SECTION 00 11 13
ADVERTISEMENT FOR BIDS
Bids will be received electronically online only by the City of Apple Valley, Minnesota, through Quest CDN, until 10:00 A.M., CST, Tuesday, June 3rd, at which time they will be reviewed for the furnishing of all labor, materials, and all else necessary for the following:
City Project 2025-113 Galaxie Avenue & CSAH 42 Entrance Monument Improvements. This List of Quantities include both the Southwest Streetscape Monument A and Bid Alternate #1 Northwest Streetscape Monument B
175 SF Remove Existing Monuments
675 SF Remove Existing Shrubs
200 SF Remove Paver Edge
25 LF Sawcut Paver Edge
480 SF Remove Concrete Paving
--- LS Earthworks
--- LS Erosion Control
--- LS Traffic Control
17.5 CY Class 5 Base for Paving
710 SF 1” Temporary Bituminous Paving
235 SF 6” Concrete Paving
9.65 CY CIP Concrete Footing
12.70 CY CIP Concrete Foundation Wall
4.50 CY CIP Concrete Masonry Stem Wall
105 LF Precast Concrete Masonry Cap 6” thick
30 LF Precast Concrete Wall Cap 2’-0” x 0’-4”
10 LF Precast Concrete Strip
2 EA Precast Concrete Cap A 4’-0” x 4’-0”
2 EA Precast Concrete Cap B 2’-8” x 2’-8”
335 SF Brick Veneer
6 EA Painted 4 ½” Metal Posts
20 LF Painted Ornamental Steel Fencing
2 EA Aluminum Sign, Anodized, ½” Thick w/ incised and epoxied logo
2 EA Aluminum Sign, Anodized City Logo
2 EA Bench
2 EA Waste Receptacle
830 SF Hydroseed
5 EA Armstrong Gold Maple 2 ½” BB
47 EA Sea Green Juniper #5 Container
65 LF Steel Landscape Edging
--- LS Site Restoration Allowance
--- LS Planting Soils and Mulch Allowance
With related items
Digital copies of the Contract Documents can be obtained at
www.questcdn.com
. The Quest CDN project number is 9658365. Bidders can download the Contract documents for $40 by searching for the project on Quest CDN website’s Project Search page.
Instructions for online bidding are attached. Please contact QuestCDN.com, prior to bidding, at (952) 233-1632 for assistance with free membership registration, downloading, and submitting bids. For electronic bids, electronic bid bonds will also be accepted only through Surety 2000 using contract #9658365. The bid bonds must be payable to the City of Apple Valley in the amount of five percent (5%) of the amount of bid, to be forfeited as liquidated damages in the event that the bid is accepted and the bidder shall fail to promptly enter into a written contract and furnish the required bond.
Any, and all questions bidders may have in connection with this solicitation are to be directed by email only to: Jason Aune, AFLA, email:
For security reasons, you must enable JavaScript to view this E-mail address..
No bidder questions will be addressed after 12:00 pm on Friday, May 30, 2025.
Bid Security in the amount of 5 percent of the amount of the Bid must be submitted through Surety 2000 and accompany each Bid in accordance with the Instructions to Bidders.
The Owner reserves the right to retain the deposits of the 3 lowest Bidders for a period not to exceed 60 days after the date and time set for the Opening of Bids. No Bids may be withdrawn for a period of 30 days after the date and time set for the Opening of Bids.
The successful bidder must be a “responsible contractor.” The term “responsible contractor” means a contractor as defined in Minnesota Statutes, section 16C.285, subdivision 3. Any prime contractor, subcontractor, or motor carrier that does not meet the minimum criteria or fails to comply with the verification requirements is not a responsible contractor and is not eligible to be awarded a construction contract for the project or to perform work on the project. A prime contractor, subcontractor, or motor carrier that makes a false statement under oath verifying compliance with the minimum criteria will be ineligible to be awarded a construction contract on the project, and the submission of a false statement may result in termination of a contract awarded to a prime contractor, subcontractor, or motor carrier that submits the false statement. A prime contractor shall include in its verification of compliance a list of all of its first-tier subcontractors that it intends to retain for work on the project. Before execution of a construction contract, a prime contractor shall submit a supplemental verification under oath confirming that all subcontractors and motor carriers that the prime contractor intends to use to perform project work have verified to the prime contractor, through a signed statement under oath by an owner or officer, that they meet the minimum criteria for a responsible contractor.
The Owner reserves the right to reject any and all Bids, to waive irregularities and informalities therein, and further reserves the right to award the Contract to the best interests of the Owner.
Christina M. Scipioni, City Clerk