutes 15 seconds |
| Gate P12, it's a little bit hard to see in this drawing. And again, I do plan to go to the plans, but it's |
| down here and then the roadway around the regional pond to get to the staging area. We do show |
| in the plans over here, not quite right near the access gate, an area for employee parking. |
| Depending on what your needs are, you know, we can talk about additional employee areas, but |
| most employee vehicles will not be allowed through the gate. If it is a, you know, a company vehicle |
| with the appropriate either flags or signage, that can be allowed through the gate. |
| Airport Public Conference Room 8 minutes 55 seconds |
And then also a phased installation around the ARF driveway. The importance there, if I don't touch
on it later, is to always have the fire department with a way to get to the airfield. So that will be
something that is important. There is a temporary extension widening of that
Airport Public Conference Room 5 minutes 57 seconds
that driveway to help with that phased installation to maintain their access, but install the pipe.
Airport Public Conference Room 6 minutes 4 seconds
And then a new asphalt driveway that's in reference to with the maintenance area. And I do plan to
actually flip to the plans because the mouse is not showing up. With the maintenance area, that
driveway, when that goes away, the new connection will be from
Airport Public Conference Room 6 minutes 23 seconds
their shed to the ARF driveway, and they'll use the ARF driveway to access the airfield from that point
into the future. So that's that new asphalt driveway. Of course, there's the 84 and 96 inch pipes plus
the structures. A phased installation as well under Airfield Road. So Airfield Road provides access to
Airport Public Conference Room 6 minutes 44 seconds
the aircraft control tower to maintenance and for the fire department to get to that fire station that is
air side. So keeping that road open is important. It's not high traffic, but we do need to have a way
for people to get back and forth because it is the only Rd. to provide them access in their personal
vehicles.
Airport Public Conference Room 7 minutes 4 seconds
So that phased installation is shown in the plans. It does include, and I'll actually go into it on the
next slide, some temporary, what we call AOA, air operations area fence, secure perimeter fencing, in
order, in a bypass Rd. in order to allow that installation. And then the installation of the U-wall and
the riprap within the pond bottom.
Airport Public Conference Room 7 minutes 25 seconds
and then your backfill grading and re-stabilization, as well as some bioswale grass to be installed on
a pond on the east side. So this project is funded in part by FDEP grant, and that is one of the
improvements to the
Airport Public Conference Room 7 minutes 44 seconds
you know, the natural habitat that kind of comes with that grant. So if you're wondering why that is
separate from everything else, that is that is kind of the basis for that.
Airport Public Conference Room 7 minutes 57 seconds
So project staging and access. Like I mentioned, this project is around the air traffic control tower.
That area is accessed off of Summit Boulevard via Airfield Road. So right near the Roger Scott Tennis
Center is where Airfield Road is. So the typical gate access is
Airport Public Conference Room 8 minutes 15 seconds
Gate P12, it's a little bit hard to see in this drawing. And again, I do plan to go to the plans, but it's
down here and then the roadway around the regional pond to get to the staging area. We do show
in the plans over here, not quite right near the access gate, an area for employee parking.
Depending on what your needs are, you know, we can talk about additional employee areas, but
most employee vehicles will not be allowed through the gate. If it is a, you know, a company vehicle
with the appropriate either flags or signage, that can be allowed through the gate.
