Request for Proposals (RFP) – Design-Build Services for DWM New Operations Facility (PS3104)

Location: Illinois
Posted: Jan 15, 2026
Due: Feb 19, 2026
Agency: Public Building Commission
Type of Government: State & Local
Category:
  • C - Architect and Engineering Services - Construction
  • Y - Construction of Structures and Facilities
Publication URL: To access bid details, please log in.
Request for Proposals (RFP) – Design-Build Services for DWM New Operations Facility (PS3104)

PROJECT DESCRIPTION:

The Public Building Commission of Chicago (PBC) has issued a Request for Proposals (RFP) pursuant to the requirements of the Public Building Commission Act (50 ILCS 20 et seq.) (the Act) for the following design-build project:

PBC Project No. 04029
PBC Contract No. PS3104
DWM New Operations Facility
4825 West Lawrence Avenue
Chicago, Illinois 60630

The PBC may award design-build contract(s) for the Project in accordance with the requirements of the Public Building Commission Act (50 ILCS 20/et seq.). This will be a two-phase procurement process. This two-phase process will evaluate design-build entities based on qualifications, technical approach, and cost proposals.
The Project will include site preparation, design and construction of a new operations facility and associated site improvements.

PHASE I

Phase I – Pre-Submission Conference Activities:
A NON-Mandatory Pre-Submission Conference will be held on Thursday, January 29, 2026, at 11:00 AM at the Copernicus Center located at 5216 West Lawrence Avenue, in Chicago, Illinois. Registration will begin at 10:30am. All interested parties are encouraged to attend.

Phase I – Pre-Submission Materials:

(To be uploaded once available)

To view related video(s), please click on respective link(s) below:

(To be uploaded once available)

Phase I – Site Visit Activities:
A
NON-Mandatory Site Visit will be held on Thursday, January 29, 2026, immediately following the Pre-Submission Conference.

Phase I – Site Visit Materials:

(To be uploaded once available)

Phase I – RFP Document:
RFP Document for Design-Build Services for DWM New Operations Facility – PS3104 – Issued January 15, 2026

Phase I – RFP Exhibits:
NOTE: Some files and/or FTP links are large and will require more time to download.

Exhibit A. Sample Form of Design-Build Agreement

Exhibit B. Insurance Requirements

Exhibit C. Project Community Area Map

Exhibit D. 100% Schematic Design BOD Drawings

Exhibit E. 100% Schematic Design BOD Narrative Report

Exhibit F. 100% Schematic Design BOD Outline Specifications

Exhibit G. Alta/NSPS Land Title Survey

Exhibit H. Environmental Phase-I Environmental Site Assessment (ESA) Report

Exhibit I. Environmental Phase-II Environmental Site Assessment (ESA) Report

Exhibit J. Environmental Site-Specific Health and Safety Plan

Exhibit K. Ground Penetrating Radar (GPR) Survey Report

Exhibit L. DRAFT Geotechnical Report

Exhibit M. DRAFT Traffic Impact Study Report

Exhibit N. DRAFT Environmental Reno/Demo Asbestos Survey Report

Exhibit O. DRAFT Environmental Reno/Demo Lead-Based Paint Survey Report

Exhibit P. DRAFT Environmental Reno/Demo Hazardous Materials Survey Report

Exhibit Q. LEED v4 BD+C New Construction USGBC Registration Receipt

Exhibit R. ComEd Energy Efficiency Program – Preliminary Incentives Report

Phase I Addenda:

(To be uploaded once available)

Phase I – Submission Deadline:
Proposals must be submitted by Thursday, February 19, 2026 at 11:00AM (CT) to the attention of Patricia Montenegro, Contract Officer at: patricia.montenegro@cityofchicago.org and pbc-procurement@cityofchicago.org .

QUESTIONS:
All questions must be directed to the attention of Patricia Montenegro, Contract Officer, by Thursday, February 5, 2026, at 4:00PM (CT) a nd submitted via email to: patricia.montenegro@cityofchicago.org .

PHASE II

Shortlisted Firms:

(Shortlisted Firms will appear here once determined)

Social Media:
Follow this project on Twitter
PBCChi#PBC

Public Building Commission of Chicago
Mayor Brandon Johnson, Chairman
Ray Giderof, Executive Director

Office of Inspector General Complaint Hotline
If you see corruption, fraud, waste, or dishonest practices of any kind please report it to the City of Chicago Office of Inspector General (OIG) – PBC’s oversight body. Concerned employees, contractors, consultants, and members of the public may contact OIG via its independent hotline and website.

