Keswick Park Master Plan Implementation

Location: Georgia
Posted: Feb 5, 2026
Due: Mar 5, 2026
Agency: Chamblee city
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
  • R - Professional, Administrative and Management Support Services
Publication URL: To access bid details, please log in.
Description Opening Date/Time Closing Date/Time


Keswick Park Master Plan Implementation



February 05, 2026
:


March 05, 2026
:

Attachment Preview

City of Chamblee
Keswick Park Master Plan Implementation
PR-2026-02
REQUEST FOR
QUALIFICATIONS
CITY OF CHAMBLEE
KESWICK PARK MASTER PLAN IMPLEMENTATION
PR-2026-02
City of Chamblee
3518 Broad Street
Chamblee, GA 30341
February 5, 2026
1
City of Chamblee
Keswick Park Master Plan Implementation
PR-2026-02
Schedule of Events
Release Date
Pre-Proposal Meeting (10:00 AM, Keswick
Park, 3460 Keswick Drive)
Q&A Process Ends (2:00 PM)
Proposals Due (2:00 PM, electronic submission)
Presentations by Selected Firms (if needed)
City Council Award
Thursday 02/05/26
Thursday 02/12/26
Thursday
Thursday
Tuesday
Tuesday
02/26/26
03/05/26
03/17/26
04/21/26
Contact for Proposal
Jodie Gilfillan, Director of Parks, Recreation & Arts Department,
procurement@chambleega.gov.
Introduction & Purpose
This request is to select a professional engineering firm to provide construction documents,
bidding and construction management assistance for improvements at Keswick Park.
Offerors are invited to demonstrate their capabilities to perform the following services which
will include, but are not limited to:
- Ability to provide civil engineering, landscape architecture and structural design of the project;
- Ability to prepare construction documents and permitting;
- Ability to provide bidding assistance;
- Ability to provide construction project management.
Scope of Work
The intent of this scope of work is to provide all professional services normally anticipated for
design, permitting, and construction phase services for a project of this type. Offerors may
add to, or alter, the following scope of work, as they see fit to accomplish the work.
Specifically, the selected offeror will provide professional engineering services for the design
of Keswick Park Upper Area based upon the following assumptions:
(1) Design based on the boundary, topography and underground utility survey, provided by the
city.
(2) Design documents based on the approved conceptual master plan, see Appendix B, and
the outcome of two (2) additional public input meetings conducted by the selected firm for
this project.
(3) Permitting will be required with DeKalb County.
(4) Geotechnical services, if required, will be provided by the City.
(5) Offeror will provide project management, civil engineering, landscape architecture and
structural design for the project.
(6) Offeror will procure sub-consultants for the project.
(7) Photometric studies will be needed for the field, parking lot and pathway lighting.
(8) Stormwater management design shall achieve both water quality/runoff reduction and
channel protection. Infiltration-based, vegetative green infrastructure practices should be
contemplated in addition to underground detention.
(9) Land disturbance will be greater than 1 acre, therefore 3-phase erosion control plans and
submittal of an NOI will be required.
2
City of Chamblee
Keswick Park Master Plan Implementation
PR-2026-02
(10) No GDOT permitting will be required.
(11) New pavilions will be prefabricated structures and approximately 25’ x 15’.
(12) Irrigation design is included in scope. An irrigation pump is not required.
(13) Water and Electrical service are located within the survey area. Offsite utility design is not
included in the scope.
(14) Meetings are limited to those defined in the scope of services.
(15) Plans will be distributed to prospective bidders as PDF’s.
(16) Reimbursable expenses for mileage and printing included in the scope of services.
(17) Permitting fees, if any, will be provided by Client.
(18) Construction duration is expected to be 12 months.
(19) Construction meetings will occur bi-weekly.
The scope of work shall consist of, but not be limited to, public input meetings; schematic
design; design development; construction documents and permitting; bidding assistance; and
construction project management. These tasks are outlined below.
1. Preliminary Activities
A. Hold Kick-Off Meeting
Hold a kick-off meeting at the City offices or the project site to review the scope of work,
schedule, and budget to ensure mutual understanding and to coordinate the work. Discuss
