Fire Station #1
Mechanical System Improvements
625 East Pine Street, Missoula, Montana
95% Progress Set
June 1, 2026
PROJECT DIRECTORY
Design Team
Mechanical Engineer / Project Manager
Western Montana Engineering, Inc.
1527 South Russell
Missoula, Montana 59801
Contact: Julie Aldegarie, P.E.
Phone: 406-721-5776
Email: julie@westernmtengineering.com
Owner
City of Missoula Fire Department
625 East Pine Street
Missoula, Montana 59802
Contact: Steven Pitman
Phone: 406-210-3471
E-mail: pitmans@ci.missoula.mt.us
SHEET INDEX
M0.1 - LEGEND AND GENERAL SPECIFICATIONS
M0.2 - HVAC SPECIFICATIONS
M0.3 - HVAC SCHEDULES
MD1.0 - BASEMENT AND HOSE TOWER DEMOLITION PLANS
MD1.1 - FIRST FLOOR OFFICES DEMOLITION PLAN
MD1.2 - APPARATUS BAY DEMOLITION PLAN
MD1.3 - SECOND FLOOR DEMOLITION PLANS
MD1.4 - SECOND FLOOR HYDRONIC DEMOLITION PLAN
MD1.5 - ROOF DEMOLITION PLAN
M1.0 - BASEMENT AND HOSE TOWER PLANS
M1.1 - FIRST FLOOR OFFICES HVAC PLAN
M1.2 - APPARATUS BAY HVAC PLAN
M1.3 - SECOND FLOOR HVAC PLAN
M1.4 - MECHANICAL ROOM PLANS
M1.5 - ROOF HVAC PLAN
M2.1 - HYDRONIC SYSTEM SCHEMATIC AND DETAILS
M3.1 - HVAC DETAILS
E0.1 - NOTES AND DETAILS
ED1.1 - ELECTRICAL DEMOLITION PLANS
E1.1 - ELECTRICAL PLANS
A1.0 - FIRST FLOOR ARCHITECTURAL PLAN
A1.1 - ROOF ARCHITECTURAL PLAN
East Pine Street
East Broadway
MECHANICAL LEGEND
ABBREVIATIONS
AFF
AG
ARCH
C.O.
DN
(E)
FCO
FA
MECH.
ABOVE FINISHED FLOOR
ABOVE GRADE
ARCHITECT OR ARCHITECTURAL
CLEANOUT
DOWN
EXISTING
FLOOR CLEANOUT
FRESH AIR
MECHANICAL
(N)
NC
NO
RA
SA
SS
TYP
VTR
WCO
NEW
NORMALLY CLOSED
NORMALLY OPEN
RETURN AIR
SUPPLY AIR
STAINLESS STEEL
TYPICAL
VENT THROUGH ROOF
WALL CLEANOUT
CONVENTIONS
NEW WORK (DARK)
EXISTING (LIGHT)
DEMOLISH
1
M1.0 SECTION REFERENCE
SD-#
# CFM
HVAC
AIR DEVICE MARK:
AIR DEVICE NUMBER ON TOP,
CFM ON BOTTOM
C
SC
H
R
SW
GW
HWS
HWR
CWS
CWR
GWS
GWR
SUPPLY AIR DUCT
RETURN AIR DUCT
RECTANGULAR DUCT
RECTANGULAR TO ROUND
DUCT TRANSITION
HEEL TAP BRANCH
ELBOW W/ TURNING VANES
HIGH-EFFICIENCY TAKE-OFF
WITH DAMPER
FLEXIBLE DUCT
HATCH INDICATES NEW
MECHANICAL EQUIPMENT
HATCH INDICATES EXPOSED
DUCTWORK AND AIR DEVICES
M
BD
F
FS
T
S
MS
CO
CO2
MOTOR OPERATED DAMPER
VOLUME DAMPER
BACKDRAFT DAMPER
FIRE DAMPER
