RFP26-016 Baker Roof Replacement

Location: Missouri
Posted: Apr 1, 2026
Due: Apr 24, 2026
Agency: Missouri Western State University
Type of Government: State & Local
Category:
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.
  • RFP26-016 Project Information | Baker Roof Drawings | Baker Roof Replacement | April 1, 2026
  • Attachment Preview

    REQUEST FOR PROPOSAL RFP26-016
    FOR
    BAKER ROOF REPLACEMENT
    Submission Deadline: April 24, 2026
    2:00 p.m. CST
    Questions and/or requests for clarification of this RFP should be submitted via email to the Purchasing Department
    at purchase@missouriwestern.edu. All questions and/or clarifications can be sent at any time regarding this RFP to
    the Purchasing Department until 9:00 a.m. CST on April 16, 2026. Questions received after this date may not be
    answered. Please reference RFP26-016 on all correspondence. Answers to the submitted questions will be emailed
    to each Vendor as an addendum to this solicitation by April 17, 2026. It is the responsibility of all interested parties
    to read this information and return it as part of the RFP confirming receipt.
    Page 1 of 24
    Table of Contents
    Description ............................................................................................................................................................ 3
    Extent of Work ...................................................................................................................................................... 3
    Submittals .............................................................................................................................................................. 3
    Product, Delivery, Storage, and Handling.................................................................................................... 4
    Work Sequence ..................................................................................................................................................... 5
    Use of the Premises ............................................................................................................................................. 5
    Existing Conditions.............................................................................................................................................. 5
    Mandatory Pre-Bid Meeting ............................................................................................................................. 5
    Temporary Facilities and Controls ................................................................................................................ 6
    Job Site Protection ............................................................................................................................................... 6
    Safety ....................................................................................................................................................................... 7
    Workmanship ....................................................................................................................................................... 7
    Quality Assurance ............................................................................................................................................... 8
    Job Conditions, Cautions, and Warnings ...................................................................................................... 9
    Warranty................................................................................................................................................................ 9
    Products................................................................................................................................................................10
    Execution ..............................................................................................................................................................12
    Submission Deadline ........................................................................................................................................15
    Timeline ................................................................................................................................................................15
    Prevailing Wage.................................................................................................................................................16
    Bid Bond ...............................................................................................................................................................16
    Evaluation ............................................................................................................................................................16
    Attachment A: Questionnaire ........................................................................................................................17
    Attachment B: Response Cover Sheet ..........................................................................................................19
    University Standard Terms and Conditions ..............................................................................................20
    Page 2 of 24
    Description
    A. Remove all the modified roofing material on the north section and the two (2) south sections and replace
    with TPO roofing at the Missouri Western State University (MWSU) Baker Fitness Center located at
    4525 Downs Drive in St. Joseph, MO, 64507. This will include metal flashings, copings, scuppers,
    waterheads, and downspouts.
    B. The project consists of installing Carlisle SynTec’s Sure-Weld (TPO) Adhered Roofing System as
    outlined below:
    Apply the Sure-Weld Adhered Roofing System in conjunction with Insulbase Polyiso for main roof
    sections, and Taper 1/8” per 1’0” Taper Polyiso 1” start for the canopy roofs (plywood deck), after tear
    off of the existing modified roof to expose the Tectum deck in main roof sections, plywood deck in
    canopy sections, for verification of suitable substrate as specified in this specification.
    C. Replace any damaged Tectum decking panels as needed and specified on drawing. Replacement
    Tectum decking panels will be provided by MWSU.
    Extent of Work
    A. Provide all labor, material, tools, equipment, and supervision necessary to complete the installation
