County of Orange
Finance and Administrative Services Department – Purchasing Division
RFQ No 367-OC5467
Request for Qualifications to Provide Professional Consulting Services for a Transit Access
Sidewalk Along Orange Grove Road
I. Purpose:
Orange County, North Carolina, is releasing this Request for Qualifications (RFQ) seeking
proposals from qualified firms to provide professional engineering services for the Transit
Access Sidewalk along Orange Grove Road Project. The County is seeking firms whose
combination of experience and expertise will provide timely, professional services. The
County reserves the right to enter into one or more contracts with any firm selected under
this RFQ process.
The Project will include design, permitting, bidding and award assistance, and
construction administration services related to the design and construction of a 1.7-mile
Transit Access sidewalk along the northwest side of Orange Grove Road, from the
existing sidewalk near Eflin Blvd in Hillsborough, NC, to the first driveway at Cedar Ridge
High School along Grady Brown School Road, including a prefabricated pedestrian bridge
located west of the Orange Grove Road over I-40 bridge (Bridge #670262).
This project is funded in part with federal funds and is subject to applicable federal
regulations and requirements.
Electronic responses ONLY will be accepted for this solicitation.
Information related to this solicitation, including any addenda, will be posted on the
County’s website at https://www.orangecountync.gov/Bids.aspx. For questions about this
solicitation, contact:
Name: Darlene Weaver
Department/Title: Transportation Planning Manager
Address:606 Hwy86 N, Hillsborough NC, 27278
Phone: 919-245-2002
Emails: dweaver@orangecountync.gov ; finance-purchasing@orangecountync.gov
II. Project Overview and Scope of Work
A. Summary
The awarded contractor shall provide services, all as set forth in this RFQ. The scope of
work will include project management and administration, subsurface utility engineering,
roadway design, construction documents, sidewalk drainage design, erosion control
1|Page
design, Traffic Management plan, pavement marking plan, structure design, Right-of-Way
Services, utility coordination services, Geotechnical services.
Prepare an NCDOT Type I(A) CE form for the transit access sidewalk along Orange Grove
Road to comply with the National Environmental Policy Act (NEPA), NCDOT policies and
procedures for environmental documentation, and other related federal, state, and local laws
and regulations. This project will evaluate the addition of a 6-foot sidewalk on the north/west
side of New Grady Brown School Road from Cedar Ridge High School's first driveway to the
intersection with Orange Grove Road, then heading north on Orange Grove Road
approximately 1 mile to Eflin Boulevard. All ground disturbance and easements are assumed
to be within the project study area as outlined in red below.
B. Deliverables
Project Management
• Project Management Plan (PMP)
• Quality Management Plan (QMP)
• Initial Project Schedule
• Draft and final meeting minutes following meetings.
• Documentation of General Coordination activities
• Files shall be correlated with survey files.
2|Page
Roadway Design
• Design Assumptions Submittal
• Design Assumptions
Typical Sections
Draft Recommendation Plan Set Submittal
• Title Sheet
• Typical Sections Sheets
• Plan Sheets with Horizontal Design
• Profile Sheets with Vertical Design
• Cross Sections
• Preliminary Right of Way and Easement Limits
• Proposed Guardrail Design if required.
• Preliminary Slope Stake lines
• Preliminary Earthwork Summary
• Preliminary Construction Cost Estimate
Preliminary 65% Submittal
• Approved Draft Recommendation Plan Set
• Proposed Right-of-Way and Easements
• Cross sections
• Updated Preliminary Construction Cost Estimate
Right of Way Plans
• Proposed Right-of-Way Plans (Right of Way Acquisition and Utility
Coordination Services Needed)
90% Submittal
• Approved Right-of-Way Plans
• Cross sections
• Estimated Construction Quantities
• Engineer's Construction Cost Estimate
100% Submittal (Final)
• Approved 90% Plans
• Cross sections
• Estimated Construction Quantities
• Engineer's Construction Cost Estimate
Final Sealed Plans and Bid Document Submittal
• Approved 100% Plans
• Estimated Construction Quantities
• Engineer's Construction Cost Estimate
Bid Construction Document
• Engineer’s Estimate
• Lead pre-bid meeting, prepare agenda, and provide meeting
minutes.
