Opens June 9 ? North Merchant Street Reconstruction Project Phase 2 ? Specifications

Location: Illinois
Posted: May 26, 2026
Due: Jun 9, 2026
Agency: Effingham city
Type of Government: State & Local
Category:
  • Y - Construction of Structures and Facilities
  • Z - Maintenance, Repair or Alteration of Real Property
Publication URL: To access bid details, please log in.
Opens June 9 – North Merchant Street Reconstruction Project Phase 2 – Specifications Public Works bids
Posted on May 26, 2026
Download

Attachment Preview

PROJECT MANUAL
FOR
N. MERCHANT ST.
RECONSTRUCTION PROJECT – PHASE 2
CDI PROJECT #5727.02
MAY 2026
PREPARED FOR:
CITY OF EFFINGHAM
EFFINGHAM, IL
CITY ENGINEER: LUKE THOELE, P.E.
PREPARED BY:
CIVIL DESIGN, INC.
ROBERT HANFLAND, P.E.
307 E WASHINGTON
EFFINGHAM, ILLINOIS 62401
PHONE: 217-342-2025
DIRECT: 217-340-0347
EMAIL: RHANFLAND@CIVILDESIGNINC.COM
1
TABLE OF CONTENTS
ITEM:
NOTICE TO CONTRACTORS
SPECIAL PROVISIONS
PROPOSAL
BID BOND
NOTICE OF AWARD
CONTRACT
CONTRACT BOND
NOTICE TO PROCEED
PAGE#
3
4 - 21
22 – 25
26 – 27
28
29 – 30
31 - 34
35
2
SPECIAL PROVISIONS
The following Special Provisions supplement the “Standard Specifications for Road and Bridge
Construction of the State of Illinois”, adopted January 1 2022, the latest editions of the “Manual of Uniform
Traffic Control Devices for Streets and Highways”, and the “Manual of Test Procedures for Materials in
effect on the date of invitation for bids which apply to govern the N. MERCHANT ST. RECONSTRUCTION
PROJECT – PHASE 2, City of Effingham, Illinois, and in case of conflict with any part or parts of said
Specifications, the said Special Provisions shall take precedence and shall govern.
LOCATION OF PROJECT
The proposed work for this project is to be located along N. Merchant St. between Flamingo Ave. &
Evergreen Ave. in the City of Effingham, IL 62401. Please see location map on the title sheet of the
construction plans for additional details.
DESCRIPTION OF WORK
The work included in this section consists of the reconstruction of pavement and subbase with other
miscellaneous work.
LIQUIDATED DAMAGES
It is understood and agreed that time is of the essence in the performance of the Contract and that failure
on the part of the Contractor to complete the contract work in the time herein set forth will result in certain
loss and damages to the Owner. Failure on the contractor’s part to complete such work shall be considered
just cause for forfeit of his/her surety bond.
Any Street closures on Merchant Street shall be completed in a timely manner. Any roadway or driveway
pavement that has been removed shall be replaced with permanent or temporary pavement before opening
to traffic. In the case the contractor shall fail or neglect to comply with these requirements, then said
Contractor shall and will pay to the Owner such sums as may be due to him under the terms of the Contract
at the rate specified in the Standard Specifications for Road and Bridge Construction.
In case the Contractor of the work shall fail or neglect to have substantial completion of the project on or
before December 31, 2026 then said Contractor shall and will pay to the Owner such sums as may be due
to him under the terms of the Contract at the rate specified in the Standard Specifications for Road and
Bridge Construction.
Substantial completion shall be defined as all work from back-of-curb to back-of-curb on Merchant Street.
Sanitary sewer, sidewalk, and seeding work may take place after the substantial completion date.
JOINT UTILITY LOCATING INFORMATION FOR EXCAVATORS (J.U.L.I.E.)
This work shall be done in accordance with Article 107.39 of the Standard Specifications except as herein
modified.
If any of the location marks placed by a utility company in conformance with this procedure are destroyed
by Contractor operations, the Contractor shall immediately notify the utility owner and bear the costs of
remarking the facilities at his own cost and expense. Compliance with this special provision shall be
considered incidental to the contract and no additional compensation will be allowed for any costs incurred.
