| Location: | New York |
|---|---|
| Posted: | Mar 25, 2026 |
| Due: | Mar 26, 2026 |
| Agency: | DEPT OF DEFENSE |
| Type of Government: | Federal |
| Category: |
|
| Solicitation No: | W50S8J26QA011 |
| Publication URL: | To access bid details, please log in. |
APEX Accelerators are an official government contracting resource for small businesses. Find your local APEX Accelerator (opens in new window) for free government expertise related to contract opportunities.
APEX Accelerators are funded in part through a cooperative agreement with the Department of Defense.
The APEX Accelerators program was formerly known as the Procurement Technical Assistance Program (opens in new window) (PTAP).
Project Title: Bldg. 20 Sewer Pipe Repair
Project Location: Stratton Air National Guard Base, Scotia, NY
Project Number: VBDZ262101. Reference attached statement of work (SOW) for project details.
This is a total small business set-aside for NAICS 237110, water and sewer line and related structures construction with a small business size standard of $45M.
The magnitude of this project is less than $25,000.
Reference 52.212-2 Evaluation-Commercial Products and Commercial Services. (Deviation) for the quote evaluation factors.
Quotes shall be submitted via email to the following address: 109.aw.fal.msc.contracting@us.af. mil
A site visit will be held on March 19, 2026, at 10:00 am. All attendees will meet at the civil engineering building (bldg. 25), 1 Air National Guard Road, Scotia, NY 12302. Interested parties should email 109.aw.fal.msc.contracting@us.af.mil confirming their intent to attend the site visit. In addition to a valid, government issue photo id, attendees should be prepared to present the following information upon arrival at the gate:
Q&A from 24 March 2026:
1. How deep is the sewer line?
Answer: Between 6-7 feet based off our locator
2. What size and material is it made of?
Answer: 6” SDR.
3. What kind of flow should we figure for?
Answer: 2 buildings run through it, but we will coordinate with the facilities on the day of maintenance and try to schedule an alternate work schedule day to reduce use.
4. Are OSHA 10hr required?
Answer: No, we do not require OSHA 10hr.
Q&A from 25 March 2026:
1. Do you know if ground water is an issue?
Answer: Yes, there is ground water.
2. Are there any soil borings available?
Answer: No, soil borings are not available.
3. Does anybody familiar with the site know if the existing soil is clay, gravel or sand?
Answer: The site is mainly shale.
| Mar 12, 2026 | [Solicitation (Original)] 109 AW - Bldg 20 Sewer Pipe Repair |
| Mar 24, 2026 | [Solicitation (Updated)] 109 AW - Bldg 20 Sewer Pipe Repair |