Specifications by JH
Page 1 of 9
Reviewed by MW/TN
Jacket 741-835
Requisition: 3-00002
U.S. Government Publishing Office (GPO)
Government Publishing and Printing Procurement
General Terms, Conditions, and Specifications
for the procurement of
Document Scanning (St Paul Project)
As requisitioned from the U.S. Government Publishing Office (GPO) by the
Department of Defense
BID OPENING: Bids shall be opened at 1:00 p.m., prevailing Eastern Standard Time, on June 18, 2026 at the
U.S. Government Publishing Office. All parties interested in attending the bid opening shall email bids@gpo.gov
one (1) hour prior to the bid opening date and time to request a Microsoft Teams live stream link. This must be a
separate email from the bid submission. The link will be emailed prior to the bid opening.
Any questions before or after award concerning these specifications contact Juliann Handziak at
Jhandziak@gpo.gov or (614) 488-4616, Ext. 3. No collect calls.
BID SUBMISSION: Bidders must email bids to bids@gpo.gov for this solicitation. No other method of bid
submission will be accepted at this time. The Jacket Number 741-835 and bid opening date must be specified in
the subject line of the emailed bid submission. Bids received after the bid opening date and time specified above
will not be considered for award.
ADDITIONAL EMAILED BID SUBMISSION PROVISIONS: The Government will not be responsible for
any failure attributable to the transmission or receipt of the emailed bid including, but not limited to, the
following:
1. Illegibility of bid.
2. Emails over 75 MB may not be received by GPO due to size limitations for receiving emails.
3. The bidder’s email provider may have different size limitations for sending email; however, bidders are advised
not to exceed GPO’s stated limit.
4. When the email bid is received by GPO, it will remain unopened until the specified bid opening time.
Government personnel will not validate receipt of the emailed bid prior to bid opening. GPO will use the
prevailing time (specified as the local time zone) and the exact time that the email is received by GPO’s email
server as the official time stamp for bid receipt at the specified location.
BIDDERS PLEASE NOTE: The GPO 910 “BID” Form is no longer required. Bidders are to fill out,
sign/initial, as applicable, pages 8-9.
INSPECTION OF MATERIAL: Contractor is required to examine furnished material immediately upon
receipt, pursuant to GPO Publication 310.2, Contract Clauses, 7. Government Furnished Property (GFP). If at that
time there is disagreement with the description or requirements as presented in the specifications and prior to the
performance of any work, the contractor shall contact the contract administrator Juliann Handziak at 614-488-
4616, x3. Failure to bring any discrepancies to the attention of the GPO will not relieve the contractor of the
responsibility to perform. An accurate number of originals cannot be determined at this time. Contractor must
inform the US GPO Publishing Specialist via email immediately if furnished material is 10% more than estimated
count.
GPO CONTRACT TERMS: Any contract which results from this Invitation for Bid will be subject to the
applicable provisions, clauses, and supplemental specifications of GPO Contract Terms (GPO Pub. 310.2,
effective 12/1/87, Rev. 01-18).
• GPO Contract Terms (GPO Publication 310.2): https://www.gpo.gov/docs/default-source/forms-and-
standards-files-for-vendors/contractterms2018.pdf
Page 2 of 9
Jacket 741-835
WARRANTY: Contract Clause 15, "Warranty", of GPO Contract Terms (Publication 310.2, effective December
1, 1987 (Rev. 01-18)) is amended for the solicitation to the effect that the warranty period is EXTENDED from
120 days to one calendar year from the date the check is tendered as final payment. All other provisions remain
the same.
SECURITY WARNING: It is the contractor's responsibility to properly safeguard personally identifiable.
information (PII) from loss, theft, or inadvertent disclosure and to immediately notify the Government of
any loss of personally identifiable information. PII is "information which can be used to distinguish or trace an
individual's identity, such as their name, social security number, biometric records, etc., alone, or when combined
with other personal or identifying information which is linked or linkable to a specific individual, such as date and
place of birth, mother's maiden name, etc. (Ref.: OMB Memorandum 07-16.) Other
specific examples of PII include, but are not limited to:
(a) Personal identification number, such as passport number, driver's license number, taxpayer
identification number, or financial account or credit card number.
(b) Address information, such as street address or personal email address; and,
(c) Personal characteristics, including photographic image (especially of face or other distinguishing
characteristic), fingerprints, handwriting, or other biometric image or template data (e.g., retina scans,
voice signature, facial geometry).
SECURITY CONTROL PLAN: The contractor shall operate and maintain an effective security system whereby
materials used to perform the contract are manufactured and/or stored (e.g. while awaiting distribution or
disposal) so as to ensure against theft and/or the unauthorized possession of the materials. Contractor is cautioned
that Government provided information shall not be used for non-government business. Specifically, Government
information shall not be used for the benefit of a third party.
The Government retains the right to conduct on-site security reviews at any time during this contract.
1.The plan shall contain at a minimum how government files (data) will be secured to prevent disclosure to a third
party prior to and after termination of contract.
2.Explain how all accountable materials will be handled throughout all phases of production.
