CONSTRUCTION MANAGER AT-RISK
REQUEST FOR PROPOSAL
OWNER:
THE CONFEDERATED TRIBES OF THE COLVILLE RESERVATION
PROJECT:
FIRST FOODS MEAT PROCESSING PLANT
OMAK, WA
ISSUE DATE:
FRIDAY, APRIL 10TH, 2026
PROPOSAL DUE DATE AND TIME:
Proposals shall be submitted no later than:
5:00 PM PST ON WEDNESDAY, APRIL 29, 2026
SUBMIT PROPOSAL TO:
Connect Advisors
Attn: Josie Hohn
Email: jhohn@connect-advisors.com
First Foods Meat Processing Plant CMAR RFP
SECTION 1: GENERAL INFORMATION
1.1 Introduction
The Confederated Tribes of the Colville Reservation (“Owner”) has engaged Connect Advisors
as their Owner’s Representative (“O.R.”) firm for the First Foods Meat Processing Plant
(“Project”). Connect Advisors is seeking proposals from qualified construction management
firms (“Firm”) to provide Construction Management At-Risk (“CMAR”) services to the Owner in
the development and construction of the Project.
All Firms are encouraged to review each section of the following document carefully and
respond promptly to be considered for this project. Owner has the right to reject any Proposals
not properly delivered.
This RFP is not an offer to enter into a contract but is merely a solicitation of entities interested
in submitting a Proposal to the Owner for the Project.
1.2 About the Colville Tribes
The Confederated Tribes of the Colville Reservation is a Sovereign Nation. Presidential
Executive Order established the Colville Indian Reservation in 1872, with a land base of 1.4
million acres, located in North Central Washington State. The Tribes’ Indian Country now
includes various off-reservation trust land holdings. The Tribes’ administrative headquarters
are located at the Colville Indian Agency Campus, approximately 2 miles southeast of
Nespelem, WA with offices located throughout our reservation. Tribal Business hours are
Monday through Thursday, 7:00 am to 5:30 pm, excluding Fridays, Saturdays, Sundays, Tribal
holidays and Federal Holidays.
SECTION 2:SUBMISSION INSTRUCTIONS
2.1 Response Due Date
Proposals must be submitted to the Josie Hohn no later than 5:00 pm, April 29, 2026. All
Proposals and accompanying documents will become property of the Colville Tribes and will
not be returned.
2.2 Required Number of Proposals
Firms must provide one (1) electronic copy of their response by emailing jhohn@connect-
advisors.com. Please use the subject line “First Foods Meat Processing Plant RFP Response”
and label the file “[FIRM NAME] First Foods Meat Processing Plant RFP Response”.
2.3 Response Format
Proposals should be prepared simply, providing a straightforward and concise delineation of
the Firm’s approach and capabilities to satisfy the criteria listed in Section 4. The proposal may
not be longer than 30 pages, letter sized, single spaced, with no less than 12-point font.
Proposals should be clear, complete, and adhere to the structure required by this RFP. Firms
that deviate from the required format may be deemed non-responsive.
First Foods Meat Processing Plant CMAR RFP
2.4 Site Visitation
A site visit is required. The site visit will be held on April 23, 2025, at 10:00 AM. By submitting
a proposal, the CMAR acknowledges that the CMAR is satisfied as to the nature and locations of
the work, and certifies all information required to perform the requirements of this RFP.
2.5 Questions
Questions should be directed to Josie Hohn via email using the email above. Questions will
be taken until seven (7) days prior to the submission date with the final addendum issued
no later than three (3) days prior to submission. Unauthorized contact with other tribal
employees or by any method other than email regarding this RFP may result in
disqualification. All oral communications will be considered unofficial and non-binding on
the Tribes.
SECTION 3: PROJECT INFORMATION
3.1 Project Location
The Project is located Northwest of Mission Road in Omak, WA on land that is being held in
trust for the Owner. An address has yet to be established. Please refer to the architectural and
civil drawings for location.
3.2 Project Description
This project includes the construction of an approximately 18,255 GSF food processing facility
with associated parking, loading areas and exterior improvements. The project will be
composed of a pre-engineered metal building constructed on a concrete foundation. The
building will be a type V, fully sprinklered, facility. The program includes food processing
areas, a production viewing area, offices, meeting space and employee support spaces.
3.3 Scope of Services
3.3.1 The Firm will be responsible for providing CMAR services related to the pre-
construction and construction phases of the Project as identified, but not limited to,
the following:
3.3.2 Preconstruction Activities:
.1 Staffing: The Firm shall provide the proper number of qualified staff members
as necessary to competently and fully manage all Pre-Construction services.
