University Davis Building
Septic System
Replacement
Solicitation
July 16, 2026
UNDS Septic System Replacement
TABLE OF CONTENTS
July 16, 2026
I.
SOLICITATION .................................................................................................................................... 3
II.
PROJECT OVERVIEW .......................................................................................................................... 3
III. SCOPE OF WORK................................................................................................................................ 4
IV. SCHEDULE ......................................................................................................................................... 5
V.
WORK CONSIDERATIONS/RESTRICTIONS ............................................................................................ 6
VI. ALASKA NATIVE OR AMERICAN INDIAN (AN/AI) REQUIREMENTS......................................................... 7
VII. BID SUBMISSION REQUIREMENTS ...................................................................................................... 7
VIII. BID EVALUATION ............................................................................................................................... 8
IX. TERMS AND CONDITIONS................................................................................................................... 8
X.
APPENDICES ...................................................................................................................................... 9
• APPENDIX A - Bid Form
• APPENDIX B - Drawings & Supporting Documents
• APPENDIX C - TCC Example Construction Short Form Contract
2
UNDS Septic System Replacement
July 16, 2026
I. Solicitation
Tanana Chiefs Conference (TCC) is soliciting bids from qualified contractors for the replacement of the septic
system for the University Davis Building located at 2175 University Ave, Fairbanks, AK 99709.
Registration/Questions: Each Proposer must register by 5:00 p.m. on July 21, 2026 to submit written questions
and receive addenda notifications. To register, please send an email to Project Managers, Daren Schlotfeldt
(Daren.Schlotfeldt@tananachiefs.org) and Tim Troppmann (Timothy.Troppmann@tananachiefs.org). Include firm
name, address, telephone, email address, and name of contact person. A sample contract will be sent to those
that register.
Minimum Contractor Qualifications: To be eligible to submit a bid for this project, Contractor is required to
demonstrate they have a minimum of three years’ construction experience and have completed at least three
projects of similar size and scope.
Written Questions and Addenda Publication: All questions must be submitted in writing to
Daren.Schlotfeldt@tananachiefs.org and Timothy.Troppmann@tananachiefs.org on or before July 23, 2026 by
5:00 PM Alaska Time (AKT).
Bid Submission Deadline: Bids must be received by email no later than July 30, 2026, 2:00 PM (AKT), sent to
Daren.Schlotfeldt@tananachiefs.org and Timothy.Troppmann@tananachiefs.org. Bids received after the time
announced will not be considered, unless otherwise determined by TCC.
Additional bid submission details:
• Only emailed electronic bids will be accepted - recommend setting a delivery and read receipt
• Bids will not be opened publicly
• Faxed bids will not be accepted
II. Project Overview
Tanana Chiefs Conference is a non-profit Tribal Organization who provides health services, education, training,
and work force development opportunities to more than 10,000 Alaska Natives located in 42 Villages throughout
Interior Alaska.
Project Team:
Owner:
Tanana Chiefs Conference
Project Manager:
Daren Schlotfeldt (Daren.Schlotfeldt@tananachiefs.org)
Tim Troppmann (Timothy.Troppmann@tananachiefs.org)
Designer:
AK Built Construction & Design
Project Delivery
Method:
Design-Bid-Build
3
UNDS Septic System Replacement
July 16, 2026
III. Scope of Work
Each bidder shall thoroughly examine the work area and be familiar with the contract documents. The failure or
neglect of a bidder to receive or examine any contract document or any part thereof shall in no way relieve it from
any obligations with respect to its Bid or to the contract. No claim for additional compensation shall be allowed
which is based upon a lack of knowledge of any contract document.
The scope of work includes the following activities:
A. Demolition: Reference Appendix B for site specific drawings.
a. Remove and dispose of existing 2,500 gallon septic tank.
b. Remove and stockpile landscape rock for reinstallation.
c. Where proposed SAS overlaps existing SAS, over excavate a minimum of two feet beyond
proposed SAS limits. Backfill over excavation with classified fill.
d. Remove existing AC pavement to property line.
B. Soil Conditions
a. A test hole will be excavated to collect soil, percolation, and ground water data for the
designed system.
b. Should site conditions differ from the assumed conditions used for design, contractor shall
document conditions and contact TCC project manager to confirm alternative action and
means for financial compensation.
C. New Construction: Reference Appendix B for site specific drawings.
a. Install foundation clean out.
b. Install 2,500 gallon septic tank.
c. Install double clean out.
d. Install 24’ W X 90’ L bed SAS.
e. Reinstall riprap landscape.
f. Repave parking lot.
4
UNDS Septic System Replacement
July 16, 2026
g. Topsoil and seed remaining disturbed area.
D. Inspections
a. A substantial completion inspection shall be performed by TCC. One-week minimum notice
is to be provided prior to requesting inspection.
E. Work Plan & Schedule: Immediately after the Notice of Intent to Award, the Contractor is responsible
for developing and submitting a formal Work Plan & Schedule based on procurement of the required
materials and phasing of the project. Contractor shall also submit for approval, product data for all
products incorporated into the work. The Work Plan & Schedule will be used by TCC to notify building
users of upcoming activities and coordination. The Contractor will provide 3-week look ahead
schedule and update the document during construction activities. The Work Plan & Schedule shall be
submitted to TCC for review within 7 working days of the NOITA. Email to TCC Project Manager is an
acceptable method of submitting work plan, schedule, and product data.
a. Work Plan will be reviewed by TCC to coordinate any projects that may be in vicinity of work.
b. Contractor shall plan for and schedule the portion of work associated with the service of the
buildings waste line to be completed after hours and/or weekends to ensure no disruption to
the buildings occupants. The buildings domestic waste service must remain operational
during normal business hours for the duration of the project.
c. TCC intends to cancel any current routine septic pumping services at project start date and
any future pumping service required during the course of construction will be the
responsibility of the contractors to coordinate.
F. Close-Out: Contractor will provide as built drawings denoting variation from design, O&M data as
applicable to equipment, and provide any onsite owner training required to operate and maintain the
equipment safely and effectively.
Schedule
Issue Request for Bids to Contractors
Deadline for Questions (5:00 PM AKT)
Receive and Open Bids (2:00 PM AKT)
Issue Notice of Intent to Award (NOITA)
Execute Construction Contract/Notice to Proceed
Substantial Completion
July 16, 2026
July 23, 2026
July 30, 2026
July 31, 2026
August 7, 2026
September 11, 2026
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.