Airport Public Conference Room 8 minutes 55 seconds
| assuming the person is a badged driver for the secure area, but for people who either may not be |
|---|
| badged or may not be approved to drive, that area is identified outside the secure perimeter for their |
| vehicle parking. |
| Airport Public Conference Room 9 minutes 13 seconds |
| Also, staging and stockpiling in the immediate vicinity of the pipe can installation can be limited. And |
| I'll get to that in the plans as well. That pipe is sitting outside what's called the taxiway safety area. |
| Airport Public Conference Room 9 minutes 32 seconds |
| and then it's inside the taxiway object free area. So you will be allowed to work while aircraft come |
| and go along that taxiway, but you won't be allowed to leave piles of material either overnight in a |
| certain limit. Just a little bit off to the west side, |
| Airport Public Conference Room 9 minutes 51 seconds |
| would be outside the taxiway object free area. So as you're excavating and you're placing the |
| material, it might have to go just a hair further because that pipe is right there in that area between |
| the two airfield boundaries. |
| Airport Public Conference Room 10 minutes 8 seconds |
| And again, I'll bring up the plans. We can look at where those rest, you know, between the pipe just |
| to give you a little more familiarity with it if you don't already have familiarity with it. |
| Airport Public Conference Room 10 minutes 21 seconds |
| This is the phasing with, well, yeah, the two phases that we have identified in the plans. The left two |
| photos represent work area A, but they are further broken down into work area A, phase one, and |
| work area A, phase two. On the far left is work area A, phase one. |
| Airport Public Conference Room 10 minutes 43 seconds |
| They were determined from downhill to uphill. And work area A has that breakdown based off of the |
| installation under Airfield Road. So |
| Airport Public Conference Room 10 minutes 58 seconds |
| Work area A, phase one, again, the far left is the U-wall, the pipe, the structure, and some additional |
| pipe more or less up to that existing airport perimeter fence. If you drive down Airfield Road in that |
| area, you have airport perimeter fence on both sides of you, one for the regional pond. |
| Airport Public Conference Room 11 minutes 16 seconds |
| and then one for where the taxiway and the R station are. |
| Airport Public Conference Room 11 minutes 23 seconds |
| Once that pipe is installed up to that limit, then that would be backfilled and that bypass Rd. would |
| be constructed, pushing towards the regional pond. That includes A relocation, a temporary |
| installation of a perimeter fence to maintain that security around the region. |
| Airport Public Conference Room 11 minutes 41 seconds |
| pod. There are portions of the regional pod. If you go through gate P12, which would be that |
| entrance gate for construction activity, they don't have fence, right? So the pond itself rests within |
| the airport secure perimeter. So we have to move that fence and maintain that airport perimeter. So |
| then there would be that tax |
| Airport Public Conference Room 12 minutes |
| The temporary bypass Rd. is proposed to be asphalt millings, perhaps off of, you know, what was... |
| Airport Public Conference Room 12 minutes 9 seconds |
assuming the person is a badged driver for the secure area, but for people who either may not be
badged or may not be approved to drive, that area is identified outside the secure perimeter for their
vehicle parking.
Airport Public Conference Room 9 minutes 13 seconds
Also, staging and stockpiling in the immediate vicinity of the pipe can installation can be limited. And
I'll get to that in the plans as well. That pipe is sitting outside what's called the taxiway safety area.
Airport Public Conference Room 9 minutes 32 seconds
and then it's inside the taxiway object free area. So you will be allowed to work while aircraft come
and go along that taxiway, but you won't be allowed to leave piles of material either overnight in a
certain limit. Just a little bit off to the west side,
Airport Public Conference Room 9 minutes 51 seconds
would be outside the taxiway object free area. So as you're excavating and you're placing the
material, it might have to go just a hair further because that pipe is right there in that area between
the two airfield boundaries.
Airport Public Conference Room 10 minutes 8 seconds
And again, I'll bring up the plans. We can look at where those rest, you know, between the pipe just
to give you a little more familiarity with it if you don't already have familiarity with it.
Airport Public Conference Room 10 minutes 21 seconds
This is the phasing with, well, yeah, the two phases that we have identified in the plans. The left two
photos represent work area A, but they are further broken down into work area A, phase one, and
work area A, phase two. On the far left is work area A, phase one.
Airport Public Conference Room 10 minutes 43 seconds
They were determined from downhill to uphill. And work area A has that breakdown based off of the
installation under Airfield Road. So
Airport Public Conference Room 10 minutes 58 seconds
Work area A, phase one, again, the far left is the U-wall, the pipe, the structure, and some additional
pipe more or less up to that existing airport perimeter fence. If you drive down Airfield Road in that
area, you have airport perimeter fence on both sides of you, one for the regional pond.
Airport Public Conference Room 11 minutes 16 seconds
and then one for where the taxiway and the R station are.
Airport Public Conference Room 11 minutes 23 seconds
Once that pipe is installed up to that limit, then that would be backfilled and that bypass Rd. would
be constructed, pushing towards the regional pond. That includes A relocation, a temporary
installation of a perimeter fence to maintain that security around the region.