COMBINATION FIRE/SMOKE DAMPER
THERMOSTAT
TEMPERATURE SENSOR
MANUAL SWITCH
CARBON MONOXIDE
SENSOR
CARBON DIOXIDE SENSOR
SUPPLY AIR DEVICE
WITH AIR FLOW
DIRECTIONS INDICATED
RETURN AIR DEVICE
PLUMBING AND HYDRONIC
DOMESTIC COLD WATER
SOFTENED COLD WATER
DOMESTIC HOT WATER
HOT WATER RECIRCULATION
WASTE
SANITARY WASTE
GREASE WASTE
VENT
HEATING WATER SUPPLY
HEATING WATER RETURN
CHILLED WATER SUPPLY
CHILLED WATER RETURN
GROUNDWATER SUPPLY
GROUNDWATER RETURN
CD
IRR
LPS
MPS
GCR
PCR
NG
LPG
CA
VAC
NO
RD
RDO
CONDENSATE DRAIN
IRRIGATION PIPING
LOW PRESSURE STEAM
MEDIUM PRESSURE STEAM
GRAVITY CONDENSATE RETURN
PUMPED CONDENSATE RETURN
NATURAL GAS
PROPANE PIPING
COMPRESSED AIR PIPING
VACUUM PIPING
NITROUS OXIDE GAS PIPING
ROOF DRAINAGE PIPING
ROOF DRAIN OVERFLOW PIPING
TEE UP
TEE DOWN
ELBOW UP
ELBOW DOWN
CLEANOUT
CLEANOUT
FLOOR DRAIN
FLOOR SINK
COLD SUPPLY STOP
HOT SUPPLY STOP
P-TRAP
P-TRAP
HOSE END DRAIN
CAP
UNION
GLOBE VALVE
ISOLATION VALVE
PRESSURE REDUCING VALVE
CHECK VALVE
BACKFLOW PREVENTOR
GAS VALVE
MANUAL BALANCE VALVE
RELIEF VALVE
TWO-WAY CONTROL VALVE
THREE-WAY CONTROL VALVE
CONCENTRIC REDUCER
ECCENTRIC REDUCER
TRAP
TEST PLUG
STRAINER
THERMOMETER
IMMERSION WELL & SENSOR
PUMP
FIRE SPRINKLER HEAD
METER
MANUAL AIR VENT
PIPING ISOLATOR
GAUGE
POINT OF CONNECTION
MECHANICAL SHEET INDEX
M0.1 - LEGEND AND GENERAL SPECIFICATIONS
M0.2 - HVAC SPECIFICATIONS
M0.3 - HVAC SCHEDULES
MD1.0 - BASEMENT AND HOSE TOWER DEMOLITION PLANS
MD1.1 - FIRST FLOOR OFFICES DEMOLITION PLAN
MD1.2 - APPARATUS BAY DEMOLITION PLAN
MD1.3 - SECOND FLOOR DEMOLITION PLANS
MD1.4 - SECOND FLOOR HYDRONIC DEMOLITION PLAN
MD1.5 - ROOF DEMOLITION PLAN
M1.0 - BASEMENT AND HOSE TOWER PLANS
M1.1 - FIRST FLOOR OFFICES HVAC PLAN
M1.2 - APPARATUS BAY HVAC PLAN
M1.3 - SECOND FLOOR HVAC PLAN
M1.4 - MECHANICAL ROOM PLANS
M1.5 - ROOF HVAC PLAN
M2.1 - HYDRONIC SYSTEM SCHEMATIC AND DETAILS
M3.1 - HVAC DETAILS
GOVERNING CODES
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 UNIFORM PLUMBING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2020 NATIONAL ELECTRIC CODE
COMCHECK
Date:
June 1, 2026
Revisions:
LEGEND AND
GENERAL
SPECIFICATIONS
M0.1
HVAC
SPECIFICATIONS
M0.2
Revisions:
June 1, 2026
Date:
ROOF-TOP UNIT SCHEDULE - RTU-5
BOILER SCHEDULE
MARK
MANUF. AND MODEL
INPUT CAPACITY
OUTPUT CAPACITY
VOLT/PHASE
FLA
B-1
LOCHINVAR KHB155N
155,000 BTU/HR
143,000 BTU/HR
120 / 1Ø
---
B-2
LOCHINVAR KHB155N
155,000 BTU/HR
143,000 BTU/HR
120 / 1Ø
---
1. PROVIDE WITH FLOW SWITCH, SIDEWALL CONCENTRIC VENT KIT, AND CONDENSATE NEUTRALIZATION KIT.
MOCP
15
15
COMMENTS
1
1
PUMP SCHEDULE
MARK
P-1
P-2
P-3
P-4
SERVES
BOILER B-1
BOILER B-2
MAIN CIRC
MAIN CIRC
MANUFACTURER
AND MODEL
GRUNDFOS UPMS20-78
GRUNDFOS UPMS20-78
TACO VR15M
TACO VR15M
GPM HEAD
RPM
9
10'
---
9
10'
---
25
30'
---
25
30'
---
1. PUMP SHALL BE SUITABLE FOR 30% PROPYLENE GLYCOL.
2. PUMP PROVIDED WITH BOILER, SHIPPED LOOSE, AND FIELD-INSTALLED.
3. PUMP SHALL BE DUCTILE IRON MODEL.
H.P.
FRAC.
FRAC.
0.6 MAX
0.6 MAX
VOLT/PHASE
120 V / 1Ø
120 V / 1Ø
120 V / 1Ø
120 V / 1Ø
COMMENTS
1, 2
1, 2
1, 3
1, 3
MARK
EF-1
MANUFACTURER
AND NUMBER
CAPTIVEAIRE DU240HFA
EXHAUST FAN SCHEDULE
CFM
E.S. P.
RPM
SONES
H.P.
(IN. W. C.)
(AT 5 FT)
4600
1.0"
914
16.4
3
VOLT/PHASE
FLA
208V / 3Ø
10.2
COMMENTS
1, 2
1. PROVIDE WITH 14" HIGH CURB FOR FLAT ROOF, MOTORIZED BACKDRAFT DAMPER, EXHAUST FAN HEAT BAFFLE, FACTORY-MOUNTED AND WIRED VFD, AND BACNET SUITABLE.
BASEBOARD SCHEDULE
MARK
BB-1
BB-2
BB-3
BB-4
BB-5
MANUFACTURER
AND NUMBER
SLANT-FIN 351-14
SLANT-FIN 351-14
SLANT-FIN 351-14
SLANT-FIN 351-14
SLANT-FIN 351-14
COVER
HEIGHT
14"
14"
14"
14"
14"
NO. OF
TIERS
2
2
2
2
2
TUBE DIAM.,
MATERIAL
3/4" Cu
ELEMENT
TYPE
H-1
3/4" Cu
H-1
3/4" Cu
H-1
3/4" Cu
H-1
3/4" Cu
H-1
ACTIVE
LENGTH
2.0'
2.0'
2.0'
4.0'
6.0'
HEATING
BTU/HR
960
960
960
1,920
2,880
GPM
1.0
1.0
1.0
1.0
1.0
COMMENTS
1, 2
1, 2
1, 2
1, 2
1, 2
GENERAL: HEATING CAPACITY AT 120 F AVG WT, 70 F EAT.
1. PROVIDE AT 8" TO 12" OF CASING ON EACH END OF ACTIVE LENGTH, INCLUDING VALVE COVER. SPECIALTIES SHALL BE LOCATED IN THE UNIT CASING OR
EXPOSED NEAR THE CEILING ABOVE.