3.How the disposal of waste materials will be handled; and,
4.How all applicable Government-mandated security/privacy/rules and regulations as cited in this contract shall
be adhered to by the contractor and/or subcontractor(s).
The Contractor shall assume all records are unclassified, as all previously classified records should have been
declassified. There could be instances where the record(s) were declassified (noted on the first page), but the
markings on subsequent pages were not properly removed. In the event records are found with classified
markings, the Contractor shall immediately protect the record and contact DOE.
The Contractor must utilize a Federal accredited moderate boundary network to ensure the protection of Federal
records. The records may contain Controlled Unclassified Information (CUI) and in most cases are not marked
properly or have old markings. The Contractor must safeguard the records, and the records must be kept under an
authorized person's direct control or protected with at least one physical barrier to protect CUI from unauthorized
access. When not in an authorized holder's direct possession, CUI will be kept in a locked desk drawer, filing
cabinet or within a locked office as long as the CUI is protected from unauthorized viewing. DOE O 471.7,
Controlled Unclassified Information (CUI) Paragraph 4f(4)v
See attached for General security requirements and guidance
PREAWARD SURVEY: In order to determine the responsibility of the prime contractor or any subcontractor,
the Government reserves the right to conduct an on-site preaward survey at the contractor's/subcontractor's facility
or to require other evidence of technical, production, managerial, financial, and similar abilities to perform, prior
to the award of a contract. As part of the financial determination, the contractor in line for award may be required
to provide one or more of the following financial documents:
1) Most recent profit and loss statement
Page 3 of 9
Jacket 741-835
2) Most recent balance sheet
3) Statement of cash flows
4) Current official bank statement
5) Current lines of credit (with amounts available)
6) Letter of commitment from paper supplier(s)
7) Letter of commitment from any subcontractor
The documents will be reviewed to validate that adequate financial resources are available to perform the contract
requirements. Documents submitted will be kept confidential and used only for the determination of responsibility
by the Government. Failure to provide the requested information in the time specified by the Government may
result in the Contracting Officer not having adequate information to reach an affirmative determination of
responsibility.
PAYMENT: Submitting invoices for payment via the GPO fax gateway (if no samples are required) utilizing the
GPO barcode coversheet application program is the most efficient method of invoicing. Instruction for using this
method can be found at the following web address:
http://winapps.access.gpo.gov/fms/vouchers/barcode/instructions.html .
Invoices may also be mailed to: U.S. Government Publishing Office, Office of Financial Management,
Attn: Comptroller, Stop: FMCE, Washington, DC 20401.
For more information about the billing process refer to the General Information of the Office of Finance web page
located at https://www.gpo.gov/how-to-work-with-us/vendors/how-to-get-paid.
NOTE: Partial Payments, as defined in GPO Pub. 310.2, Contract Terms, Contract Clause 25, are authorized
provided that each payment request is for one or more completed lots (payment for a partial lot will not be
permitted). Payment requests must include the signed certification for each lot, with the DOD coordinator’s
signature of acceptance, for each invoice submitted to GPO. Lots will be determined after award, with agreement
between the DOD, GPO, and the contractor.
CONTRACTOR’S INVOICE FOR PAYMENT MUST BE ITEMIZED IN ACCORDANCE WITH THE
SCHEDULE OF PRICES.
GOVERNMENT IN-PLANT INSPECTIONS: The Government reserves the right to have Government
representative(s) inspect any operation under this contract at the start of its production and at any time during
production. In addition to the inspections indicated, the Government reserves the right to inspect all stages of
production.
TITLE: Document Scanning (St Paul Project)
PRODUCT: These specifications cover scanning of five individual collections. A total of 98 boxes to be picked
up from two different locations, approximately 258,000 total documents (86 boxes) of documents to be scanned
and 1 box of Microfiche to be digitalized. 12 boxes, approximately 36,000 documents, to be shredded ONLY.
Boxes are standard banker boxes (10” H x 12” W x 15” D). More information on collection below. Award will be
based on scanning documents into multi-page-PDF files, and an estimated total of 258,000 originals.
QUANTITY: Approximately 258,000 Originals, 86 boxes to be scanned/ digitalized. Approximately 36,000
Originals, 12 boxes to be shredded ONLY.
DESCRIPTION: PREDOMINANT PRODUCTION FUNCTION: Scanning Services (NO PRINTING
REQUIRED).
Page 4 of 9
Jacket 741-835
SCOPE: This statement of work is for digitization for approximately 258,000 sheets/ Microfiches, 86 boxes of
paper copy records and Microfiche. Along with only shredding 12 boxes of paper copy records.
Contractor will be required to separate each page for scanning. Contractor may disassemble and unbind to
scan the furnished document to get it ready for scanning.
Contractor must exercise reasonable care to ensure that the integrity of the material is preserved. Where
materials are stapled, or otherwise fastened or bound, care must be used in taking the materials apart to
ensure that part of the document is not obliterated or that the authenticity of the document becomes
questionable.
The contractor will be required to inspect all documents to determine their suitability for scanning. If
contractor determines that any document is unsuitable, contractor to contact Publishing Specialist at
Jhandziak@gpo.gov.