Airport Public Conference Room 11 minutes 41 seconds
pod. There are portions of the regional pod. If you go through gate P12, which would be that
entrance gate for construction activity, they don't have fence, right? So the pond itself rests within
the airport secure perimeter. So we have to move that fence and maintain that airport perimeter. So
then there would be that tax
Airport Public Conference Room 12 minutes
The temporary bypass Rd. is proposed to be asphalt millings, perhaps off of, you know, what was...
Airport Public Conference Room 12 minutes 9 seconds
| you know, a couple of those driveways. If it is milled up, you would have those millings, but, you |
|---|
| know, a bypass Rd. for those personal vehicles for the control tower, the maintenance staff, and the |
| fire department. Again, we have to maintain their access. So then the rest of the pipe would be |
| installed and that goes |
| Airport Public Conference Room 12 minutes 30 seconds |
| back to the north up to that fire department driveway. And that's that phased installation through |
| that driveway that I talked about, where there'd be a temporary widening of it shown on the north |
| end of that driveway. And then |
| Airport Public Conference Room 12 minutes 48 seconds |
| we get into work area B, which would be, again, from halfway of the fire department all the way up to |
| the north limit of the project. |
| Airport Public Conference Room 12 minutes 58 seconds |
| And that's shown in that right photo. So work area A and work area B are 60 calendar days. There's A |
| 30-day mobilization period on the front end. That all adds up to 150 calendar day period of |
| performance. And again, these phases were developed to maintain the airport operations. So you |
| won't be able to work them concurrently. |
| Airport Public Conference Room 13 minutes 18 seconds |
| If there's a desire to reverse the order, maybe work work area B prior to work area A, maybe work, |
| you know, the 84 inch section that's parallel taxiway alpha before doing the portion that goes to the |
| regional pond. Those discussions can be had. But again, |
| Airport Public Conference Room 13 minutes 37 seconds |
| Some of these areas, keeping ARF access, keeping air to Rd. access, those absolutely have to occur. |
| Airport Public Conference Room 13 minutes 48 seconds |
| So then that other element is that pond on the east side with the installation of the bioswale grass. |
| That grass would be installed on the banks of, there's really two ponds. You can see one is a little bit |
| darker than the other. It's the one that's uphill from the storm where you can see the green. So it's |
| only one of the ponds. |
| Airport Public Conference Room 14 minutes 8 seconds |
| that would get that by as well, grassing the one that does see more runoff. And this is on the east |
| side, it's off of Spanish Trail, right around where |
| Airport Public Conference Room 14 minutes 21 seconds |
| There's the flight school access. The name of that road is escaping me right now. But it's a go |
| Spanish Trail between Summit and Langley. It's right off there and there's an access down there. So |
| that grass mixture was coordinated through our landscape architects for appropriate grasses. |
| Airport Public Conference Room 14 minutes 44 seconds |
| for this climate. And there's a couple of different installation methods that can be done for it. But |
| again, that's just another element. This does not have to be worked after any of the other elements. |
| It could be first, it could be in the middle, it could be at the end within that period of performance. |
| Airport Public Conference Room 15 minutes 4 seconds |
| Plus then the establishment of that grass with watering for 45 days to get that established. So that is |
| the high level of the scope. And before we touch on that, like I said, I did want to go to the plans. |
| Airport Public Conference Room 15 minutes 23 seconds |
| Of. |
you know, a couple of those driveways. If it is milled up, you would have those millings, but, you
know, a bypass Rd. for those personal vehicles for the control tower, the maintenance staff, and the
fire department. Again, we have to maintain their access. So then the rest of the pipe would be
installed and that goes
Airport Public Conference Room 12 minutes 30 seconds
back to the north up to that fire department driveway. And that's that phased installation through
that driveway that I talked about, where there'd be a temporary widening of it shown on the north
end of that driveway. And then
Airport Public Conference Room 12 minutes 48 seconds
we get into work area B, which would be, again, from halfway of the fire department all the way up to
the north limit of the project.
Airport Public Conference Room 12 minutes 58 seconds
And that's shown in that right photo. So work area A and work area B are 60 calendar days. There's A
30-day mobilization period on the front end. That all adds up to 150 calendar day period of
performance. And again, these phases were developed to maintain the airport operations. So you
won't be able to work them concurrently.