special restriction with construction within Keswick Park due to this being within a
neighborhood.
2. Public Meetings and Master Plan
A. Hold Public Input Meetings
Hold two (2) public input meetings to gather additional feedback and incorporate public
comments into the conceptual master plan. Conduct meeting with the Client to review draft
master plan, and revise and render final master plan based on Client meeting.
3. Schematic Design
A. 30% Schematic Design
Prepare 30% level (schematic design) construction plans based on the final site concept
plan.
The schematic design plans will include the following drawings.
a. Cover Sheet
b. Survey of Existing Conditions (by others)
c. Demolition Plans
d. Staking Plans
e. Grading and Drainage Plans
f. Landscape Plans
g. Architecture Plans
B. Prepare preliminary hydrology study model.
C. Update master plan cost estimate.
3
City of Chamblee
Keswick Park Master Plan Implementation
PR-2026-02
D. Meet with the City to review the schematic design level plans and cost
estimate.
E. Incorporate the City’s comments into the design.
F. The City to approve schematic design submittal prior to the design team
proceeding on to the design development phase.
G. Deliverables:
Two printed sets of the schematic design submittal
PDF of schematic design submittal
Schematic design cost estimate
Memo of meeting with City
4. Design Development
A. 50% Design
Prepare and submit 50% level (design development) construction plans to the City. The design
development will include the following drawings:
Cover Sheet
Survey of Existing Conditions (by others)
Demolition Plans
Staking Plans
Grading and Drainage Plans
Utility Plans
Site Lighting Plans
Construction Details
Tree Protection Plan
Landscape Plan and Details
Architecture, Mechanical, Electrical, Plumbing and Structural Plans
Once the City has reviewed the submittal, a status meeting will be held at the City offices or
project site to review City comments and discuss schedule to complete.
B. Preliminary stormwater sizing.
C. Prepare an updated cost estimate for the design development plans.
D. Meet with the City to review the design development level plans and cost
estimate.
E. Incorporate the City’s comments into the design.
F. The City to approve Design Development submittal prior to the design team
proceeding on to the Construction Document Phase.
G. Deliverables:
Two printed sets of the Design Development submittal
PDF of Design Development submittal
Design development cost estimate
4
City of Chamblee
Keswick Park Master Plan Implementation
PR-2026-02
Memo of meeting with City
Schedule updated project schedule
5. Construction Documents and Permitting
A. 95% Design
Prepare and submit 95% level construction plans and specifications to the City for final review. The
construction plan set will include the following drawings:
Cover Sheet
Survey of Existing Conditions (by others)
Demolition Plans
Staking Plans
Grading and Drainage Plans
3-Phase Erosion Control Plans
Construction Details
Utility Plans
Profiles
Site Lighting Plans
Tree Protection Plans
Landscape Plans and Details
Irrigation Plans and Details
Architecture, Mechanical, Electrical, Plumbing and Structural Plans
B. Update the cost estimate based on the 95% construction plans.
C. Complete the stormwater hydrology report.
D. Meet with the City to review the construction documents and updated cost
estimate.
E. Prepare technical specifications.
F. Submit plans to City of Chamblee and DeKalb County for permit review.
G. Monitor and respond to agency comments, as required, for permit issuance.
H. Deliverables:
Two printed sets of construction plans
PDF of construction plans
PDF of updated cost estimate
PDF of technical specifications
PDF of hydrology report
Memo of meeting with City
Annotated responses to permitting requirements
PDF of approved plans
Schedule updated project schedule
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...and lead public design charrettes and incorporate findings into development of the draft ...

State Government of Georgia

Bid Due: 6/18/2026

...Planning services will be selected in July of 2026. The Master Plan will ...

Macon Bibb County

Bid Due: 6/18/2026

...in connection with the Airport Capital Improvement Plan at the Thomson-McDuffie County Airport... ...

Thomson McDuffie County

Bid Due: 6/08/2026

...SOLICITATION DESCRIPTION DUE DATE RFP No. 26-0005 Consultant Services for Master Study for ...

Consolidated Government of Columbus

Bid Due: 6/12/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.