CHAIN OF CUSTODY: Chain of custody must be maintained at all times on ALL collections. Documentation
may be requested at any time to verify this. Procedures needed for ALL collections handing material are use of
transfer of custody form and tamper-proof seal on truck. No special procedures are needed during production.
PICKUP LOCATION:
The vendor will be escorted at all times while in the Government facility.
Pickup boxes with original contents at two different locations:
49 boxes to be picked up at the district office in St Paul MN (332 Minnesota St., Suite E1500, St. Paul, MN
55101)
49 boxes to be picked up at the field office location in Hayward, WI (10637 Hayward Court Unit 2 Hayward, WI
54843 phone: 651-290-5883
Collection: St. Paul Project
QUANTITY: Approximately 258,000 sheets, 86 boxes.
TRIM SIZE: Material will consist of 4x6” to Oversized documents (over 11x17”) sheets, CD’s, and Microfiche.
See products to be scanned for breakdown.
PRODUCTS TO BE SCANNED: Hard copy original documents furnished in 86 storage boxes. 85 boxes
contain paper documents and 1 box contains microfiche. Documents will consist of but not limited to single-sided
documents, double-sided documents, black only, color, grayscale, handwritten, laser print, Line-work,
photocopies, text, typewritten, colored paper and plain white paper. Documents range from 2-sided GBC bound
documents, envelopes, forms (8.5 x 11”), half pages, maps, Non-standard sizes (not 8.5 x 11 or 8.5 x 14) sheets,
Oversized documents (any document over 11 x 17”), photos, paper clipped documents and stapled documents.
Documents in this collection are in good quality and poor quality along with containing frayed edges throughout.
CD’s possible throughout collection. All CD’s to be transferred/digitized suitable to media content. Documents to
be converted to PDFs and photos are to be left in original format if readable. If photos are not in a readable, they
are to be converted to a suitable file format.
Descriptions for paper records:
64% No Intervention: Furnished source materials are ready to be inserted into an automatic document scanner,
requiring no deconstruction. For example: loose leaf documents that are all one standard size (8-1/2 x 11, 8-1/2 x
14, or 11 x 17).
Page 5 of 9
Jacket 741-835
20% Light Intervention: Furnished source materials require slight deconstruction before being inserted into an
automatic document scanner. For example: all one standard size documents that are rolled, stapled or paper
clipped.
10% Medium Intervention: Furnished source materials require moderate deconstruction before being inserted into
an automatic document scanner and consists of light intervention. For example: documents of various standard
sizes and may include folder tabs and/or tab dividers, sticky notes to be removed and replaced.
5% Heavy Intervention: Furnished source materials require difficult deconstruction before being inserted into an
automatic document scanner and consists of light and/or medium intervention. For example: documents of various
standard sizes and may include folded, torn, or stuck-together pages.
1% Glass Work: Defined as copies made from originals that can only be scanned manually on the scanner glass
and may include but not limited to, receipts, half-pages, envelopes, onion skin, or thermal facsimile paper, odd-
size originals, checks, permanently bound books, two-sided spiral bound, computer forms that cannot
automatically feed, and extremely poor quality originals that require extensive handling and analysis on a page-
by-page basis.
- The contractor is to prepare all documents for scanning (i.e. removing staples, paper clips, rubber bands and
other binding methods).
- Documents do not need to be reassembled
- Books can be cut apart
- Color Mode to be CMYK
- Image clean up required _ Deskew (Image Straightened), Despeckle (Remove spots/Dirt), Image Cropping
(Excess border removed)
- OCR IS required
- Metadata requirements: NOT Required
- Bates numbering requirements: NOT Required
- Naming Convention: Save each project as MVP-year-project #, i.e. "MVP-2022-12345"
- Section 508 accessibility requirements: NOT required
-Files NOT to be compressed to reduce file size
DELIVERABLE: Contractor to provide Multiple page PDFs of files within each box.
The documents do not need to be re-stapled or re-bound, but the order needs to remain intact.
Contractor to store ALL documents/ 98 boxes (Est. 294,000 documents for 6 months) until the written approval
for has been provided by GPO. Once approval is provided contractor is to dispose of all documents. Documents
are to be reduced to a size that ensures ALL the information is unreadable/unidentifiable. Letter of destruction is
required.
Waste must be destroyed in a manner that it is not possible to recreate the product; i.e. burning, pulping,
shredding, macerating, or other suitable means. If the contractor selects shredding as a means of destruction, it
must be a crosscut shredder with a maximum size of 5/32 x 1-1/2" crosscut particles.
Damaged Microfiche: If the contractor determines that any piece is damaged to the extent that a viable scan
cannot be made, the contractor is required to document the collection name/location and number of the damaged
pieces. All damaged, unscannable pieces shall be recorded on an Excel spreadsheet and submitted to the
customer through the GPO Contract Administrator. The contractor is responsible for maintaining the integrity of
the microfiche as they are furnished by the government. The contractor will be required to inspect all pieces to
determine their suitability for scanning.
STORAGE MEDIA: Contractor to provide two copies of files. Files to be stored/ provided on two identical
contractor supplied portable hard drive suitable for data required.
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.