Airport Public Conference Room 13 minutes 18 seconds
If there's a desire to reverse the order, maybe work work area B prior to work area A, maybe work,
you know, the 84 inch section that's parallel taxiway alpha before doing the portion that goes to the
regional pond. Those discussions can be had. But again,
Airport Public Conference Room 13 minutes 37 seconds
Some of these areas, keeping ARF access, keeping air to Rd. access, those absolutely have to occur.
Airport Public Conference Room 13 minutes 48 seconds
So then that other element is that pond on the east side with the installation of the bioswale grass.
That grass would be installed on the banks of, there's really two ponds. You can see one is a little bit
darker than the other. It's the one that's uphill from the storm where you can see the green. So it's
only one of the ponds.
Airport Public Conference Room 14 minutes 8 seconds
that would get that by as well, grassing the one that does see more runoff. And this is on the east
side, it's off of Spanish Trail, right around where
Airport Public Conference Room 14 minutes 21 seconds
There's the flight school access. The name of that road is escaping me right now. But it's a go
Spanish Trail between Summit and Langley. It's right off there and there's an access down there. So
that grass mixture was coordinated through our landscape architects for appropriate grasses.
Airport Public Conference Room 14 minutes 44 seconds
for this climate. And there's a couple of different installation methods that can be done for it. But
again, that's just another element. This does not have to be worked after any of the other elements.
It could be first, it could be in the middle, it could be at the end within that period of performance.
Airport Public Conference Room 15 minutes 4 seconds
Plus then the establishment of that grass with watering for 45 days to get that established. So that is
the high level of the scope. And before we touch on that, like I said, I did want to go to the plans.
Airport Public Conference Room 15 minutes 23 seconds
Of.
| Airport Public Conference Room 15 minutes 24 seconds |
|---|
| This will pull up now. |
| Airport Public Conference Room 15 minutes 27 seconds |
| Um... |
| Airport Public Conference Room 15 minutes 29 seconds |
| And I will just go a little bit more. |
| Airport Public Conference Room 15 minutes 36 seconds |
| Into. |
| Airport Public Conference Room 15 minutes 39 seconds |
| There it is. |
| Airport Public Conference Room 16 minutes 1 second |
| Does anyone need to sign in yet? Has everyone signed in? |
| Airport Public Conference Room 16 minutes 6 seconds |
| But. |
| Airport Public Conference Room 16 minutes 8 seconds |
| And not interesting. |
| Airport Public Conference Room 16 minutes 14 seconds |
| It. |
| Airport Public Conference Room 16 minutes 19 seconds |
| Yes. |
| Airport Public Conference Room 16 minutes 23 seconds |
| I need to join and try to ship. |
| Airport Public Conference Room 16 minutes 28 seconds |
| That's only showing. |
| Airport Public Conference Room 16 minutes 30 seconds |
| If you don't access the connections to my computer, so I think I... |
| Airport Public Conference Room 16 minutes 39 seconds |
| Anyone who's online, if you could sign in in the chat, that way we can get a sign-in sheet on there as |
| well. |
| Airport Public Conference Room 16 minutes 50 seconds |
| All right, so this is a closer up version of work area A, phase one. That's the portion that's a U-wall in |
| the pipe within the regional pond bottom. And then we have the existing airport fence line that is |
| right through here. And then |
| Airport Public Conference Room 17 minutes 9 seconds |
| the installation of the pipe up to that fence line limit. The next one would be... |
| Airport Public Conference Room 17 minutes 18 seconds |
| the relocation, the temporary AOA fence that's shown down here, the temporary bypass Rd. and |
| another segment of temporary AOA fence. Again, because when you drive down Airfield Road, you |
| have fence on both sides of you. So we're reestablishing that. We're shifting that road. So that way |
| we can install the pipe. |
| Airport Public Conference Room 17 minutes 37 seconds |
Airport Public Conference Room 15 minutes 24 seconds
This will pull up now.
Airport Public Conference Room 15 minutes 27 seconds
Um...
Airport Public Conference Room 15 minutes 29 seconds
And I will just go a little bit more.
Airport Public Conference Room 15 minutes 36 seconds
Into.
Airport Public Conference Room 15 minutes 39 seconds
There it is.
Airport Public Conference Room 16 minutes 1 second
Does anyone need to sign in yet? Has everyone signed in?
Airport Public Conference Room 16 minutes 6 seconds
But.
