MARTINEZ UNIFIED SCHOOL DISTRICT
REQUEST FOR QUALIFICATIONS
FOR DESIGN-BUILD SERVICES
ALHAMBRA HIGH SCHOOL BUILDING F REPLACEMENT AND VARIOUS CAMPUS
MODERNIZATIONS PROJECT
RFQ # 26-04
Martinez Unified School District (“District”) is seeking to prequalify design-build entities or
design-build teams to submit proposals to design and construct the District’s Alhambra High
School Building F Replacement and Various Campus Modernizations Project
(“Project”), in accordance with the design-build statute, Education Code section 17250.10 et
seq. Only respondents that have been prequalified by the District in response to this Request
for Qualifications (“RFQ”) will be eligible to submit proposals in response to the District’s
subsequent Request for Proposals (“RFP”) for the Project.
Respondents to this RFQ shall submit a fully completed and sealed Statement of Qualifications
(“SOQ”), using the District’s standard prequalification template for design-build projects, as
further described herein, to:
MARTINEZ UNIFIED SCHOOL DISTRICT
921 Susana Street
Martinez, CA 94553
ATTN: Andy Cannon, Chief Business Official
RFQ # 26-04
ALL SOQS ARE DUE BY 2:00 P.M. ON WEDNESDAY, APRIL 29, 2026. Oral, telegraphic,
facsimile, telephone, or email SOQs will not be accepted. SOQs received after this date and
time will not be accepted and will be returned unopened. Two (2) printed Sets and one (1)
electronic file are required to be submitted.
District reserves the right to waive irregularities and omissions in the information contained
in any SOQ, and to make all final determinations. District may use other sources of
information outside of the SOQs to investigate respondents or to verify answers.
Each SOQ must be certified under penalty of perjury by the respondent. If any information
provided by a respondent becomes inaccurate, the respondent must immediately notify
District and provide updated, accurate information in writing, under penalty of perjury. District
reserves the right to suspend or rescind prequalification at any time based on subsequently
learned information.
Questions regarding this RFQ may be directed in writing to the Project Manager, Patrick Walsh,
at Patrick.walsh@cumming-group.com, and must be submitted on or by 2:00 PM,
Wednesday, April 15, 2026.
MARTINEZ UNIFIED SCHOOL DISTRICT
1
RFQ #26-04 - Design-Build Services
AHS Building F Replacement and Various Modernizations Project
DWK 4532181v1
I.
RFQ SCHEDULE SUMMARY
The District may change the dates on this schedule without prior notice.
DEADLINE
April 1, 2026
April 15, 2026 at 2:00 PM
April 22, 2026
April 29, 2026 at 2:00 PM
TBD
Anticipated June 2026
ACTION ITEM
Release of RFQ.
Last day to receive written questions from
respondents.
Last day for District to issue addenda or
answer questions.
Deadline for submissions in response to RFQ.
Notice to prequalified short-listed
respondents.
Release of RFP to prequalified short-listed
respondents.
II. PROJECT DESCRIPTION AND SCOPE OF SERVICES
Pursuant to Education Code section 17250.10 et seq., the District is seeking a design-build
entity or team (“Design/Builder”) to design and construct the District’s Alhambra High School
Building F Replacement and Various Campus Modernizations (“Project”). The Project is further
defined in the attached APPENDIX A, along with the District’s expected cost range and
schedule for the Project. The District’s performance specifications, which the selected
Design/Builder must adhere to in delivering the Project, will be made available to prequalified
respondents at the RFP stage.
The selected Design/Builder must be appropriately licensed and registered in the State of
California for architectural, engineering, and construction services as needed to complete the
Project. In addition, the selected Design/Builder shall have experience with both design and
construction of public school facilities and in working with the Office of Public School
Construction (“OPSC”), the Division of the State Architect (“DSA”), and Title 24 of the
California Code of Regulations.
All contractors who are part of the design-build team must be registered with the Department
of Industrial Relations (“DIR”) as required by law. The selected Design/Builder will be required
to comply with the Labor Code prevailing wage requirements, skilled and trained workforce
requirements, the District’s Project Labor Agreement, and the District’s bonding and insurance
requirements. The selected Design/Builder shall be required to work cooperatively with
District staff, the Governing Board, all other technical consultants, the bridging architect, the
project inspector, and any program and/or construction manager, if any, retained by the
District for the Project, citizens’ oversight committee, other District committees, and the
community to facilitate timely and professional completion of the Project.
MARTINEZ UNIFIED SCHOOL DISTRICT
2
RFQ #26-04 - Design-Build Services
AHS Building F Replacement and Various Modernizations Project
DWK 4532181v1
III. DESIGN-BUILD PROCUREMENT PROCESS
Pursuant to Education Code section 17250.25, procurement of a Design/Builder will follow
two (2) phases:
1. Prequalification – First, by this RFQ, the District will prequalify respondents using a
standard template request for statements of qualifications. The significant factors the
District reasonably expects to consider in evaluating qualifications are identified in
Section VIII, below. The District intends to short-list Design Build Teams based on the
evaluation.
1. Design-Build Proposals – Second, the District will issue an RFP, inviting only
prequalified short-listed respondents to submit competitive sealed proposals for the
Project. The District will use a best value selection method for evaluating proposals.
