INCORPORATED COUNTY OF LOS ALAMOS
BID AND SPECIFICATIONS
Los Alamos Canyon Fiber Optic Extension
INVITATION FOR BIDS NO. IFB25-33
Funding Source NMED CPB DW-6368
Advertised on January 12th,2025 in the Albuquerque Journal
Prepared by:
______________________________________
Sam Herceg, Engineering Associate
Reviewed by:
______________________________________
James Alarid, Deputy Utilities Manager
Authorized for release by:
________________________________
Philo S. Shelton, III P.E., Utilities Manager
The County of Los Alamos is an Equal Opportunity Employer
IFB25-33
Incorporated County of Los Alamos
Los Alamos Canyon Fiber Optic Extension
This page intentionally left blank.
2
IFB25-33
Incorporated County of Los Alamos
Los Alamos Canyon Fiber Optic Extension
1.0 BIDDING PHASE ......................................................................................................................... 6
1.1 Invitation for Bids...................................................................................................................................... 6
1.2 Summary of Work ..................................................................................................................................... 9
1.3 Requirements for Bidders ....................................................................................................................... 10
1.3.1 Bid Evaluation Criteria................................................................................................................................10
1.3.2 Required Bid Response Documents ...........................................................................................................10
1.3.3 The Bidder’s Bid Response Documents......................................................................................................10
1.3.4 Liquidated Damages for Failure to Enter into Contract .............................................................................11
1.3.5 Conditions of Work ....................................................................................................................................11
1.3.6 Addenda and Requests for Interpretation .................................................................................................11
1.3.7 Power of Attorney......................................................................................................................................12
1.3.8 Obligation of Bidder ...................................................................................................................................12
1.3.9 Safety Standards and Accident Prevention ................................................................................................12
1.3.10 Substitutes or Brand Name or Equal......................................................................................................13
1.3.11 Bids to Remain Subject to Acceptance ..................................................................................................13
1.3.12 Withdrawal of Bids ................................................................................................................................13
1.3.13 Acceptance or Rejection of Bids ............................................................................................................13
1.3.14 Award.....................................................................................................................................................13
1.3.15 Registration of Contractors and Subcontractors ...................................................................................14
1.3.16 Procurement Preferences......................................................................................................................14
1.4 Notices to Contractors............................................................................................................................. 15
1.41 Applicable Law ...........................................................................................................................................15
1.4.2 Gross Receipts Tax .....................................................................................................................................15
1.4.3 Minimum Wage Rates................................................................................................................................15
1.4.4 Work Conditions.........................................................................................................................................15
1.4.5 Public Information......................................................................................................................................15
1.5 Bid Forms ................................................................................................................................................ 17
1.5.1 Bid Form .....................................................................................................................................................19
1.5.2 Alternates and Allowances.........................................................................................................................20
1.5.3 List of Subcontractors ................................................................................................................................22
1.5.4 Bid Bond .....................................................................................................................................................23
1.5.5 Campaign Contribution Form.....................................................................................................................25
1.5.6 Certification - Debarment, Suspension, and other Responsibility Matters ...............................................27
1.5.7 Permanent Main Office Address of Company............................................................................................29
1.5.8 Authorization for Verification of Information ............................................................................................29
1.5.9 Certificate of Contractors Registration .....................................................................................................30
2.0 AWARD PHASE ......................................................................................................................... 31
2.1 Award Forms........................................................................................................................................... 31
2.1.1 Notice of Award .........................................................................................................................................31
3
IFB25-33
Incorporated County of Los Alamos
Los Alamos Canyon Fiber Optic Extension
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
Receipt of Notice of Award ........................................................................................................................33
Performance Bond .....................................................................................................................................34
Payment (Labor and Materials) Bond ........................................................................................................36
Insurance Requirement..............................................................................................................................38
Contract ...................................................................................................................................................... 40
3.0 CONSTRUCTION PHASE ......................................................................................................... 47
3.1 Construction Phase Related Forms .......................................................................................................... 47
3.1.1 Contractor Personnel Information .............................................................................................................47
3.1.2 Notice to Proceed ......................................................................................................................................48
3.1.3 Acceptance of Notice to Proceed...............................................................................................................49
3.1.4 Application and Certification for Payment Part 1 ......................................................................................50
3.1.5 Application and Certification for Payment Part 2 ......................................................................................51
3.1.6 Affidavit of Payment and Release of Liens.................................................................................................52
3.1.7 Field Order .................................................................................................................................................54
3.1.8 Change Order .............................................................................................................................................55
3.2 Conditions of the Contract - General Conditions ..................................................................................... 60
3.2.1 Definitions ..................................................................................................................................................60
3.2.2 Additional Instructions...............................................................................................................................63
3.2.3 Schedules, Reports and Records ................................................................................................................65
3.2.4 Shop Drawings and Submittals...................................................................................................................67
3.2.5 Start of Various Types of Work and Management Planning ......................................................................68
3.2.6 Materials, Services and Facilities ...............................................................................................................69
3.2.7 Substitutes or “Brand Name” or Equal.......................................................................................................70
3.2.8 Inspection and Testing ...............................................................................................................................72
3.2.9 Correction of Work.....................................................................................................................................73
3.2.10 Patents ...................................................................................................................................................74
3.2.11 Surveys, Permits, and Regulations.........................................................................................................74
3.2.12 Subsurface and Physical Conditions ......................................................................................................76
3.2.13 Protection of Work, Property and Persons............................................................................................78
3.2.14 Changes in the Work..............................................................................................................................79
3.2.15 Suspension, Delay or Termination of Work ...........................................................................................82
3.2.16 Subcontracting.......................................................................................................................................84
3.2.17 Duties of the Contractor ........................................................................................................................84
3.2.18 Job Site Administration..........................................................................................................................85
3.2.19 Engineer’s Authority ..............................................................................................................................89
3.2.20 Duties, Responsibilities and Limitations ................................................................................................90
3.2.21 Engineer’s Review of Work, Rejection of Work, Inspections, and Tests................................................90
3.2.22 Limitations of Authority.........................................................................................................................90
3.2.23 Land and Right-of-Way ..........................................................................................................................91
3.2.24 Warranty/Guaranty ...............................................................................................................................91
3.2.25 Miscellaneous ........................................................................................................................................92
3.2.26 Dispute Resolution, Applicable Law, and Venue ...................................................................................93
4
IFB25-33
Incorporated County of Los Alamos
Los Alamos Canyon Fiber Optic Extension
3.2.27
3.2.28
3.2.29
3.2.30
Examination of Records Provisions........................................................................................................93
American with Disabilities Act Compliance ...........................................................................................93
A. Bids and Proposals are public Records .............................................................................................93
Wage Rate Determination .....................................................................................................................94
3.3 ATTACHMENTS ........................................................................................................................ 95
3.3.1 License Agreement for Staging Area ..........................................................................................................96
3.3.2 Wage Rate Information..............................................................................................................................99
3.4 TECHNICAL SPECIFICATIONS ............................................................................................... 121
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.