2. PROVIDE WITH STANDARD WHITE POWDER-COATED FINISH.
CONVECTOR SCHEDULE
MARK
UC-1
UC-2
UC-3
MANUFACTURER
AND NUMBER
RITTLING SF
RITTLING SF
RITTLING SF
LENGTH
24"
28"
24"
DEPTH
6"
8"
6"
HEIGHT
32"
32"
32"
HEATING
BTU/HR
1,500
2,500
1,500
GPM
1.0
1.0
1.0
COMMENTS
1
1
1
GENERAL: HEATING CAPACITY AT 120 F AVG WT, 70 F EAT.
1. CONVECTOR SHALL HAVE 16-GAUGE STEEL CABINET IN ONE OF MANUFACTURER'S STANDARD COLORS, TO BE SELECTED
AT SUBMITTAL TIME. PROVIDE WITH STANDARD LOUVERED INLET AND OUTLET AND ONE ACCESS DOOR IN FRONT OF
UNIT.
FAN-COIL UNIT SCHEDULE
MARK
FC-1
FC-2
FC-3
MANUFACTURER
AND NUMBER
DAIKIN BCHD0081
DAIKIN BCHD0061
DAIKIN BCHD0081
TOTAL
CFM
800
600
800
OA E.S.P.
CFM IN W.C.
120 0.70"
110 0.70"
120 0.70"
BTU/HR
25,000
22,000
18,000
HEATING
EAT
GPM
55 F
2.5
55 F
2.2
55 F
1.8
WATER dP
2.5' W.C.
1.8' W.C.
1.4' W.C.
COOLING HP MAX
BTU/HR
VOLT/
PHASE
FLA MCA COMMENTS
21,810
0.52 120 / 1Ø 8.8 11.0
1, 2
14,920
0.38 120 / 1Ø 6.4
8.0
1, 2
19,100
0.47 120 / 1Ø 8.8 11.0
1, 2
GENERAL: HEATING CAPACITY AT 120 F EWT, 30% PROPYLENE GLYCOL. COOLING CAPACITY AT 80 F DB / 61 F WB EAT.
1. PROVIDE WITH BOTTOM FILTER ACCESS.
2. UNIT TO BE HUNG FROM CEILING EXPOSED IN SPACE.
CONDENSING UNIT SCHEDULE
MARK
CU-1
CU-2
CU-3
MANUFACTURER
AND NUMBER
DAIKIN DC3SEN2410
DAIKIN DC3SEN1810
DAIKIN DC3SEN2410
COOLING
RATED CAPACITY
BTU/HR
23,200
18,000
23,200
SEER2
13.4
13.4
13.4
ELECTRICAL
VOLT AND
MCA
PHASE
208 / 230V / 1Ø
13.5
208 / 230V / 1Ø
11.1
208 / 230V / 1Ø
13.5
MOCP
20
15
20
1. PROVIDE WITH TXV, LINE SETS, HARD START KIT, FREEZE-STAT KIT, AND LOW AMBIENT KIT.
2. SEER2 IS AT ARI CONDITIONS.
COMMENTS
1, 2
1, 2
1, 2
CABINET UNIT HEATER SCHEDULE
MARK
CUH-1
MANUFACTURER
AND NUMBER
DAIKIN FCHH203
TOTAL
CFM
330
OA E.S.P.
CFM IN W.C.
0
0.50"
BTU/HR
11,000
HEATING
HP
EAT
GPM WATER dP
VOLT/
PHASE
FLA MCA COMMENTS
60° F
1.2 0.5' W.C.
FRAC 120 / 1Ø 3.5
4.4
1
GENERAL: HEATING CAPACITY AT 120 F EWT, 30% PROPYLENE GLYCOL.
1. UNIT TO BE HUNG FROM CEILING EXPOSED IN SPACE.
AIR DEVICE SCHEDULE
NOTE: AIR DEVICES WITH MARK OF (E)SD-# ARE EXISTING AIR DEVICES FROM PREVIOUS DESIGNS.