The procedure for final selection will be as follows:
a. The District will evaluate responsive proposals using only the criteria and
selection procedures specifically identified in the RFP.
b. The District may, at its discretion, request proposal revisions and hold
discussions and negotiations with responsive proposers. The RFP will define
applicable procedures to ensure that discussions or negotiations are conducted
in good faith.
c. The District will rank responsive proposers based on a determination of value
provided, but shall not be required to rank more than three (3) proposers.
d. The District will award the contract, if at all, to the responsible Design/Builder
whose proposal is determined by the District to be the best value.
Per Board policy, any person or entity that has performed or is performing services for District
relating to the solicitation of this design-build project will not be eligible to submit a proposal
as a design-build entity or to join a design-build team.
IV. FULL OPPORTUNITY
No Respondent will be discriminated against on the basis of race, religious creed, color,
national origin, ancestry, physical disability, mental disability, reproductive health decision-
making, medical condition, genetic information, marital status, sex, gender, gender identity,
gender expression, age, sexual orientation, or veteran or military status of any person in any
consideration leading to the award of the contract. District also affirmatively ensures that
Disadvantaged Business Enterprises (“DBE”), Small Local Business Enterprises (“SLBE”),
Small Emerging Local Business Enterprises (“SELBE”), and Disabled Veterans Business
Enterprises (“DVBE”) shall be afforded full opportunity to respond to this RFQ.
V. LIMITATIONS
This RFQ is neither a formal request for bids, nor an offer by the District to contract with any
party responding to this RFQ. The District reserves the right to add additional prequalified
respondents for consideration after distribution of this RFQ, if it is found to be in the best
interest of the District. All decisions concerning selection of the Design/Builder will be made
in the best interests of the District. The issuing of a subsequent RFP and awarding of the
contract pursuant to the subsequent RFP, if at all, is at the sole discretion of the District.
MARTINEZ UNIFIED SCHOOL DISTRICT
3
RFQ #26-04 - Design-Build Services
AHS Building F Replacement and Various Modernizations Project
DWK 4532181v1
The District makes no representation that participation in this RFQ process will lead to an
award of contract or any consideration whatsoever. The District shall in no event be
responsible for the cost of preparing any response to this RFQ.
SOQs submitted by respondents are not public records and are not open to public inspection.
All information provided will be kept confidential to the extent permitted by law. The contents,
however, may be disclosed to third parties for purposes of verification or investigation. State
law requires that the names of respondents applying for prequalification status shall be public
records subject to disclosure.
VI. RESTRICTIONS ON LOBBYING AND CONTACTS
From the period beginning on the date of the issuance of this RFQ and ending on the date of
the award of the contract, no person, or entity submitting in response to this RFQ, nor any
officer, employee, representative, agent, or consultant representing such a person or entity
shall contact through any means or engage in any discussion regarding this RFQ, the
evaluation or selection process/or the award of the contract with any member of the District,
Governing Board, selection members, or any member of the Citizens’ Oversight Committee.
Any such contact shall be grounds for the disqualification of the respondent submitting a SOQ.
VII. STANDARD TEMPLATE FOR STATEMENT OF QUALIFICATIONS
Attached hereto as APPENDIX B is the District’s design-build prequalification template.
Respondent must complete the prequalification template, certify its answers under penalty of
perjury, and attach all information requested therein. The completed, certified prequalification
template, together with all attachments, constitutes respondent’s SOQ.
Each SOQ must be certified under penalty of perjury. If any information provided by a
respondent becomes inaccurate, the respondent must immediately notify District and provide
updated, accurate information in writing, under penalty of perjury.
VIII. EVALUATION
The District will evaluate all timely submitted SOQs. Each SOQ must be complete. Incomplete
SOQs will be considered nonresponsive and grounds for disqualification. The District retains
the sole discretion to determine issues of compliance and to determine whether a respondent
is responsive and qualified.
Significant factors the District reasonably expects to consider in evaluating qualifications are
as follows:
• All required licenses and registration to design and construct the Project, with no
recent revocations or suspensions;
• Established performance history, including an absence of criminal or civil violations or
significant disputes;
• Capacity to obtain required bonds and insurance for the Project;
• Design expertise and experience;
• Construction expertise and experience;
• Acceptable safety record;
MARTINEZ UNIFIED SCHOOL DISTRICT
4
RFQ #26-04 - Design-Build Services
AHS Building F Replacement and Various Modernizations Project
DWK 4532181v1
• Enforceable commitment to use a skilled and trained workforce for the Project, as
applicable; and
• Financial capacity to complete the Project.
District may use other sources of information outside of the SOQs to investigate respondents
or verify answers. District’s investigation may extend beyond contacting project references
identified in SOQs.
After completing its evaluation, the District will notify respondents selected for
prequalification.
IX. FINAL DETERMINATION
Prequalification is at the sole discretion of the District. The District reserves the right to waive
irregularities and omissions in the information contained in any SOQ, and to make all final
determinations. The District further reserves the right to suspend or rescind prequalification
at any time based on subsequently learned information.
The District makes no representation that participation in this RFQ process will lead to an
award of contract or any consideration whatsoever. The District reserves the right to seek
proposals from or to contract with any firm not participating in this process. The District shall
in no event be responsible for the cost of preparing any SOQ or other response to this RFQ.
WE THANK YOU FOR YOUR INTEREST IN THE DISTRICT’S PROJECT!
MARTINEZ UNIFIED SCHOOL DISTRICT
5
RFQ #26-04 - Design-Build Services
AHS Building F Replacement and Various Modernizations Project
DWK 4532181v1
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.