Request for Proposals for Solar Photovoltaic Expansion

Location: Colorado
Posted: Feb 26, 2026
Due: Mar 24, 2026
Agency: Denver Water
Type of Government: State & Local
Category:
  • S - Utilities and Training Services
Publication URL: To access bid details, please log in.
Engineering
Request for Proposals for Solar Photovoltaic Expansion
Contract or Solicitation Number:
N/A
Solicitation Description:

Denver Water is requesting proposals from Design/Builder (Contractor) to design, furnish, and install the Solar Photovoltaic Expansion Project (Project). Project includes ground mounted, behind the meter, solar photovoltaic (PV) system at Denver Water’s Recycling Treatment Plant.

Post Date:
February 26, 2026
Due Date:
March 24, 2026
Solicitation Documents:
Solar RFP_Recycle Treatment Plant_Final.pdf

Attachment Preview

Solar Photovoltaic Expansion at DW Recycling Treatment Plant
REQUEST FOR PROPOSALS (RFP)
Submission Deadline: 2:00 pm (MT), March 24, 2026
Section 1 – Introduction and Background
Project Description
Denver Water is requesting proposals from Design/Builder (Contractor) to design, furnish, and install the
Solar Photovoltaic Expansion Project (Project). Project includes a ground mounted, behind the meter,
solar photovoltaic (PV) system at Denver Water’s Recycling Treatment Plant. The intent of the contract is
to maximize the tax credits that can be gained by commencing a solar array installation by July 4, 2026,
or installing and commissioning a complete solar installation by December 31, 2027, as laid out in IRS
Notice 2025-42.
Background and History
To reach the goal of net-zero carbon emissions by 2030, the Board directed staff to identify and
implement internal sustainability goals and commitments to support reaching net-zero carbon and avoid
adding new sources of carbon emissions to the extent feasible.
The Board further directed staff to complete a study of its property and facilities to identify opportunities to
produce renewable energy, offsetting the use of utility power and increasing resiliency of operations to
disruptions of the electrical grid.
On October 1, 2024, Denver Water contracted with Baker Tilly to perform the following evaluations:
1. Assess Denver Water’s current renewable energy assets, facilities, and land assets.
2. Identify potential improvements, changes, and additions to renewable energy generating
capacity.
3. Develop a strategy to effectively mark the current and potential new energy produced by
Denver Water through one or more agreements/partnerships or participation in wholesale
markets.
4. Advise Denver Water through completion of the process to secure one or more buyers for its
current and potential renewable energy portfolios.
Baker Tilly completed an assessment of current renewable energy assets and land assets as well as the
completion of improvements, changes, and additions to renewable generation recommendations. Baker
Tilly recommended focusing on distributed solar generation upgrades at 14 high and medium ranked
Denver Water project sites. Denver Water is proceeding with implementing solar arrays at four (4) of our
Pump Stations and now are planning to design, furnish, and install solar arrays at the Recycling
Treatment Plant Site.
Location
Recycling Water
Treatment Plant
Address
5650 York Street
Commerce City, CO 80022
Estimated
Size (KW)
3,000
Estimated Annual
Generation [kWh/yr]
4,800,000
Preliminary individual site design development for the site above can be shared with the Contractors after
application and approval to the Security Prequalified Contractor/Consultant List.
Page 2 of 21
Project Objectives
The following specific project objectives have been identified:
Design-Build the installation for turnkey, ground mounted, PV system within the project budget
and timeframe
Installation of PV systems within the project timeframe
Provide a web-based condition and performance monitoring system
Obtain the highest net-present value of energy savings
Achieve the highest cumulative energy savings
Design, procure, install, and commission commercial grade, high efficiency PV systems
Provide reliable PV systems with low-cost, long-term replacement and maintenance including
disposal
Provide Denver Water with the lowest energy cost
Partner with experienced, innovative, and financially stable vendors
Minimize impact on Denver Water operations at prioritized locations
Reduce the cost of energy by utilizing all available financial incentives (utility or otherwise)
Section 2 – Project Overview
Scope of Services
Design, furnish, and install a turnkey, ground mounted, solar PV system at Denver Water’s Recycling
Water Treatment Plant within the outlined schedule and budget. The solar PV systems will offset
approximately 100-110% of annual site electrical usage, which can be shared once the Contractor meets
the requirements of the Security Prequalified Contractor List (SPCL), as outlined in Section 8.
Project Assumptions
The following assumptions were made in the Scope of Work development:
Contractor to provide all construction drawings, equipment, materials, labor, permitting, utility
coordination, as-builts, and commissioning necessary to install fully functional PV systems at the
listed site, within the agreed upon project cost over a 2-year period (2026 through 2027).