CONTRACTOR RESPONSIBLE FOR LOCATING UTILITES
Before beginning work, it shall be the Contractor’s sole responsibility to coordinate with the utility owners
and to determine the actual location of all such facilities. The Contractor shall also obtain from the respective
utility owners detailed information relative to the location of their facilities and the working schedules of the
utility owners for removing or adjusting them.
4
COOPERATION BETWEEN CONTRACTORS
There is a possibility that other Contractor operations may be ongoing within the proposed project limits at
the same time as the work included in this contract is being performed. The Contractor for this Section
shall cooperate with any other Contractors performing work adjacent to this project in accordance with
Article 105.08 of the Standard Specifications. Any inconveniences or delays caused the Contractor in
complying with this requirement shall be considered incidental to the contract and no additional
compensation will be allowed.
LOCATION OF UTILITIES NOT SHOWN ON PLANS
The Contractor is advised that various underground and surface utilities and structures may or may not be
correctly shown on the plans. Such facilities are shown on the plans for the information of the Contractor,
but information so given is not to be construed as a representation that such facilities will be found or
encountered exactly as shown. Other utilities and structures may also be encountered which are not shown
on the plans. The Owner and its Engineer assume no responsibility whatever in respect to the sufficiency
or accuracy of the information shown in the plans relative to the presence or location of such facilities.
MAINTAIN UTILITIES IN OPERATING CONDITION
The Contractor shall maintain in operating condition all utilities encountered in the work. The Contractor
shall be entirely responsible for all damages to water pipes; electrical conduits; existing drains or sewers;
gas pipes; and poles carrying electrical current, telephone or television lines during the prosecution of the
work and shall be liable for damages to public or private property resulting there from, which amount may
be deducted from any monies due the Contractor for work done. Any damage to existing utilities as a result
of the Contractor’s construction operations shall be repaired to the satisfaction of the utility owner at the
Contractor’s expense, whether or not said utilities are shown in the plans.
Name and Address of Utility Owners
UTILITY
Electric & Gas
Cable TV
Internet
Water & Sewer
Telephone
OWNER
Ameren Illinois
Mediacom
Wabash Communications
City of Effingham
Illinois Consolidated
Communications
ADDRESS
701 S 9th Street
Mattoon, IL 61938
107 S Henrietta
Effingham, IL 62401
14415 US Hwy 45
Louisville, IL 62858
201 E. Jefferson
Effingham, IL 62401
2116 S 17th St.
Mattoon, IL 61938
The location of existing utilities shall be identified by the contractor through the JULIE. Where possible
conflicts exist, the Contractor shall conduct his activities in a manner to protect utilities.
In addition to the requirements of Article 105.07 of the Standard Specifications, the Contractor shall
coordinate his operations with the proposed utility adjustments to minimize delays in construction of the
project.
5
This is the opportunity summary page. It provides an overview of this opportunity and a preview of the attached documentation.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Follow PLA Survey - Brandon Road Interbasin Project - Increment II - Flushing

DEPT OF DEFENSE

Bid Due: 6/16/2026

Follow 183 CES Repair Base Fire Alarm Active Contract Opportunity Notice ID W50S7U-26-B-A001

DEPT OF DEFENSE

Bid Due: 6/18/2026

Bid Identifier Status Broadcast Date Date Due Bid Name Addendum Attachments BID 26-31-0-2026/trn

City of Evanston

Bid Due: 6/23/2026

Project: Hickory Creek and East Interceptor Multisensor Inspection Ref. #: 2987-0726 Type: RFP

City of Joliet

Bid Due: 7/02/2026

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only for convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.