    of the Sure-Weld reinforced TPO (Thermoplastic Polyolefin) Adhered Roofing System including
    flashings and insulation as specified herein and as indicated on the drawings in accordance with
    the manufacturer's most current specifications and details.
    B. The roofing contractor shall be fully knowledgeable of all requirements of the contract documents
    and shall make themselves aware of all job site conditions that will affect their work.
    C. The roofing contractor shall confirm all given information and advise the building owner, prior to
    bid, of any conflicts that will affect their cost proposal.
    D. Any contractor who intends to submit a bid using a roofing system other than the approved
    manufacturer must submit for pre-qualification in writing fourteen (14) days prior to the bid date.
    Any contractor who fails to submit all information as requested will be subject to rejection. Bids
    stating “as per plans and specs” will be unacceptable.
    Submittals
    A.
    Prior to starting work, the roofing contractor must submit the following:
    1. Shop drawings showing layout, details of construction, and identification of materials.
    2. A sample of the manufacturer's Membrane System Warranty.
    Page 3 of 24
    3. Submit a letter of certification from the manufacturer which certifies the roofing contractor
    is authorized to install the manufacturer's roofing system and lists foremen who have
    received training from the manufacturer along with the dates training was received.
    4. Certification from the membrane manufacturer indicating the membrane thickness over the
    reinforcing scrim (top ply membrane thickness) is nominal 15 mil or thicker.
    5. Certification of the manufacturer's warranty reserve.
    B. Upon completion of the installed work, submit copies of the manufacturer's final inspection to the
    specifier prior to the issuance of the manufacturer's warranty.
    Product, Delivery, Storage, and Handling
    A. Deliver materials to the job site in the manufacturer's original, unopened containers or wrappings
    with the manufacturer's name, brand name and installation instructions intact and legible. Deliver
    in sufficient quantity to permit work to continue without interruption.
    B. Comply with the manufacturer's written instructions for proper material storage.
    1. Store Sure-Weld membrane in the original undisturbed plastic wrap in a cool, shaded area.
    Sure-Weld membrane that has been exposed to the elements for approximately 7 days must
    be prepared with Carlisle Weathered Membrane Cleaner prior to hot air welding.
    2. Store curable materials (adhesives and sealants) between 60°F and 80°F in dry areas
    protected from water and direct sunlight. If exposed to lower temperature, restore to 60°F
    minimum temperature before using.
    3. Store materials containing solvents in dry, well-ventilated spaces with proper fire and
    safety precautions. Keep lids on tight. Use before expiration of their shelf life.
    4. The roofing contractor shall confirm all given information and advise the building owner,
    prior to bid, of any conflicts that will affect their cost proposal.
    5. Any contractor who intends to submit a bid using a roofing system other than the approved
    manufacturer must submit for pre-qualification in writing fourteen (14) days prior to the
    bid date. Any contractor who fails to submit all information as requested will be subject
    to rejection. Bids stating "as per plans and specs" will be unacceptable.
    C. Any materials which are found to be damaged shall be removed and replaced at the applicator's
    expense.
    Page 4 of 24
    Work Sequence
    A. Schedule and execute work to prevent leaks and excessive traffic on completed roof sections. Care
    should be exercised to provide protection for the interior of the building and to ensure water does
    not flow beneath any completed sections of the membrane system.
    B. Do not disrupt activities in occupied spaces.
    Use of the Premises
    A. Before beginning work, the roofing contractor must secure approval from the building owner's
    representative for the following:
    1. Areas permitted for personnel parking.
    2. Access to the site.
    3. Areas permitted for storage of materials and debris.
    4. Areas permitted for the location of cranes, hoists and chutes for loading and unloading
    materials to and from the roof.
    B. Interior stairs or elevators may not be used for removing debris or delivering materials, except as
    authorized by the building superintendent.
    Existing Conditions
    A. If discrepancies are discovered between the existing conditions and those noted on the drawings,
    immediately notify the owner's representative by phone and solicit the manufacturer's approval
    prior to commencing with the work. Necessary steps shall be taken to make the building watertight
    until the discrepancies are resolved. Any conditions which are not shown on the shop drawings
    should be indicated on a copy of the shop drawing and included with bid submittal if necessary to
    clarify any conditions not shown.
    Mandatory Pre-Bid Meeting
    B. A pre-bid meeting will be held at the job site. Meet at the back side of Baker near the football
    scoreboard on Tuesday April 14th at 10:00 AM with Brian Harrah. He can be reached at 816-689-
    9790 if there are any questions.
    Page 5 of 24
    This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
    Daily notification on new contract opportunities

    With GovernmentContracts, you can:

    • Find more opportunities and win more business
    • Receive daily alerts for all new bid opportunities
    • Get contract opportunities matched to your business
    ONE WEEK FREE TRIAL

    See also

    ...Follow HSTR GW and FW Roof Replacement Active Contract Opportunity Notice ID 140P6026Q0046 ...

    INTERIOR, DEPARTMENT OF THE

    Bid Due: 7/02/2026

    ...North Platte R-I Roof Replacements - Dearborn, MO StatusAccepting Bids Bid Date 6/16/26 ...

    Drexel Technologies

    Bid Due: 6/16/2026

    ...North Platte R-I Roof Replacements - Dearborn, MO StatusAccepting Bids Bid Date 6/16/26 ...

    Drexel Technologies

    Bid Due: 6/16/2026

    ...INVITATION FOR BID (IFB) MODOT 0000000320SL: FY27 KC Independence Salt Dome Roof Replacement... ...

    State Government of Missouri

    Bid Due: 6/11/2026

    * Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.