2. Scope of Work
The selected contractor shall be responsible for the following:
Demolition and Removal:
Remove and properly dispose of the existing sidewalk.
Remove and properly dispose of the existing flower beds at the front entrance.
Prepare the foundation for new concrete installation.
Concrete Sidewalk Installation:
Install a new 6-inch thick, 4-foot-wide concrete sidewalk totaling 140 linear meters.
Ensure the new sidewalk is properly pinned to the school’s foundation.
Ensure appropriate drainage and grading.
Install six (6) roof drains beneath the sidewalk, each covered with a grate for easy cleaning.
Broom finish for slip resistance
Front Entrance Concrete Replacement:
Install new concrete at the front entrance, covering an area of 51 square meters.
Finishing Work:
Apply color-matching brick or parging where the flower beds were removed.
Ensure all work areas are cleaned and restored to a safe and presentable condition.
Reseed all areas of grass disturbed by the project.
3. Project Timeline
The project is expected to begin on June 30, 2025 and be completed by Aug 8, 2025. Contractors must provide a proposed work schedule with their bid submission.
|