Phone: (833) TALK-2-IG / (833) 825-5244

Email: talk2ig@igchicago.org

Website: Online Intake Form – Chicago Office of Inspector General

Attachment Preview

public building commission of chicago
Request for Proposals
Design-Build Services
for DWM New
Operations Facility
PS3104
ISSUED: January 15, 2026
Public Building Commission of Chicago
Richard J. Daley Center, Room 200
50 W. Washington Street
Chicago, Illinois 60602
www.pbcchicago.com
Mayor Brandon Johnson
Chairman
Ray Giderof
Executive Director
CONTACT INFORMATION
FIRM NAME:
CONTACT NAME:
CONTACT TELEPHONE:
CONTACT EMAIL:
ADDRESS:
This Cover Sheet page MUST be submitted with your Submission.
TABLE OF CONTENTS
SECTION I. INTRODUCTION ....................................................................................................................... 1
SECTION II. KEY INFORMATION ................................................................................................................ 3
SECTION III. PROJECT DESCRIPTION ...................................................................................................... 9
SECTION IV. PHASE I QUALIFICATIONS EVALUATION CRITERIA....................................................... 14
SECTION V. SUBMISSION REQUIREMENTS ........................................................................................... 19
SECTION VI. SUBMISSION CHECKLIST ................................................................................................. 21
ATTACHMENTS - FORMS AND EXHIBITS
FORMS
Form A. MBE/WBE, EEO, CRO, and CH Participation
Form B. Joint Venture Affidavit
Form C. Disclosure Affidavit
Form D. Disclosure of Retained Parties
Form E. Affidavit of Non-Collusion
Form F. Safety Information
Form G. Legal Actions
Form H. References
Form I. Proposal Acknowledgement
Form J. Proposal Execution Page
EXHIBITS
Exhibit A. Sample Form of Design-Build Agreement
Exhibit B. Insurance Requirements
Exhibit C. Project Community Area Map
Exhibit D. 100% Schematic Design BOD Drawings
Exhibit E. 100% Schematic Design BOD Narrative Report
Exhibit F. 100% Schematic Design BOD Outline Specifications
Exhibit G. Alta/NSPS Land Title Survey
Exhibit H. Environmental Phase-I Environmental Site Assessment (ESA) Report
Exhibit I. Environmental Phase-II Environmental Site Assessment (ESA) Report
Exhibit J. Environmental Site-Specific Health and Safety Plan
Exhibit K. Ground Penetrating Radar (GPR) Survey Report
Exhibit L. DRAFT Geotechnical Report
Exhibit M. DRAFT Traffic Impact Study Report
Exhibit N. DRAFT Environmental Reno/Demo Asbestos Survey Report
TABLE OF CONTENTS
Exhibit O. DRAFT Environmental Reno/Demo Lead-Based Paint Survey Report
Exhibit P. DRAFT Environmental Reno/Demo Hazardous Materials Survey Report
Exhibit Q. LEED v4 BD+C New Construction USGBC Registration Receipt
Exhibit R. ComEd Energy Efficiency Program - Preliminary Incentives Report
SECTION I – INTRODUCTION
A. INTRODUCTION
The Public Building Commission of Chicago (“Commission” or “PBC”) has enhanced education, safety, and
recreation across the region by building or renovating hundreds of schools, city colleges, libraries, parks, fire
houses, police stations and other public facilities. PBC’s Partners include the City of Chicago, Cook County,
Department of Water Management, Department of Fleet & Facility Management (2FM), Department of Family
Support Services, Office of Budget and Management, Chicago Public Library, Chicago Public Schools, Chicago
Park District, City Colleges of Chicago and other municipalities. Beginning with land acquisition, the PBC's
professional staff may manage each project through planning, financing, site preparation and remediation, design,
construction and furnishing, functioning as a single point of responsibility for "turn-key" development.
B. TWO-PHASE DESIGN-BUILD REQUEST FOR PROPOSAL (RFP) PROCESS
1. Request for Proposals – Phase I & Phase II: The Public Building Commission of Chicago (PBC) is seeking
a qualified Design-Build entity to provide design and construction services for the Department of Water
Management (DWM), herein referred to as the “Project.” The PBC will award a Design-Build contract for the
Project in accordance with the requirements of the Public Building Commission Act (50 ILCS 20/et seq.) This
procurement is being solicited using the two-phase RFP for Design-Build Process provided by the Public
Building Commission Act (50 ILCS 20/3 – 50 ILCS 20/20). As part of the Phase I Qualifications submission,
Design-Build proposers shall submit their past performance history and qualifications as prescribed in this
RFP for consideration by the PBC. The PBC shall review the Phase I Qualifications submissions and create
a short list of the most highly qualified design build entities (not less than 2 or more than 6) and notify those
entities they have been selected to submit Phase II Technical and Cost proposals for the PBC’s consideration.
The PBC shall provide the short-listed proposers with the final Project Scope and Performance Criteria (SPC)
that will define the PBC’s project requirements, project objectives, programmatic needs and goals, design
criteria, performance criteria, budget parameters and schedule and delivery requirements. The PBC will