Airport Public Conference Room 16 minutes 8 seconds
And not interesting.
Airport Public Conference Room 16 minutes 14 seconds
It.
Airport Public Conference Room 16 minutes 19 seconds
Yes.
Airport Public Conference Room 16 minutes 23 seconds
I need to join and try to ship.
Airport Public Conference Room 16 minutes 28 seconds
That's only showing.
Airport Public Conference Room 16 minutes 30 seconds
If you don't access the connections to my computer, so I think I...
Airport Public Conference Room 16 minutes 39 seconds
Anyone who's online, if you could sign in in the chat, that way we can get a sign-in sheet on there as
well.
Airport Public Conference Room 16 minutes 50 seconds
All right, so this is a closer up version of work area A, phase one. That's the portion that's a U-wall in
the pipe within the regional pond bottom. And then we have the existing airport fence line that is
right through here. And then
Airport Public Conference Room 17 minutes 9 seconds
the installation of the pipe up to that fence line limit. The next one would be...
Airport Public Conference Room 17 minutes 18 seconds
the relocation, the temporary AOA fence that's shown down here, the temporary bypass Rd. and
another segment of temporary AOA fence. Again, because when you drive down Airfield Road, you
have fence on both sides of you. So we're reestablishing that. We're shifting that road. So that way
we can install the pipe.
Airport Public Conference Room 17 minutes 37 seconds
| the rest of the way. And then this goes up to the ARF station and then install the pipe under a |
|---|
| portion of the ARF driveway, give them a little bit wider access. They have wide vehicles that if they're |
| responding in an emergency, they go relatively fast and they'll take that turn pretty wide. So |
| Airport Public Conference Room 17 minutes 58 seconds |
| You know, the standard 16, 20 foot driveway is just a little too narrow for them if they do have an |
| actual emergency. |
| Airport Public Conference Room 18 minutes 8 seconds |
| And then... |
| Airport Public Conference Room 18 minutes 11 seconds |
| There's the installation. |
| Airport Public Conference Room 18 minutes 17 seconds |
| of the rest of the pipe. And then I talked about the demolition of the maintenance driveway. That |
| would be this portion through here, both where the pipe goes plus a little bit more. And then this is |
| that new driveway for maintenance that connects to the ARF station. That is detailed in the plans. |
| Airport Public Conference Room 18 minutes 36 seconds |
| with what that pavement section is supposed to be. |
| Airport Public Conference Room 18 minutes 40 seconds |
| And... |
| Airport Public Conference Room 18 minutes 42 seconds |
| I'll pull it up real fast. |
| Airport Public Conference Room 18 minutes 45 seconds |
| another two sheets, 3 sheets away. There's one question online. Do you have any information |
| regarding the existing located on the east-west alignment of drainage pipe? |
| JH |
| Josh Hamm 19 minutes 1 second |
| The existing utilities forgot utilities. |
| A |
| Airport Public Conference Room |
| 19 minutes 6 seconds19:06 |
| Airport Public Conference Room 19 minutes 6 seconds |
| Ah, there are some utility crossings. Most of them are parallel and between. |
| Airport Public Conference Room 19 minutes 18 seconds |
| It really the area. |
| Airport Public Conference Room 19 minutes 22 seconds |
| That would have some of the utility crossings would be right through here as we turn west and head |
| towards the regional pond. |
| Airport Public Conference Room 19 minutes 31 seconds |
| Most of them are shallower than what the pipe would be. So there might be the need to just protect |
| those through the installation. A few of them are abandoned. A couple of these FAA ones that we |
| see through here. |
| Airport Public Conference Room 19 minutes 51 seconds |
| Um... |
| Airport Public Conference Room 19 minutes 53 seconds |
the rest of the way. And then this goes up to the ARF station and then install the pipe under a
portion of the ARF driveway, give them a little bit wider access. They have wide vehicles that if they're
responding in an emergency, they go relatively fast and they'll take that turn pretty wide. So
Airport Public Conference Room 17 minutes 58 seconds
You know, the standard 16, 20 foot driveway is just a little too narrow for them if they do have an
actual emergency.
Airport Public Conference Room 18 minutes 8 seconds
And then...
Airport Public Conference Room 18 minutes 11 seconds
There's the installation.