A gate is a term used to reference a formal document; it is also the process used to acknowledge
project decisions. A gate is designed to acknowledge the approval of its related topic by project
stakeholders. In addition, a gate is a means to document decisions made that are critical to the
progress of the design beyond the current milestone/phase. Once the gate is closed, changes
cannot be made to the design deliverable nor data transferred without approval from Denver
Water and the Contractor Project Managers. If changes are identified, those changes are to be
logged and addressed in accordance with an approved change management process. Design
gates will meet the requirements of Denver Water’s Capital Projects Procedures Manual (CPPM)
at a minimum. Denver Water’s CPPM can be accessed for free at this address:
https://www.denverwater.org/contractors/construction-information/design-standards/capital-
projects-procedures-manual
Early procurement, equipment storage, and handling will be Contractor responsibility.
All project-related deliverables will be distributed collaboratively through a Denver Water
established, project-specific SharePoint site, with all final copies of documentation versioned and
archived within ProjectWise.
Site is free of any sensitive cultural resources that require environmental clearance or other
required permitting at the local, state, or federal level. Although unlikely, if unanticipated buried
historic or archaeological materials are identified, Denver Water’s Environmental Planning team
will be notified to implement an unanticipated discoveries plan.
Page 3 of 21
Site location is in urban, disturbed, and upland areas. However, in the event protected wildlife
presence is found, Contractor is responsible for providing construction clearance of protected
wildlife in compliance with authorities having jurisdiction.
In the event unknown historic waste is encountered during construction, Contractor will alert
Denver Water Construction Project Manager to determine the need for an assessment of
materials. Denver Water Environmental Compliance team may need to be alerted as well.
The Contractor shall develop all necessary supporting documentation and submit applications to
authorities having jurisdiction for permits, approvals, and reviews prior to construction.
The location being considered in the RFP is a secured/highly secured operating facility.
Coordination of Contractor’s work with Denver Water is critical to ensure minimal disruption to
Denver Water operations and any concurrent facility maintenance work.
The Contractor is responsible for all coordination with utilities and authorities having jurisdiction.
A sample of the Contract is provided with the RFP. The selected Contractor will be expected to
sign and execute a similar version of this Contract.
Upon completion of the site solar PV system, a site-specific service agreement will be negotiated
and signed. Proposal to include a sample standard service agreement including costs to be
evaluated as part of this RFP.
The site shall be photo and video documented for existing site conditions prior to construction
start.
The Contractor shall add an additional feeder section to SWGR1 to serve as a dedicated feeder
for the PV system OR the Contractor is restricted to the 13.2kV infrastructure when determining
an interconnection point.
o In an interconnection point is identified that is within an existing differential zone of
protection, then CT and PT provisions must be furnished on the PV feed and brought
back to the summing bus of the differential.
Solar PV System Minimum Design Requirements:
o 20% safety factor:
PV system sizes shall be based on Normal Module Operating Temperature
(NMOT) panel rating with an additional 20% higher than the average annual site
loads to account for operational/modeling unknowns.
Contractors to provide stand alone cost for an additional 15% safety factor –
provide as a unit price ($/MWh).
o Panel Performance Requirements:
Solar panels shall have minimum module efficiency of 20%.
PV systems shall be provided with minimum 25-year Linear Power Warranty not
exceeding 0.5% annual degradation.
o One-line diagrams are indications of current state of site electrical equipment. Actual
electrical service requirements to install a fully functional PV system, with all necessary
electrical equipment and appurtenances, shall be communicated in the RFP response.
o Contractors to specify the types, quantities and proposed location of inverters,
transformers, electrical panels, and any other required supplemental equipment
necessary for the proposed Project sites. Inverter sizing shall be adequate so as not to
cut off panel generation during peak outputs. Assume the use of string inverters for this
proposal. If a micro inverter system is preferred, provide an additional quote showing the
difference in price including details of any additional benefits to installing such a system.
o Rolling metering or independent feed metering of the PV system generation and site
electrical consumption with Proposal to include independent feed metering with monthly
net metering. Denver Water has interest in independent feed metering to facilitate
generation during a facility outage.
Page 4 of 21