MARK
SD-1
SD-2
SD-3
SD-4
SD-5
RG-1
RG-2
RG-3
RG-4
RG-5
RG-6
EG-1
TG-1
MANUFACTURER
AND NUMBER
SHOEMAKER 700MA
SHOEMAKER 700MA
SHOEMAKER 700MA
SHOEMAKER 700MA
SHOEMAKER 700MA
SHOEMAKER 905
SHOEMAKER 905
SHOEMAKER 905
SHOEMAKER 905
SHOEMAKER 905
SHOEMAKER 905
SHOEMAKER 905
SHOEMAKER 905
FACE
SIZE
6X6
8X8
8X8
10 X 10
14 X 14
10 X 4
10 X 6
12 X 6
14 X 6
16 X 16
48 X 24
48 X 24
14 X 6
NECK
SIZE
6X6
8X8
8X8
10 X 10
14 X 14
10 X 4
10 X 6
12 X 6
14 X 6
16 X 16
48 X 24
48 X 24
14 X 6
THROW
2 WAY
2 WAY
4 WAY
4 WAY
1 WAY
-
-
-
-
-
-
-
-
FINISH
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
WHITE
MOUNTING/FRAME
OBD
24 X 24 LAY-IN PANEL
NO
24 X 24 LAY-IN PANEL
NO
24 X 24 LAY-IN PANEL
NO
24 X 24 LAY-IN PANEL
NO
24 X 24 LAY-IN PANEL
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
SURFACE MOUNT
NO
1. SIMILAR AIR DEVICES BY KRUEGER, CARNES, PRICE, AND TITUS ARE ALSO ACCEPTABLE.
2. CONTRACTOR SHALL VERIFY ALL MOUNTING CONDITIONS AND AIR DEVICE COLORS.
Date:
June 1, 2026
Revisions:
HVAC
SCHEDULES
M0.3
1/2" TWS,
1/2" TWR
TO (E)BB-2
3/4" TWS,
3/4" TWR
NOTE: TWS, TWR
PIPING EXPOSED
ALONG EAST WALL.
(E)BB-2 - 1/2"
TWS, TWR
CONNECTIONS
1/2"DN
1/2" TWS,
1/2" TWR
TO (E)BB-1
(E)BB-1
1/2"DN
(E)BB-2
B04
B03
TWS
TWR
B07
TYPICAL 1
B08
3/4" TWR UP
3/4" TWS UP
B02
B01
B05
B06
B09
1 BASEMENT DEMOLITION PLAN
N
MD1.0 1/4" = 1'-0"
NOTE: 1/2" TWS AND TWR
CONNECTIONS TO (E)BB-5
AND (E)CUH-1. PIPING IS
EXPOSED IN ROOM.
3/4"
7x6
122
9x6
24 x 8, CONTRACTOR
TO VERIFY
2
(E)CUH-1
123
124
122
9x6
7x6
UP TO
ACCESS
(E)BB-5
LADDER
2 FIRST FLOOR HOSE TOWER DEMOLITION PLAN
N
MD1.0 1/4" = 1'-0"
TO ROOF
216
FAN HIGH
IN SPACE
(E)EF
(E)BB-5
1
217
ACCESS
LADDER
3 SECOND FLOOR HOSE TOWER DEMOLITION PLAN
N
MD1.0 1/4" = 1'-0"
GENERAL NOTES
1. EXISTING TEMPERATURE SENSORS AND/OR THERMOSTATS WILL BE REMOVED BY ELECTRO CONTROLS.
2. TWS / TWR REFERS TO HEATING WATER SUPPLY AND RETURN PIPING.
CONSTRUCTION NOTES
1 REMOVE RADIATOR AND EXISTING PIPING BACK FAR ENOUGH TO INSTALL NEW RADIATOR.
2 REMOVE CABINET UNIT HEATER, PIPING, AND DUCTWORK BACK FAR ENOUGH TO INSTALL NEW UNIT.
Date:
June 1, 2026
Revisions:
BASEMENT AND
HOSE TOWER
DEMOLITION
PLANS
MD1.0