Airport Public Conference Room 18 minutes 17 seconds
of the rest of the pipe. And then I talked about the demolition of the maintenance driveway. That
would be this portion through here, both where the pipe goes plus a little bit more. And then this is
that new driveway for maintenance that connects to the ARF station. That is detailed in the plans.
Airport Public Conference Room 18 minutes 36 seconds
with what that pavement section is supposed to be.
Airport Public Conference Room 18 minutes 40 seconds
And...
Airport Public Conference Room 18 minutes 42 seconds
I'll pull it up real fast.
Airport Public Conference Room 18 minutes 45 seconds
another two sheets, 3 sheets away. There's one question online. Do you have any information
regarding the existing located on the east-west alignment of drainage pipe?
JH
Josh Hamm 19 minutes 1 second
The existing utilities forgot utilities.
A
Airport Public Conference Room
19 minutes 6 seconds19:06
Airport Public Conference Room 19 minutes 6 seconds
Ah, there are some utility crossings. Most of them are parallel and between.
Airport Public Conference Room 19 minutes 18 seconds
It really the area.
Airport Public Conference Room 19 minutes 22 seconds
That would have some of the utility crossings would be right through here as we turn west and head
towards the regional pond.
Airport Public Conference Room 19 minutes 31 seconds
Most of them are shallower than what the pipe would be. So there might be the need to just protect
those through the installation. A few of them are abandoned. A couple of these FAA ones that we
see through here.
Airport Public Conference Room 19 minutes 51 seconds
Um...
Airport Public Conference Room 19 minutes 53 seconds
| Two of those are abandoned, but we have what we'll do is the FAA is very good at marking their |
|---|
| active lines. That would be a step in terms of the utility locates. But then the rest of the utilities, |
| because they are within the airport perimeter, would need to be located using a private utility locate. |
| Airport Public Conference Room 20 minutes 15 seconds |
| firm, the utility companies will not come out and locate their utilities within the airport perimeter. |
| Airport Public Conference Room 20 minutes 25 seconds |
| We have another question. Does the east pond currently hold water? Do you anticipate dewatering |
| prior to installation of the bioswale grassing? It is. |
| Airport Public Conference Room 20 minutes 38 seconds |
| It's a detention pond, so it will. |
| Airport Public Conference Room 20 minutes 43 seconds |
| So it will occasionally have water after a storm, but it does drain relatively quickly. So I don't |
| anticipate dewatering will be necessary to install the grass during the project, especially on the |
| slopes. There may have to be a little bit of flexibility in the installation schedule, but |
| Airport Public Conference Room 21 minutes 1 second |
| Again, that can be installed any time throughout the project duration. So just as long as it's not |
| actively raining or didn't rain the day or two before, then you'll be good to install the grass. And then |
| we'll have to just look ahead with the weather forecast. |
| Airport Public Conference Room 21 minutes 20 seconds |
| Make sure we're not about to get slammed with some rain right after insulation. Give it a little bit of |
| a chance to establish. |
| Airport Public Conference Room 21 minutes 28 seconds |
| but that can be worked through during the course of the project. There's another question. Is the |
| excavated trench within the TSA zone required to be backfilled at the end of each shift? So that. |
| Airport Public Conference Room 21 minutes 45 seconds |
| Get to look at sheet here. |
| Airport Public Conference Room 21 minutes 50 seconds |
| So the pipe installation itself is actually outside of the TSA. So. |
| Airport Public Conference Room 21 minutes 58 seconds |
| The TSA, Taxiway Safety Area, is this line that runs down here, keep going, at this structure, it then |
| ends up resting kind of in between the two. And then the object-free area is this line. |
| Airport Public Conference Room 22 minutes 18 seconds |
| That is over here. |
| Airport Public Conference Room 22 minutes 20 seconds |
| So the trench is outside the taxiway safety area and can be left overnight. And then |
| Airport Public Conference Room 22 minutes 33 seconds |
| You just can't have a stockpile left overnight between those two lines. So your stockpile would have |
| to be outside of the blue line, just a little bit to the west. |
| Airport Public Conference Room 22 minutes 46 seconds |
| There's, oh, sorry, only above ground stockpile. I mean, like in the trench be left open? Are you |
| saying it does have to be backfilled and no stockpiles? No, the trench in the object free area can be |
| left with coordination with the airport. So you just can't have the above ground. |
Two of those are abandoned, but we have what we'll do is the FAA is very good at marking their
active lines. That would be a step in terms of the utility locates. But then the rest of the utilities,
because they are within the airport perimeter, would need to be located using a private utility locate.
