Z1DA--612A4-19-016 | Renovate Outpatient Pharmacy and HVAC
| Location: |
Federal |
| Posted: |
Jul 17, 2026 |
| Due: |
Jul 20, 2026 |
| Agency: |
VETERANS AFFAIRS, DEPARTMENT OF |
| Type of Government: |
Federal |
| Category: |
- Z - Maintenance, Repair or Alteration of Real Property
|
| Solicitation No: |
36C26126R0036 |
| Publication URL: |
To access bid details, please log in. |
Z1DA--612A4-19-016 | Renovate Outpatient Pharmacy and HVAC
Active
Contract Opportunity
Department/Ind. Agency
VETERANS AFFAIRS, DEPARTMENT OF
Sub-tier
VETERANS AFFAIRS, DEPARTMENT OF
Office
261-NETWORK CONTRACT OFFICE 21 (36C261)
Looking for contract opportunity help?
General Information View Changes
-
Contract Opportunity Type: Solicitation (Updated)
-
Updated Published Date: Jul 17, 2026 08:27 am PDT
-
Original Published Date: May 29, 2026 01:32 pm PDT
-
Updated Date Offers Due: Jul 20, 2026 10:00 am PDT
-
Original Date Offers Due: Jun 01, 2026 10:00 am PDT
-
Inactive Policy: Manual
-
Updated Inactive Date: Aug 19, 2026
-
Original Inactive Date:
Jul 31, 2026
-
Initiative:
Classification
-
Original Set Aside:
-
-
Product Service Code: Z1DA - MAINTENANCE OF HOSPITALS AND INFIRMARIES
-
NAICS Code:
-
236220 - Commercial and Institutional Building Construction
-
Place of Performance:
Description View Changes
AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO.
CONTINUATION PAGE 2
SOLICITATION NO:
36C26126R0036
ORDER NO:
AMENDMENT NO:
0005
14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)
The purpose of this amendment is to answer three additional RFIs.
Section 01 00 00 requires the project schedule to include a minimum of forty-five (45) days for VAÂ relocation of Pharmacy Services into the completed temporary facilities, and a minimum of forty-five (45) days for VA relocation of staff, equipment, and operations from the temporary facilities back into Building 650 upon completion of the renovated outpatient pharmacy suite.
Please confirm: (a) whether both 45-day VA relocation periods are included within the 540-calendar-day period of performance; and (b) whether contract completion for purposes of the period of performance is measured at Government acceptance of the renovated pharmacy suite, or upon completion of temporary facility removal and complete site restoration following the VA's 45-day relocation back into Building 650.
ANSWER: The 540-calendar-day Contract Time includes both 45-calendar-day VA relocation periods. Contract completion is achieved upon completion of all Contract Work, including removal of the temporary facilities and complete site restoration following the VA's final relocation back into Building 650.
"Construction start date" refers to commencement of on-site construction activities, including temporary facility construction. This requirement applies to construction-phase submittals required to perform the Work and does not include closeout submittals (e.g., O&M manuals, as-built drawings) or finish selections not required before installation.
Section 01 00 00 states: 100% of ALL project submittals shall be approved prior to the construction start date. Please clarify whether construction start date refers to (a) commencement of temporary facility construction, or (b) commencement of renovation work within Building 650. Please also confirm whether closeout-phase submittals (e.g., O&M manuals, as-built drawings) and late-phase finish material submittals are included in this requirement, or whether it applies to construction-phase submittals only. GLBA appreciates the Government's attention to these questions and remains available for any clarification needed.
ANSWER: "Construction start date" refers to commencement of on-site construction activities, including temporary facility construction. This requirement applies to construction-phase submittals required to perform the Work and does not include closeout submittals (e.g., O&M manuals, as-built drawings) or finish selections not required before installation.
One of our drywall trade partners has brought up a conflict they have found on the existing walls at the perimeter of the pharmacy. Per wall type Mbb3 on Sheet A-501 at the corridor it appears that the framing is existing and one new layer of board, the security mesh fire safing and a closure angle is required to be installed. How we would install the 3 slip track at an existing wall? Are they to be cut between the existing studs and fastened to the bottom of the roof deck? Please advise if the slip track is needed.
ANSWER: Install the head-of-wall/slip-track assembly at the existing wall by attaching the slip track to the structure above as required to maintain the specified assembly. Existing studs are not required to be removed or modified except as necessary to complete the installation.
///////////////////////////////////////////////LAST ITEM//////////////////////////////////////////////////
Attachments/Links
Contact Information
Contracting Office Address
-
10535 HOSPITAL WAY
-
MATHER , CA 95655
-
USA
Secondary Point of Contact
History
Daily notification on new contract opportunities
With GovernmentContracts, you can:
- Find more opportunities and win more business
- Receive daily alerts for all new bid opportunities
- Get contract opportunities matched to your business
ONE WEEK FREE TRIAL
See also
...Security System (ESS) to Include Access Control System (ACS) and Closed Circuit Television ...
DEPT OF DEFENSE
Bid Due: 8/10/2026
...is a healthcare scheduling platform designed for hospitals and healthcare systems to manage ...
VETERANS AFFAIRS, DEPARTMENT OF
Bid Due: 7/22/2026
* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.