evaluate the Phase II Technical & Cost using the criteria and relative weights established in the Phase II RFP.
SPC will include the building's final program and space requirements; performance requirements and
specifications for the building's systems; and design guidelines. Phase II Proposers will be expected to
provide a design, with enhanced engineering and design documents.
2. Proposers: Firms formally organized as design-build entities or design firms and construction contractors
that have associated specifically for this project may submit proposals. For purposes of this RFP, no
distinction is made between entities formally organized as design-build entities and project specific design-
build associations. Both are referred to as the Design-Build Proposer (or Proposer).
3. Notice: All proposers will be notified of the results of the PBC’s evaluation of Phase I submissions. The
names of those Proposers from whom Phase II proposals will be requested will be published on the PBC’s
website at www.pbcchicago.com. For all those Proposers who submit for Phase I and Phase II, the proposal
shall be defined as all information that was submitted in response to the requirements of both phases. The
PBC is not liable for and will not compensate any Proposer for costs incurred in preparation and submission
of a response to this RFP (or for other costs) incurred prior to award of a contract. Furthermore, data and
information furnished or referred to in this RFP is for Proposers’ information only. The PBC shall not be
responsible for any interpretation or conclusion drawn from said data or information by the Proposer.
4. Prohibitions: Pursuant to the Illinois Public Building Commission Act (§50 ILCS 20/20.4d), “the design
professional that prepares the scope and performance criteria is prohibited in any design-build entity proposal
for the project.” This means any firm providing work product that may help develop the scope and performance
criteria for the design-build procurement will be precluded from inclusion on a submitting design-build team.
The following firms are precluded from responding to this solicitation as a part of a design-build team:
Moody Nolan, Inc.
Terra Engineering
David Mason Associates
E.C. Purdy & Associates
C C Johnson & Malhotra, PC
MAPS
Date of Issue: January 14, 2026
PBC: RFP for Design-Build Services for DWM New Operations Facility_PS3104
Page 1 of 47
SECTION I – INTRODUCTION
Gasparec Elberts Consulting, LLC
TEM Environmental, Inc.
Weaver Consultants Group North Central, LLC
AECOM
Vistara Construction Services, Inc.
DAMA Consultants, Inc.
True North Consultants, Inc.
C. REQUIREMENTS
Phase I and Phase II requirements have been developed based on specific criteria in accordance with PBC’s Act.
Please note the following:
i. All design must be performed under the direct supervision of appropriately licensed professionals registered
in the appropriate jurisdiction.
ii. All design must be performed by firms licensed in the appropriate technical disciplines and shall meet all
other licensing requirements specified in this RFP herein.
iii. The proposal shall be defined as all information that was submitted in response to the requirements of the
RFP.
iv. The Commission will conduct this procurement in complete compliance with Public Building Commission Act
which includes (but is not limited to): meeting mandatory timeframes, including compulsory evaluation
criteria, publishing sufficient information regarding projects, and issuing all required notices to proposers.
v. Data and information furnished or referred to in this RFP is for Proposers’ information only.
vi. The PBC shall not be responsible for any interpretation or conclusion drawn from said data or information
by the Proposer.
D. AGREEMENT OVERVIEW
1. Agreement for Design-Build Services: The PBC anticipates the Design-Build Entity will enter into an
Agreement for Design-Build Services (Exhibit A – Form of Design-Build Agreement) with the PBC in a form
substantially similar to the Agreement attached to this RFP. The Agreement will provide for the delivery of
design and construction services to complete the Project.
2. Guaranteed Maximum Price (“GMP”): It is anticipated the Design-Builder will propose a Guaranteed
Maximum Price Cost Proposal in its Phase II Proposal. The Design-Builder will be at-risk by guaranteeing a
maximum price to be included in the Design-Build Agreement and by guaranteeing substantial completion
and project delivery dates to the PBC.
Remainder of Page Intentionally Left Blank
Date of Issue: January 14, 2026
PBC: RFP for Design-Build Services for DWM New Operations Facility_PS3104
Page 2 of 47
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

...as to be eligible for funding under the FAA Airport Improvement Program. A ...

Rantoul village

Bid Due: 6/25/2026

...Engineering Services for 5th Avenue Resurfacing Improvements Project Surface Transportation Program... Construction Engineering ...

Maywood village

Bid Due: 6/12/2026

...solicitation is conducted pursuant to the Qualifications-Based Selection (QBS) process in accordance... of ...

City of Waukegan

Bid Due: 6/17/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.