.2 Budgeting: The Firm must work with the Project Team to develop detailed
Project Budgets at the completion of each design phase. This initial budget
shall include sufficient identification and clarification as to the Scope-of-Work
included and specifically excluded by the Firm. Once approved, the budget
shall be regularly updated at each stage, and presented for approval, as the
design continues to develop. The level of detail presented in each budget
update shall continue to increase as the design progresses from the initial
conceptual and programming phase through final 100% contract documents
and a final GMP. Estimates should include quantities and unit prices for each
item of work where applicable.
First Foods Meat Processing Plant CMAR RFP
.3 Value Engineering/Constructability Reviews: The Firm must provide
constructability and value engineering reviews in conjunction with above
budgets. The Firm should review all existing studies and plans to determine
their viability and propose adjustments using the current market and site
information gathered by the Project Team, if needed.
.4 Identification of Any Necessary Design-Assist (or possibly Design-Build) Trades:
Upon thorough evaluation of the project scope, anticipated design services
scheduled to be provided by the Design Team, and other key factors such as the
project schedule, the Firm may provide recommendations for any Design-Assist
or Design-Build trades that are necessary in order to best maintain the project
budget, schedule, and overall quality product.
.5 Project Logistics and Safety: The Firm must work with the Project Team to
determine how ingress/egress plans may impact operations and what
operational needs there may be necessitating specific ingress/egress plans. The
Firm must develop a project specific safety plan to be incorporated into all
bidding documents. The Firm must develop, and submit for approval, a site
logistics plan that will ensure the most appropriate, safe, and efficient means to
managing the constraints of the site, and adjacent to site, throughout the
duration of the construction phase is accomplished.
.6 Scheduling: After the project has been awarded, the Firm shall immediately
draft, present, and gain Owner approval on an overall Master Project Schedule
that fully details the preconstruction process, GMP process, commencing
construction, and all construction activities up through, and to, Final
Completion. This Master Project Schedule shall also adequately identify the
details related to the construction phase, including all key milestones,
completion of separate areas of the Project, and a clear identification of all
project turnover and close-out activities including (in no particular order),
testing, commissioning, punch lists completion, Owner move-in, Owner
occupancy, substantial completion, and final completion. The schedule shall
also identify any necessary long-lead procurement items that warrant specific
attention, timeline identification, and possibly an accelerated release by the
Owner. Once approved, this schedule shall continue to be updated, and
presented for approval, with each progression of the project design and
budget. Prior to entering into a GMP at the conclusion of the preconstruction
phase, the Firm must submit a Master Project Schedule that is fully detailed
with all construction activities that will occur throughout the construction
phase. This schedule shall include proper identification of the “float” for each
scheduled activity.
.7 Meeting Management: The Firm must properly plan, manage, and document
all meetings with the Project Team as necessary to properly complete the CMAR
services.
First Foods Meat Processing Plant CMAR RFP
.8 Reporting: The Firm must provide all reports related to the CMAR services in an
organized and detailed manner to the Project Team
.9 Cash Flow Analysis: The Firm shall provide to the Owner all necessary cash
flow analysis that properly detail and forecast the necessary flow of funds that
will be required through the course of the construction phase.
.10 GMP Delivery: At the agreed to time in the progression of design, the Firm will
proceed with the bidding process to obtain the GMP(s). This includes the
preparation, development and distribution of all bid packages including project
specific general and supplementary conditions items. The Firm will conduct
pre-bid and post-bid meetings with trade contractors to ensure that all bids are
complete and fully responsive. After receiving and analyzing contractor bids,
the Firm will present a detailed GMP proposal and packet (with all associated
back-up and exhibits) to the Owner along with making bid-package award
recommendations.
.11 Code Reviews: The Firm shall identify and make note to the Project Team any
code violations, real or perceived, found in the design documents to the best of
their ability.
.12 Permitting: Coordinate with various departments of the Tribe along with other
agencies, utility companies, etc. as needed to ensure all necessary permits,
coordination, and approvals are in place prior to commencing construction so
as to promote a seamless and efficient management of the construction phase.
.13 Pre-Construction and Design: All Pre-construction activities are to occur
concurrent with the Design Phase. This is to include all items necessary to
provide complete and adequate planning for the construction phase of the
project, as well as items such as long lead procurement management, meeting
coordination (the Firm will be responsible for scheduling, agendas, and
minutes) and various additional items, as necessary.
.14 The Firm is to provide additional CMAR services required by contract, by the
Owner’s Representative, or as necessary to provide appropriate and timely
management of the Project.
3.3.3
Construction Phase Services:
.1 Staffing: The Firm shall provide the proper amount of qualified full-time, on-site
staff to competently manage and ensure full compliance of all aspects of the
Project. This includes staffing throughout the duration of the construction
phase as well as appropriate management throughout all necessary project
close-out activities.
.2 General Conditions: The Firm shall be responsible for performance and
administration of all general conditions on the project.
First Foods Meat Processing Plant CMAR RFP
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.