Airport Public Conference Room 20 minutes 15 seconds
firm, the utility companies will not come out and locate their utilities within the airport perimeter.
Airport Public Conference Room 20 minutes 25 seconds
We have another question. Does the east pond currently hold water? Do you anticipate dewatering
prior to installation of the bioswale grassing? It is.
Airport Public Conference Room 20 minutes 38 seconds
It's a detention pond, so it will.
Airport Public Conference Room 20 minutes 43 seconds
So it will occasionally have water after a storm, but it does drain relatively quickly. So I don't
anticipate dewatering will be necessary to install the grass during the project, especially on the
slopes. There may have to be a little bit of flexibility in the installation schedule, but
Airport Public Conference Room 21 minutes 1 second
Again, that can be installed any time throughout the project duration. So just as long as it's not
actively raining or didn't rain the day or two before, then you'll be good to install the grass. And then
we'll have to just look ahead with the weather forecast.
Airport Public Conference Room 21 minutes 20 seconds
Make sure we're not about to get slammed with some rain right after insulation. Give it a little bit of
a chance to establish.
Airport Public Conference Room 21 minutes 28 seconds
but that can be worked through during the course of the project. There's another question. Is the
excavated trench within the TSA zone required to be backfilled at the end of each shift? So that.
Airport Public Conference Room 21 minutes 45 seconds
Get to look at sheet here.
Airport Public Conference Room 21 minutes 50 seconds
So the pipe installation itself is actually outside of the TSA. So.
Airport Public Conference Room 21 minutes 58 seconds
The TSA, Taxiway Safety Area, is this line that runs down here, keep going, at this structure, it then
ends up resting kind of in between the two. And then the object-free area is this line.
Airport Public Conference Room 22 minutes 18 seconds
That is over here.
Airport Public Conference Room 22 minutes 20 seconds
So the trench is outside the taxiway safety area and can be left overnight. And then
Airport Public Conference Room 22 minutes 33 seconds
You just can't have a stockpile left overnight between those two lines. So your stockpile would have
to be outside of the blue line, just a little bit to the west.
Airport Public Conference Room 22 minutes 46 seconds
There's, oh, sorry, only above ground stockpile. I mean, like in the trench be left open? Are you
saying it does have to be backfilled and no stockpiles? No, the trench in the object free area can be
left with coordination with the airport. So you just can't have the above ground.
| Airport Public Conference Room 23 minutes 8 seconds |
|---|
| Well. |
| Airport Public Conference Room 23 minutes 10 seconds |
| This, Courtney, this is for you. The DVE goal of 0% depicted on the PowerPoint presentation conflicts |
| with the bid documents 12%. |
| Airport Public Conference Room 23 minutes 20 seconds |
| We'll we'll just address that and then we'll correct that. Yeah, the the correct goal is 0%. |
| Airport Public Conference Room 23 minutes 32 seconds |
| Um... |
| Airport Public Conference Room 23 minutes 34 seconds |
| I think those were all the items I mentioned I wanted to show in a little more detail in the plans. So I'll |
| go back to the last slide here of the presentation. |
| Airport Public Conference Room 23 minutes 49 seconds |
| Just like, yeah. |
| Airport Public Conference Room 23 minutes 52 seconds |
| So, kind of as was mentioned at the top by Courtney. |
| Airport Public Conference Room 23 minutes 58 seconds |
| Keep monitoring the city purchasing website for this solicitation, 26051. Of course, today is the pre- |
| bid conferences question deadline. That correct deadline, as she mentioned, is August 11th at 10 |
| A.m. That will be updated with an addendum. |
| Airport Public Conference Room 24 minutes 17 seconds |
| You can submit your questions to purchasing at cityofpensacola.com. She mentioned as well. Any |
| questions asked today, we ask that you resubmit those in writing to get the formal answer issued. |
| And then bids are due August 20th at 2.30 P.m. local time. She mentioned there are three ways to do |
| that. |
| Airport Public Conference Room 24 minutes 36 seconds |
| That includes your bid bond as well. And then based off of the project manual, bid prices shall be |
| valid for a period of 120 days. The DBE goal is 0% and we'll get that updated in the project manual |
| with the addendum. And then the addendums will be |
| Airport Public Conference Room 24 minutes 54 seconds |
| posted to the city website again, cityofpensacola.com slash bids. |
| Airport Public Conference Room 25 minutes |
| So that is all I have. Mimi, I'll see if you have anything else before we open up to any other questions. |
| Just open up to questions before we start the tour. Any other questions? |
| Airport Public Conference Room 25 minutes 13 seconds |
| Will the bin list be released? |
| Airport Public Conference Room 25 minutes 17 seconds |
| For the attendance list? Yes, it'll be on the website. OK. We'll post that with you then. OK. |
| Airport Public Conference Room 25 minutes 26 seconds |
| Online, any questions? |
| Airport Public Conference Room 25 minutes 31 seconds |
| Good. Well, what we'll do is we'll take a five-minute break. So there's a restroom right outside to the |
| left, and we'll meet back right here, and then we're going to take a shuttle to the airfield. |
Airport Public Conference Room 23 minutes 8 seconds
Well.