• Address up to 3 Addenda
• Lead public bid opening, review bids, prepare
certified bid tabulation, and provide
recommendation for award.
Roadway Design
Preliminary 60% Plan Submittal
• Drainage Design
• Preliminary Erosion and Sediment Control Design
3|Page
90% Plans Submittal
• Drainage Summary Sheet & Quantities
• Erosion Control Plans to North Carolina Department of Environmental
Quality (NCDEQ)
Final Sealed Plans Submittal
• Approved Erosion and Sediment Control Plans (Hydraulics)
Traffic Management and Pavement Marking Plans
• Preliminary 65% Submittal
• Staging Concept Traffic Control Phasing Notes
• 90% Submittal Traffic Control Phasing Notes
• 100% Submittal (Final)
• 100% Traffic Control Phasing Notes
• Final Sealed Plans Submittal
• Final Traffic Control Phasing Notes
• Final Pavement Marking Plans
Structure Plans
• 30% Preliminary Geotechnical Design (PGD) Plans
• 100% Stamped Plans and Specifications
Right of Way Services
• Property valuation claim report
• Final Reports on each property claim
Utility Coordination
• Utility kick-off meeting coordination
• Utility meeting minutes
• Utility relocation schedule
• Special provisions
• Utility packages
• Utility By Others (UBO) (I)
Geotechnical Services
• Foundation Recommendations Report
• National Environmental Policy Act (NEPA)
• NCDOT Type I(A) Categorical Exclusion (CE) Form (draft and final)
• Project Initiation Letter and Mailing List (draft and final)
• Landowner Notification Letter
• Design Initiation Scoping Tool (DIST) (draft and final)
• Preliminary Jurisdictional Determination/Approved Jurisdictional
Determination (PJD/AJD)Package
• Natural Resources Technical Report (NRTR) (draft and final)
4|Page
• Complete Streets Review Assessment and Complete Streets Project
Sheet
III. RFQ Schedule of Events and SOQ:
Advertisement of RFQ:367-OC5467
Deadline for Questions:
Deadline for Answers:
DUE DATE & TIME FOR SOQs
Contract Effective Date
November 18, 2025
December 1, 2025
December 8, 2025
December 15, 2025, 2:00PM
TBD
IV. Statement of Qualification Submittal:
Firms must submit one electronic Statement of Qualification (SOQ) to Jovana Amaro,
Purchasing Manager at finance-purchasing@orangecountync.gov prior to the due date
and time for SOQ submissions. Each proposer is solely responsible for the delivery of SOQ
and accepts all risks of late delivery regardless of fault. In addition, offerors accept all risks
if the file is corrupted, incorrect, incomplete, or not attached. Any SOQ received after the
submission deadline shall not be considered.
Proposals must be submitted by December 15th, no later than 2:00 PM as detailed above.
Firms should enter “Firm’s Name-RFQ 367-OC5467” as the subject for the email.
All submittal components must be provided in a single PDF file transmitted via email, with
a maximum file size of 15 MB. The proposal should be submitted as one complete
package covering all items outlined in the scope of services. The SOQ must include
bookmarks linking to sections for easy navigation.
Orange County reserves the right to reject any or all submittals, to waive minor
informalities and to make such selection deemed in its best interest.
Minority Bidders: Orange County encourages all businesses, including minority, and
women owned businesses to respond to all RFPs, ITBs, and RFQs.
V. Statement of Qualification Questions:
Upon review of the RFQ documents, firms may have questions to clarify or interpret the
RFQ in order to submit the best response possible. To accommodate the RFQ Questions
process, firms shall submit any such questions by the above due date. Written questions
shall be emailed to Darlene Weaver at dweaver@orangecountync.gov and Jovana
Amaro at financepurchasing@orangecountync.gov by the date and time specified above.
Firms should enter “RFQ#: 367-OC5467: Questions” as the subject for the email.
Questions submittals should include a reference to the applicable RFQ section. The
purpose of this email notification requirement is to allow staff to see questions as they
come in quickly.
5|Page