Tender available date: Wednesday March 4, 2026.
Tender closing date: Wednesday April 15, 2026.
Project Inquiries: Kenneth Adagala, Project Procurement Officer, Alberta Transportation
E-mail:
kenneth.adgala@gov.ab.ca
TENDERS will only be received by email at
trans.tender@gov.ab.ca
, before 2:01:00 P.M., for construction of the following work:
TND0023734
Grading, Granular Base Course, Cold Milling, Asphalt Concrete Pavement, Intersection Improvements at Various Locations, Street Light Installation and Other Work
41:14 PAR 121 to 4 Km N of Hwy 600
kilometre 12.695 to 41.756
600:02 11 Km W of the Town of Provost to Hwy 13
kilometre 26.766 to 42.497
13:20 W of Hwy 899 to 16 Km E of the Town of Provost
kilometre 44.300 to 60.985
Central Region
APPROXIMATE QUANTITIES:
237 860 tonnes Supply of Aggregate – With Option
6 800 metres Cutting of Pavement
36 580 cubic metres Common Excavation
24 300 cubic metres Borrow Excavation – Contractor Supplied
23 760 cubic metres Common and/or Borrow Excavation Loaded to Trucks
5 500 cubic metres Subgrade Excavation
6 500 square metres Erosion Control Barrier (Silt Fence)
1 000 metres Culverts - Supply and Install (600 mm dia. C.S.P.)
40 910 square metres Preparing Subgrade Surface (First Layer)
35 000 tonnes Granular Base Course Des. 2 Class 25
760 tonnes Gravel Surfacing Des. 4 Class 20
71 000 square metres Topsoil Placement
19 190 square metres Slope Texturing
55 000 square metres Cold Milling Asphalt Pavement - 50
14 900 square metres Cold Milling Asphalt Pavement - 70
65 100 tonnes Asphalt Concrete Pavement – EPS Mix Type H2 (PG 58-28)
137 000 tonnes Asphalt Concrete Pavement – EPS Mix Type M1 (PG 52-34)
63.5 kilometres Milled Rumble Strip - Gap Edge Line
61.8 kilometres Roadway Lines - Supplying Paint and Painting (Directional Dividing and 2 Edge Lines)
790 posts Flexible Guidepost/Delineator - Round - Supply and Install
3 840 metres Trenching and Backfilling
3 285 metres Secondary Cable - Supply and Install (2c#4 Teck 90 HL Cable)
1 035 metres Secondary Cable - Supply and Install (2c#6 Teck 90 HL Cable)
Contractor to supply all materials.
Contract Completion Date: October 15, 2026.