Airport Public Conference Room 23 minutes 10 seconds
This, Courtney, this is for you. The DVE goal of 0% depicted on the PowerPoint presentation conflicts
with the bid documents 12%.
Airport Public Conference Room 23 minutes 20 seconds
We'll we'll just address that and then we'll correct that. Yeah, the the correct goal is 0%.
Airport Public Conference Room 23 minutes 32 seconds
Um...
Airport Public Conference Room 23 minutes 34 seconds
I think those were all the items I mentioned I wanted to show in a little more detail in the plans. So I'll
go back to the last slide here of the presentation.
Airport Public Conference Room 23 minutes 49 seconds
Just like, yeah.
Airport Public Conference Room 23 minutes 52 seconds
So, kind of as was mentioned at the top by Courtney.
Airport Public Conference Room 23 minutes 58 seconds
Keep monitoring the city purchasing website for this solicitation, 26051. Of course, today is the pre-
bid conferences question deadline. That correct deadline, as she mentioned, is August 11th at 10
A.m. That will be updated with an addendum.
Airport Public Conference Room 24 minutes 17 seconds
You can submit your questions to purchasing at cityofpensacola.com. She mentioned as well. Any
questions asked today, we ask that you resubmit those in writing to get the formal answer issued.
And then bids are due August 20th at 2.30 P.m. local time. She mentioned there are three ways to do
that.
Airport Public Conference Room 24 minutes 36 seconds
That includes your bid bond as well. And then based off of the project manual, bid prices shall be
valid for a period of 120 days. The DBE goal is 0% and we'll get that updated in the project manual
with the addendum. And then the addendums will be
Airport Public Conference Room 24 minutes 54 seconds
posted to the city website again, cityofpensacola.com slash bids.
Airport Public Conference Room 25 minutes
So that is all I have. Mimi, I'll see if you have anything else before we open up to any other questions.
Just open up to questions before we start the tour. Any other questions?
Airport Public Conference Room 25 minutes 13 seconds
Will the bin list be released?
Airport Public Conference Room 25 minutes 17 seconds
For the attendance list? Yes, it'll be on the website. OK. We'll post that with you then. OK.
Airport Public Conference Room 25 minutes 26 seconds
Online, any questions?
Airport Public Conference Room 25 minutes 31 seconds
Good. Well, what we'll do is we'll take a five-minute break. So there's a restroom right outside to the
left, and we'll meet back right here, and then we're going to take a shuttle to the airfield.

With GovernmentContracts, you can:
...General Information Document ID IFB-360-2026056-2 Status Amended Description Drainage and Minor...
Palm Beach County
Bid Due: 9/08/2026
...General Information Document ID IFB-360-2026056-1 Status Open Description Drainage and Minor...
Palm Beach County
Bid Due: 9/08/2026
...General Information Document ID IFB-360-2026056-3 Status Amended Description Drainage and Minor...
Palm Beach County
Bid Due: 9/08/2026
...Description: Australian Avenue Drainage Improvements - Federalized Department: Engineering &...
Palm Beach County
Bid Due: 3/30/2029