o Racking systems will maintain a minimum of 3 feet clearance of natural vegetative growth
to bottom of panels and adequate spacing between array arrangements to rider mow
native grass bi-annually. Racking systems for exposed concrete tank structures do not
require a ground to panel clearance requirement. Solar panels on tank structures shall
assume 3 feet free and clear space all the way around man access hatches, electric
valve operators, and jib crane mounts.
o Any disturbed or damaged native grass areas, irrigation, or other existing onsite assets
will require repair to like new condition. All native areas outside of the extent of the solar
arrays shall be returned to pre-construction conditions adhering to Section 31 01 01
identified in Exhibit D – Project Specific Technical Specifications.
Codes and Standards
o All products and components outlined herein must conform to the following codes,
standards, and rating methodologies:
If PV modules using hazardous materials (i.e. Cadmium or other hazardous
materials) are included in the RFP, the environmental impact of the hazardous
material usage must be discussed, including any special maintenance
requirements and proper disposal/recycling of the modules at the end of their
useful life. Modules containing hazardous materials must comply with the EPA
Landfill Disposal Requirements. Any additional costs related to PV modules
containing hazardous materials must be clearly identified.
Follow most current requirements of codes governing installations, including but
not limited to:
UL certification
National Electrical Code
IBC including authorities having jurisdiction amendments
All outdoor enclosures should be at minimum rated NEMA 3R
Occupational Health and Safety Administration (OSHA) directives
Must comply with IBC wind uplift requirements and the American Society
of Civil Engineers Standard for Minimum Design Loads for Buildings and
Other Structures (ASCE 7)
Monitoring System
o Denver Water must have access to system performance monitoring and historical data
via secure website. Denver Water will provide business network access via ethernet
connections.
o Monitoring System shall report energy generation back to user dashboards and general
metering tracking. Data must include:
Production analytics
Power generation
Predicted power
Irradiance vs. kW
PV string level monitoring
Plant alerts, reporting, fault codes, performance, and weather (ambient
temperature, wind speed, etc.)
Insulation
o Monitoring System should be Building Automation System [BAS] compatible with TCP/IP
protocol, Monitoring System may be able to read items like ambient temperature from a
BAS.
Page 5 of 21
Section 3 – Contractor Qualifications
Contractors to submit the following company qualifications and shall be limited to no more than 4 pages:
Organization Information:
Company Profile:
o Year founded
o Private or Publicly Held
o Number of employees
o States and countries in which you do business
o Target customers (residential, commercial, industrial, governmental, etc.)
o Organization participation in Green Programs and surrounding communities beyond their
engineering, procurement, and construction work.
Green E certification status, as applies (See: http://www.green-e.org)
Financial Strength & Payment Bonding Capacity:
o If public, provide a link to investor reports. If private, attach audited financial statements
from 2025/2024.
o Provide firm’s bonding capacity.
Project Team:
o Provide team leader identification for the entire proposal, including full contact
information.
o Identify each business entity, person, or firm involved in the proposal and their role, e.g.
design, installation, permitting, equipment supply by component, operations and
maintenance.
o Identify any portion of work that will be performed by subcontractors.
o Provide resumes of personnel that will be directly involved with the development, project
manager, construction, and commissioning of the proposed systems.
Quality:
o Describe company’s (or each firm’s) quality assurance processes.
o Describe customer satisfaction processes, if any.
Safety Record:
o List firm’s Experience Modification Rate (EMR) for each of the past three premium years.
Insurance:
o Provide a sample insurance certificate indicating compliance with insurance
requirements.
Legal:
o Has the firm or any of the executive officers of the firm been a party to a lawsuit involving
the performance of any equipment it has installed? If so, please include a summary of the
issues and the status of the lawsuit.
Solar Project Experience:
Overview:
o Demonstrate technical experience and capability to design, construct, and manage large-
scale grid-connected PV projects in the U.S. If a project team, identify the firm with the
experience.
o Demonstrate interconnection experience and capabilities.
o Overview of company’s non-residential grid-connected PV systems installed (not in
development):
Total kWdc installed
Total kWdc installed in the last three years
Number of ground mounted systems installed since 2011
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...refrigerator featuring an automatic electric ignition system. Power System: Minimum 100W roof-mounted... solar ...

DEPT OF DEFENSE

Bid Due: 6/09/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.